| Nice PEA; now, can they raise the relatively minor amount of cash to do a proper FBS and then build a mine? 
 Firestone Releases Positive Preliminary  Economic Assessment for the Torlon Hill Zinc-Lead-Silver Deposit,  Guatemala Showing 97% IRR, 1.2 Year Payback and $45.4 Million NPV
 
 Press Release: Firestone Ventures Inc. – 7 hours ago
 
 finance.yahoo.com
 
 
 
 EDMONTON, ALBERTA--(Marketwire - Mar 6, 2013) -  Firestone  Ventures Inc. ("Firestone" or the "Corporation") (TSX VENTURE:FV)(  F5V.F)   is pleased to announce the results of the Preliminary Economic   Assessment ("PEA") completed on its Torlon Hill Zinc-Lead-Silver Project   located in Guatemala (the "Project") by ProMet Dadi Pty. ("ProMet")   based in Johannesburg, South Africa. The PEA outlines an operation with a   617,000 tonne per year throughput, projecting an after-tax 97%  internal  rate of return ("IRR") and an after-tax US $45.4 Million net  present  value ("NPV") at a 5% discount rate.
 
 Firestone''s plan is to construct the mine and mill facility  that will  produce a zinc concentrate and a silver-rich lead concentrate  that will  be direct shipped to market. Firestone continues to advance  the  social, environmental and technical aspects of the Project that will   allow for the completion of a Feasibility Study and advance the project   to production.
 
 ProMet Study Base Case Highlights
 
 After-tax  and after-royalty Net Present Value ("NPV") at a 5%  discount rate of  US$45.4 Million and an after-tax Internal Rate of  Return ("IRR") of 97%  that assumes expenditure and commissioning happen  in the same year,              Payback of 1.2 years after tax and after plant start-up,             Initial capital cost ("Capex") of US$26 Million over a 12-month development period,             An  initial 5 year mine life from the mining and processing of three   million tonnes at a processing rate of 617,000 tonnes per year from one   open pit operation with a strip ratio estimate of 2.57:1,             Life  of Mine ("LOM") payable production of 106,392 tonnes of  contained zinc  metal, 42,979 tonnes of contained lead metal and 766,800  ounces of  silver from the production of a zinc concentrate and a  silver-rich lead  concentrate,             Estimated Operating Costs for the initial 5 year mine-life are $42.42/tonne,             Commodity price assumptions for base case of $1.00/lb zinc, $1.00/lb lead and $30/ounce silver.
 The  PEA is preliminary in nature and  includes inferred mineral resources  that are considered too speculative  geologically to have economic  considerations applied to them that would  enable them to be categorized  as mineral reserves. There is no certainty  that the estimates of the  PEA will be realized.
 
 Firestone''s President and CEO,  Pamela Strand commented, "The  operation outlined by this PEA for the  Torlon Hill Project indicates  the potential for a fast track to market  approach for our zinc  project. The projected NPV, net cash flows, and  relatively low capital  costs arise from Firestone''s advantages,  including a deposit near  significant infrastructure (including the Pan  American highway, multiple  ports and future hydro power). Our results  to date, coupled with this  engineering study make a compelling case for  expediting the development  of the Torlon Hill Project."
 
 Economic Sensitivities
 
 The economics of the Project are most sensitive to metal   prices, recovery and the grade of the potentially mineable   mineralization. The results of the sensitivity analysis are illustrated   below.
 
 Note: To view the "NPV Sensitivity" graph, please click the following link:  media3.marketwire.com
 
 
   | Financial Sensitivities at Various Zinc Prices (5% discount rate) 
 |   | Price of Zinc (US$/lb)
 | After-tax NPV US$ Millions
 | After-tax IRR |   | $1.05 | $48.0 | 102% |   | $1.00 | $45.4 | 97% |   | $0.95 | $42.5 | 91% |   | $0.90 | $39.6 | 84% |  The  Project has favorable economic potential across a range of  discount  rates and commodity prices. The  operations outlined in this PEA are  projected to generate over $49.4 Million in  revenue after-tax over the 5  years of mine life at an 5% discount rate.
 
