PolyMet Updates Capital and Operating Costs Tuesday May 20, 8:44 am ET
Revised Construction Plans Reduce Pre-Revenue Capital Costs and Time Line
Project Development Update Conference Call: May 21 at 10:30 A.M. EDT
HOYT LAKES, MINNESOTA--(MARKET WIRE)--May 20, 2008 -- PolyMet Mining Corp. (Toronto:POM.TO - News)(AMEX:PLM - News) ("PolyMet" or the "Company") reported today that its board of directors has reviewed and approved revised plans and cost estimates for construction and operating costs at its northern-Minnesota copper-nickel-precious metals development-stage project. PolyMet controls 100% of the NorthMet copper-nickel-precious metals ore-body and owns the nearby Erie Plant, located near Hoyt Lakes in the established mining district of the Mesabi Iron Range in northeastern Minnesota.
The revised plans include:
- the sale of concentrate during the construction and commissioning of new metallurgical facilities resulting in a shorter pre-production construction period (under twelve months) and reduced capital costs prior to first revenues ($312 million versus $380 million)
- higher metal prices more than offset higher capital and operating costs, which include substantial additional environmental protection measures
- mine plans (based on copper at $1.25 per pound) reflect the increase in reserves and decrease in stripping ratio reported on September 26, 2007, the use of 240-ton trucks, and owner versus contract mine operations.
Since completion of the Definitive Feasibility Study ("DFS") in September 2006, PolyMet has been focused on providing information to the Minnesota Department of Natural Resources ("MDNR") and other permitting agencies in support of the MDNR's preparation of the Environmental Impact Statement. The MDNR remains on target for completion of the draft EIS at the end of June.
PolyMet has assembled a senior management team with the experience and skills to oversee construction and operation of the plant and mine. The Company has also entered into service agreements with three Minnesota-based engineering and construction firms and has undertaken a detailed review of the construction and development plans in order to optimize these activities. As a result, PolyMet believes its project is operationally and financially more robust and provides additional measures to minimize and mitigate environmental impacts.
KEY POINTS
- DFS-equivalent capital costs increase 36% to $516.8 million
- Updated development plan contemplates:
-- additional $85.1 million in measures to protect the environment, increasing the total capital to $601.9 million
-- the initial sale of concentrate during construction and commissioning of the new metallurgical facilities which requires additional handling facilities included in these totals
-- staged construction reduces pre-production capital costs to $312.3 million (including the additional environmental measures) with most of the additional $289.6 million for construction of the metallurgical facilities expected to be funded from operating cash flow
- Break-even cost of producing copper (on a co-product basis) increases to $1.05 per pound compared with $0.81 per pound in the DFS. Increase primarily driven by higher costs of fuel and general inflation. On a by-product credit basis the cost of producing copper falls to a negative $0.28 per pound.
- Based on three-year trailing average metal prices (the SEC metal price deck) the economics have improved compared with the DFS:
-- After tax internal rate of return increases to 30.6% from 26.7% in the DFS
-- After tax net present value of future cash flow discounted at 7.5% increases to $649.4 million from $595.4 million in the DFS.
-- Average EBITDA in the first five years of operation increases to $217.3 million a year from $175.3 million.
CONFERENCE CALL
PolyMet will host a conference call to discuss the Project Development Update at 10:30 a.m. Eastern Daylight Time on Wednesday May 21, 2008.
Call-in Numbers: Canada: +1 (416) 641-6125 Toll Free: +1 (866) 542-4236 International Toll Free: + (800) 7701-8886
Playback: Canada/International: +1 (416) 695-5800, pass code 3261847 Toll Free: +1 (800) 408-3053, pass code 3261847 CAPITAL COSTS
Since the September 2006 DFS, and on a like-for-like basis, the total capital cost has increased by 36% to $516.8 million. This increase reflects both cost inflation and design scope changes since the DFS, including facilities needed to ship concentrate during the construction and commissioning of the new hydrometallurgical plant.
In addition, PolyMet is anticipating $85.1 million of expenditures on measures to protect the environment, over and above the measures contemplated in the DFS. $76.6 million for mining equipment that was assumed to be provided by a mining contract in the DFS has been incorporated as an operating lease in updated operating costs.
