| Nord Mobilizes Crews for Pre-Production Tailings Site Development at Castle High-Grade Silver Mine 
 thenewswire.com
 
 Seasonal production slated for 2026 following gravity-circuit commissioning.
 
 June 16, 2025 – TheNewswire - Nord  Precious Metals Mining Inc. (TSX-V: NTH | OTCQB: CCWOF | FRANKFURT:  4T9B) ("Nord" or the "Company") is pleased to report that the Company has  mobilised field crews and earth-moving equipment to its historic Castle  Silver Mine tailings complex, thereby initiating the first phase of a  staged plan to begin seasonal silver-dominant production in 2026. The  work centres on pad preparation and road upgrades ahead of installing a  gravity circuit that will recover silver along with cobalt, nickel and  other critical metals from multiple legacy tailings deposits across the  63 km² property.
 
 Management Commentary
 
 Frank J. Basa, B. Eng., CEO, commented: “With a modular  unit design, an 80-day permit window, and tailings grades that  household-name mines would envy, the potential to generate cash flow  becomes viable while erasing a century-old environmental liability. It’s  mining in reverse, and our First Nations and local communities will see  the benefits first.”
 
 Key Highlights
 
 - Site works: pads and access roads will be cleared at  the Miller Creek tailings pad and the newly identified Castle West  coarse-tailings pile, both within 400 m of the historic headframe.
 
 - Proven grades: drill and metallurgical test work show  to date: payable silver, as cobalt, copper, and nickel credits add  further value.
 
 - Low-carbon plant design: gravity modules arrive  pre-assembled in ISO containers and sit on crushed-rock pads, no  concrete, rebar or CO2-intensive foundations, allowing for reuse,  removal and full reclamation once processing is complete.
 
 - Fast-track permitting: Ontario's Ministry of Mines has  invited Nord to file its 80-day Recovery Permit application under s.  152.1 of the Mining Act; submission is scheduled for after July 1, 2025.  (See Nord’s June 2, 2025 news release for details on the Ontario  Government’s new recovery permit application process).
 
 - Commissioning timeline: on-site wet commissioning in Q3  and full seasonal processing from July 2026 onward (weather-dependent).
 
 - ESG & First-Nations focus: the program will remove  legacy tailings, proposed back-fill underground stopes with benign  material, and establish long-term environmental monitoring and training  roles in partnership with regional Indigenous communities.
 
 Building on Nord's management established track record of  sustainable development, this initiative represents the Company's most  ambitious environmental remediation program to date, transforming  century-old mining liabilities into both economic opportunity and  ecological restoration.
 
 Current sampling and metallurgical test work has been completed on the tailings  (see Company news release  September 16, 2024)  and will continue during the tailing processing.  Note that this  decision to move forward with processing the tailings has not been based  on a feasibility study of mineral reserves demonstrating economic and  technical viability. Because a feasibility study hasn't been completed,  there's a greater chance that the project might encounter unforeseen  technical or economic challenges during the production process. This  could include issues with the variability in grade within the tailings  deposit, processing methods, or costs, which could impact the project's  potential profitability.
 
 Low-Cost, High-Impact Build
 
 Nord will provide a technical update on metallurgical  performance and circular-economy metrics in a separate release  summarizing its presentation at the MICA Network Tailings Workshop on  June 12, 2025.
 
 About Nord's Processing Infrastructure
 
 Nord operates the only permitted mineral processing and  analytical facility in the Cobalt-Gowganda Camp through its Temiskaming  Testing Labs (TTL) facility. The Company has invested significantly in  gravity concentration equipment and metallurgical expertise, positioning  it as the district's central processing hub for both newly mined  material and historic tailings.
 
 Qualified person
 
 The technical information in this news release was  approved and prepared under the supervision of Mr. Frank J. Basa,  B.Eng., (PEO), director of Nord Precious Metals, a qualified person in  accordance with National Instrument 43-101.
 
 About Nord Precious Metals Mining Inc.
 
 Nord Precious Metals Mining Inc. operates the only  permitted high-grade milling facility in the historic Cobalt Camp of  Ontario, where the Company has established a unique position integrating  high-grade silver discovery with strategic metals recovery operations.  The Company's flagship Castle property encompasses 63 sq. km of  exploration ground and the past-producing Castle Mine, complemented by  the Castle East discovery where drilling has delineated 7.56 million  ounces of silver in  Inferred resources  grading an average of 8,582 g/t Ag (250.2 oz/ton) in 27,400 tonnes of  material from two sections (1A and 1B) of the Castle East Robinson Zone,  beginning at a vertical depth of approximately 400 meters. Note that  mineral resources that are not mineral reserves and do not have  demonstrated economic viability. Please refer to the Nord Precious  Metals  Press Release May 27, 2020, for the resource estimate.
 
 Nord's integrated processing strategy leverages the  synergistic value of multiple metals. High-grade silver recovery  supports the economics of extracting critical minerals including cobalt,  nickel, and other battery metals, while the Company's proprietary  Re-2Ox hydrometallurgical process enables production of technical-grade  cobalt sulphate and nickel-manganese-cobalt (NMC) formulations. This  multi-metal approach, combined with established infrastructure including  TTL Laboratories and underground mine access, positions Nord to  capitalize on both precious metals markets and the growing demand for  battery materials.
 
 The Company maintains a strategic portfolio of battery  metals properties in Northern Quebec through its 35% ownership in  Coniagas Battery Metals Inc. (TSXV: COS) as well as the St.  Denis-Sangster lithium project comprising 260 square kilometers of  prospective ground near Cochrane, Ontario.
 
 More information is available at  www.nordpreciousmetals.com.
 
 “Frank J. Basa”
 
 Frank J. Basa, P. Eng.
 
 Chief Executive Officer
 
 For further information, contact:
 
 Frank J. Basa, P.Eng.
 
 Chief Executive Officer
 
 416-625-2342
 
 or:
 
 Wayne Cheveldayoff,
 
 Corporate Communications
 
 P: 416-710-2410
 
 E:  waynecheveldayoff@gmail.com
 
 Neither the TSX Venture Exchange nor its Regulation  Services Provider (as that term is defined in the policies of the TSX  Venture Exchange) accepts responsibility for the adequacy or accuracy of  this release.
 
 Caution Regarding Forward-Looking Statements
 
 This news release may contain  forward-looking statements which include, but are not limited to,  comments that involve future events and conditions, which are subject to  various risks and uncertainties. Except for statements of historical  facts, comments that address resource potential, upcoming work programs,  geological interpretations, receipt and security of mineral property  titles, availability of funds, and others are forward-looking.  Forward-looking statements are not guarantees of future performance and  actual results may vary materially from those statements. General  business conditions are factors that could cause actual results to vary  materially from forward-looking statements.  The  Company does not undertake to update any forward-looking information in  this news release or other communications unless required by law.
 |