We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Arcon Energy (MIDL Presently) The Ultimate Sleeper

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: TJG who wrote (2770)6/7/1998 9:23:00 PM
From: Ga Bard   of 4142
 
C'mon guys ... read the news release 4/22/98 it is all there ...

Arcon has commissioned Maverick Engineering, Inc. to manufacture its first 100,000-gallon plant for production in Sept. 1998. Milestones for the plant are as
follows:

-- April 24 -- HAZOP study complete (Hazardous operations OSHA is

complete);

May 1 -- Issue process and final installation plans;
May 8 -- Final signoff of engineering requirements;
May 8 -- Issue turnkey contract;
June 26 -- Supervision of detailed design project;
July 3 -- Authorize procurement of all equipment, pumps, etc.;
July 17 -- Assemble unit for completion;
Aug. 14 -- Site installation ready for completion;
Sept. 1 -- Complete commissioning and start up.


The only thing that may have changed is John Sprigs told me last week when I checked on the progress that the 100K was upgraded to a 150K.

Geeze..

GB