PBR clones platform P54 to speed up production of Tupi. Cloning strategy started a year ago. P-56 is clone of P-51, in Marlim Sul, na Bacia de Campos. P-54, in its turn replicated P-50, with minimum alterations. The P-62 will "a clone of the clone", because it will be a copy of P-54. And you have to consider that P-51 and P-52, the option of making 2 equal projects to gain scale.
In an interview in Offshore Technology Conference (OTC), in Houston, executive in charge of Pré-Sal da Petrobras, José Formigli Filho, highlighted the reduction in time of delivering rigs: 1) cloning reduces lead time 2) anticipates production and major benefit revenue stream comes earlier "This gives a monstrous impact in the project." he said.
According to Formigli, the total time to construct, a platform, considering project, bidding, detailing and execution is 60 months. With cloning we reduce to 50 months. Sometimes even less.
According to Formigli, the total time to constrcut, a platform, considereng project, bidding, detailing and execution is 60 months. With cloning we reduce to 50 months. Sometines even less. |