 The  metallurgical test work completed by Firestone and used  within this PEA  is preliminary in scope and results in the generation of  the  concentrates from the process proposed. Firstly a zinc concentrate  with  30-40% zinc as carbonate with 45% payable metal and a lead  concentrate  with 60% lead and >300 g/t silver with 95% payable. These  initial  terms have been obtained from metal traders in China using  specific  assumptions although no specific contracts have been  finalized. Costs  in this PEA are CIF Chinese Port and all transport  costs, treatments  charges and fees are included.
 
 The Company has completed  significant drilling of the current  National Instrument 43-101 ("NI  43-101") defined resource whereby 92%  of the resource estimate and the  ore included in this PEA is in the  measured and indicated categories.  The ore body is open in two  directions and this PEA recommended  continued definition drill program  to expand the existing resource. All  past resource estimates have had a  3% zinc equivalent cut off within  the defined pit shell confines. With a  successful definition drill  program and remodeling of the current  resource, Firestone expects to be  able to support increased production  scenarios, which would further  increase the already favorable Project  NPV.
 
 Terry  Tucker, Firestone Director, elaborated on the  preliminary economics of  the Project, "We are pleased with the level of  engineering expertise  behind this  PEA. Through the process we gained considerable insight  into potential  opportunities for further improvement in the already  attractive overall  potential economics, including future zinc  concentrate concepts that  will be validated during the Feasibility  Study phase. The relatively low  unit operating cost of production  coupled with demand for zinc  concentrate by various smelters, means  this operation has the potential  to remain profitable and we are  predicting that the zinc price to remain  strong as both demand and  supply increase in the future."
 
 
   | Project Description 
 |   | Capital Costs | US$ |   | Process Plant | $11,255,074 |   | Infrastructure | $ 2,927,605 |   | Indirect Costs | $ 7,621,414 |   | Project Sub Costs | $21,804,094 |   | Contingency (20%) | $ 4,455,873 |   | PROJECT TOTAL | $26,259,967 |  Mining  at Torlon will be by standard open pit methods using a mining   contractor with a bench height of 5m. Waste haulage distance is   estimated at 500m with ore haulage at 2km. It is assumed that 75% of the   rock will be free digging with ripping and hydraulic breaking and that   the balance of 25% will require light blasting. Based on a 617,000  tonne  per year of ore milled and 1,700 tonnes per day of ore mined, the  cost  estimates for mining ore and waste are $2.47 and $1.80 per ton   respectively with a 2.57 stripping ratio.
 
 The process  plant proposed has been based on a three stage  crushing and screening,  DMS pre concentration, then milling of the DMS  concentrate. The mill  product will then by subjected to differential  floatation to generate  both a zinc and lead concentrate. The  concentrates will then be washed,  dewatered and shipped from the site.
 
 ProMet has  concept designed the location for deposition of  slimes and tailings.  All materials to be mined at Torlon would be  oxidized forms of  mineralization.
 
 Estimated power requirements for the  site infrastructure were  estimated at 3000kW that is envisioned to be  supplied by four 1000 kVA  diesel generating units with a fifth for  standby.
 
 
   | Operating cost summary | 
 | 
 | 
 | 
 | 
 |   | 
 | Total Monthly | 
 | 
 | 
 |   | Item | 
 | Cost (US$) | % of Total | 
 | 
 |   | Fixed costs | 
 | 
 | 
 | 
 | 
 |   | Overheads | $ | 2 353 | 1% | 
 | 
 |   | Sub Total | $ | 2 353 | 1% | 
 | 
 |   | 
 | 
 | 
 | 
 | 
 | 
 |   | Variable costs | 
 | 
 | 
 | 
 | 
 |   | Power | $ | 238 021 | 62% | 
 | 
 |   | Water | $ | 13 129 | 3% | 
 | 
 |   | Reagents | $ | 49 270 | 13% | 
 | 
 |   | Grinding Media (Primary and Secondary Mills) | $ | 7 492 | 2% | 
 | 
 |   | Mill Liners (Primary and Secondary Mills) | $ | 4 911 | 1% | 
 | 
 |   | Crusher Liners | $ | 11 090 | 3% | 
 | 
 |   | Laboratory Costs | $ | 20 899 | 5% | 
 | 
 |   | Maintenance Costs | $ | 38 074 | 10% | 
 | 
 |   | Concentrate Transport | $ | - | 
 | 
 | 
 |   | Sub total | $ | 382 886 | 99% | 
 | 
 |   | 
 | 
 | 
 | 
 | 
 | 
 |   | Total | $ | 385 239 | $ | 7.49 | per ROM |  
 
   | Cash Costs per ton processed | US$ |   | Mining | $ 7.09 |   | Processing | $ 7.49 |   | Slimes | $ 0.12 |   | Fixed | $ 5.09 |   | Off Mine | $12.58 |   | Capex Inc Financing | $ 10.04 |   | TOTAL COST/TON ROM | $42.42 |  Areas for Optimization
 