PolyMet has previously stated that it has been reviewing the possibility of selling concentrate during the construction and commissioning of new metallurgical facilities. This staged approach shortens the initial construction period, makes the project less sensitive to the delivery schedule for long lead time equipment such as autoclave vessels, and means that PolyMet can commence operations of the mine, the existing crushing and milling plant, the existing tailings disposal facilities, and the new flotation circuit, before starting the new hydrometallurgical plant.
As a result of the staged approach, the total capital required prior to initial production and sales declines to $312.3 million, which includes $64.7 million of additional environmental safeguards for this level of activity.
Capital Costs (US dollars, millions)
Initial Full Change Concentrate Project from DFS Sales
Definitive Feasibility Study 379.8 138.7 Escalation and other scope changes 137.0 36% 108.9 ------- ----------- Total 516.8 247.6
Environmental measures 85.1 64.7 Total change 222.1 58% 173.6 ------- ----------- TOTAL 601.9 312.3 ------- ----------- ------- ----------- OPERATING PLANS AND COSTS
The overall mining and operating plan remains the same as that defined in the DFS and which forms the basis of the plan being analyzed in the environmental impact statement. PolyMet intends to mine 32,000 tons of ore per day for an operating life of twenty years, processing a total of 224 million tons of ore.
The mine plan continues to be based on the following metal prices: copper - $1.25/lb, nickel - $5.60 per pound, cobalt - $15.25/lb, palladium - $210 per ounce, platinum - $800 per ounce, and gold - $400 per ounce.
Operating costs per ton of ore processed have increased to $13.33 from $11.02 in the DFS reflecting higher fuel, mine equipment, and other consumable costs, as well as general inflation. The cost of mining and delivering ore to the plant is now estimated at $4.31 per ton compared with $3.80 per ton in the DFS. The increase in mining costs has been partially offset by the lower strip ratio, larger mining equipment, and owner versus contractor operation.
The economic analysis is based on SEC-reserve standards, namely the three-year trailing average, which we calculated at April 30, 2008 (the end of our first fiscal quarter.) This price deck is: copper - $2.90/lb, nickel - $12.20/lb, cobalt - $23.50/lb, palladium - $320/oz, platinum - $1,230/oz, and gold - $635/oz. While these prices are somewhat higher than those used on the economic analysis in the DFS, each price is well below current market levels - in the first quarter of 2008, the following prices prevailed: copper - $3.52/lb, nickel - $13.09/lb, cobalt - $46.37/lb, palladium - $441/oz, platinum - $1,867/oz, and gold - $925/oz.
This translates into copper cash costs of $1.05 per pound using a co-product basis to calculate costs, compared with the DFS estimate of $0.81/lb. Taking revenues from the other metals as a deduction against costs, the co-product basis shows a cost of $(0.28) per pound compared with $0.06 per pound in the DFS.
ECONOMIC SUMMARY
Key economic metrics include earnings before interest, tax, depreciation, and amortization (EBITDA) which is projected to increase to $217.3 million on average over the first five years of operations from $175.3 million estimated in the DFS. The net present value of future cash flow (after tax) discounted at 7.5% is estimated to be $649.4 million compared with $595.4 million in the DFS, and the after tax internal rate of return is now estimated at 30.6% compared with 26.7% in the DFS. The table below also sets out the affect on EBITDA of a 10% change in each metal price.
Key Economic Highlights
Update DFS May-08 Sep-06
Operating plan Proven and probable reserves million t 274.7 181.7 Ore mined - life of operation million t 224.0 181.7 Overburden removed (capitalized under site preparation) million t 18.5 - Waste million t 285.3 302.3
Operating costs per ton processed Mining and delivery to plant $/t 4.31 3.80 Processing $/t 8.07 6.75 G&A $/t 0.94 0.46 Total $/t 13.33 11.02
Metal price assumptions (SEC-standard) Copper $/lb 2.90 2.25 Nickel $/lb 12.20 7.80 Cobalt $/lb 23.50 16.34 Palladium $/oz 320 274 Platinum $/oz 1,230 1,040 Gold $/oz 635 540
Economic summary Annual earnings before interest, tax, depreciation and amortization (EBITDA) - average first five years $ million 217.3 175.3 Net present value of future after tax cash flow discounted at 7.5% $ million 649.4 595.4 Internal rate of return (after tax) 30.6% 26.7%
Sensitivity: 10% +/- price equals $_ million in EBITDA Copper $ million 18.6 15.7 Nickel $ million 13.3 9.3 Cobalt $ million 0.9 0.9 Palladium $ million 1.7 2.0 Platinum $ million 1.7 2.1 Gold $ million 0.3 0.5
Copper costs cash - co-product method $/lb 1.05 0.81 cash - by-product method $/lb (0.28) 0.06 SCHEDULE
The MDNR is on track to complete the draft EIS by the end of June 2008, after which it will be formally published in the Federal Register and State EQB Monitor. Completion of the draft EIS will be the culmination of a multi-year effort involving PolyMet, PolyMet's consultants, multiple governmental agencies and an independent EIS contractor. In addition to providing a detailed project description, PolyMet has submitted more than 100 detailed technical reports to assist those preparing the EIS to assess the environmental impacts of the project and to explore ways to avoid, minimize or mitigate the environmental impacts.
Once the draft EIS is published, non-government organizations, government agencies, and the public will have an opportunity to comment during a 30-day state and parallel 45-day federal public comment period. The final EIS will incorporate analysis and appropriate responses to comments, a process that can take several months. The final EIS also has an opportunity for public comment during a 15-day state and 30-day federal comment period. Once the EIS receives a declaration of "adequacy" from the State and "record of decision" from the federal government, the various permits required for construction can be issued. It should be noted that the government agencies that participate in preparing the EIS are the same agencies that will be responsible for preparing the permits that PolyMet will need before the Company can commence construction.
Promptly upon issuance of permits, PolyMet plans to start construction. Detailed construction scheduling shows the mine could deliver ore to the plant in less than a year from the start of construction. As production and sales of concentrate are ramped up, PolyMet plans to complete construction and commissioning of the new hydrometallurgical facilities within approximately eighteen months. Much of the capital costs of the new facilities are expected to be funded from cash flow from the sales of concentrates during this initial period.
MINNESOTA SERVICE AGREEMENTS
PolyMet has entered into service agreements with three Minnesota-based engineering and construction firms which will provide specialized expertise combined with local experience:
Barr Engineering: headquartered in Minneapolis, MN with offices in Duluth, MN and Hibbing, MN, Barr employs approximately 400 engineers and scientists with a strong emphasis on environmental matters. The firm will focus on mine pre-development such as the design and construction of haul roads, stockpile foundations, waste water treatment, overburden stripping, and tailings dams.
Ames Construction: headquartered in Burnsville, MN, the firm is one of the largest heavy civil and industrial design-build general contractors in the US, with expertise in mine development, mine facility construction, landfill construction, and environmental remediation. Ames will initially work with PolyMet and Barr in the detailed planning of mine site development, prior to the commencement of construction upon receipt of permits.
Krech Ojard: headquartered in Duluth, MN with offices throughout the U.S., the firm provided specialist advice to Bateman Engineers in connection with the DFS assessment of the railroad requirements for moving ore from the NorthMet mine site to the Erie plant site. The construction role includes design engineering services for the rail transfer hopper and the new and re-activated rail lines, both between the mine and the plant and rail within the plant site.
Joe Scipioni, President and CEO stated, "Our acquisition of the Erie Plant and our location in an established mining district reduce our exposure to capital cost inflation, which is proving to be a significant challenge for many mine development projects around the world. While we are not immune to rising energy costs and the weakness of the dollar, we believe that we are more competitive on the world stage today than we were when the DFS was completed in 2006."
He continued, "Since the completion of the DFS we have been planning the construction and start-up phase as well as optimizing the overall project. The biggest single change relates to measures to protect the environment. In planning to spend an additional $85 million on environmental protection, we believe that we are addressing concerns of the local community and the permitting agencies."
He concluded, "With completion of the draft EIS scheduled for the end of June, we will be advancing through the public review period and permitting, as well as detailed planning for construction. Everyone is working diligently to make sure that the project moves forward and is done properly."
PolyMet Mining Corp. (www.polymetmining.com) is a publicly-traded mine development company that controls 100% of the NorthMet copper-nickel-precious metals ore body through a long-term lease and owns 100% of the Erie Plant, a large processing facility located approximately six miles from the ore body in the established mining district of the Mesabi Range in northeastern Minnesota. PolyMet has completed its Definitive Feasibility Study and is seeking environmental and operating permits to enable it to commence production. The NorthMet project is expected to require approximately one million man hours of construction labor and create at least 400 long-term jobs, a level of activity that will have a significant multiplier effect in the local economy.
POLYMET MINING CORP.
Joe Scipioni, President |