 The PEA has been successful in achieving the target set by   Firestone to provide a low Capex fast track to market operation. A   series of recommendations have been outlined in the PEA to meet a   potential 18-24 month Project execution timeline. The budget for this   work is $1.2 Million. These areas include:
 
 Resource  optimization to identify additional mineral resources  including  remodeling for a total metal content to include low grade ore,              Remodel the resource using a new block and geological model,             Quantification and design of the upgrades to the existing road access route,             Continue environmental baseline studies, socioeconomic studies and completion of an EIA,             Additional  metallurgical analysis to quantify the key design  criteria to include  but not limited to crushing work, milling  liberation, screening  performance, flotation tests and upgrade testwork  on the zinc  concentrates,             Geotechnical studies, and             Finalize formal off take agreements.
 PEA Report
 
 The PEA was prepared in accordance with the guidelines of   National Instrument 43-101 by the independent engineering firm ProMet   Dadi Africa (Pty) Ltd. ("ProMet") located in Cape Town, South  Africa.  ProMet is a leading full-service engineering firm and has  experience in  the sector that includes the design and construction  supervision of  mining projects in Africa. The complete PEA report will  be filed on  SEDAR and Firestone''s website within 45 days of this news  release.
 
 Qualified Persons
 
 The PEA was prepared under the supervision of Mr. Kevin Van   Wouw, FSAIMM and Mr. Alan Minnaar, Pr. Eng., both independent Qualified   Persons as defined by NI 43-101 and independent of Firestone. Mr. Van   Wouw has reviewed and is responsible for the technical information   contained in this news release. The geological block model and resource   estimate are derived from the NI 43-101 compliant mineral resource   estimate dated December 2008 (  www.sedar.com),   authored by Al Workman, P.Geo. and Kurt Breede., P.Eng., of Watts   Griffis McOuat Limited, Toronto. ProMet has reviewed the 2008 estimate,   and confirms that there is no material change to the resource since its   initial publication and accepts the estimate as its own for use in the   PEA. On behalf of the Company, the technical information in this news   release has also been reviewed and approved by Pamela Strand, P.Geol.,   President of Firestone and a Qualified Person in accordance with NI   43-101.
 
 About Firestone Ventures Inc.
 
 Firestone is a Canadian-based exploration and development   company with zinc-lead-silver and copper projects in Central America and   has been working in Guatemala since 2004. Our main project is the   Torlon Hill Zinc-Lead-Silver Project in Guatemala. The current NI 43-101   oxide resource (see news release 18 November 2008 on   www.sedar.com)   is summarized in the following table and the deposit remains open to   expansion. The NI 43-101 resource used a 3% zinc equivalent cut-off   grade and a 35.5% zinc top-cut.
 
 Torlon Deposit Oxide Mineral Resource - as at March 6, 2013
 
 
  *The total contained metal assumes 100% metal recovery and does not indicate economic viability | 
 | Tonnes | Zinc %
 | Zinc (lbs)*
 | Lead %
 | Lead (lbs)*
 | Silver (g/t)
 | Silver (oz)*
 |   | Measured and Indicated | 1,891,636 | 7.32 | 304,905,997 | 2.41 | 100,294,541 | 14.25 | 866,663 |   | Inferred | 169,705 | 4.42 | 16,502,114 | 1.96 | 7,317,680 | 12.53 | 68,367 |  
 Smithsonite (ZnCO3) is the prevalent zinc mineral  at Torlon,  occurring as a replacement to limestone and resulting in high  grade  mineralization locally exceeding 40% zinc. Other non-sulphide  zinc  minerals are relatively rare and there is no evidence of  deleterious  zinc-clay minerals.
 
 In addition to Torlon, Firestone  also has a large land  position covering a significant portion of the  Central Guatemala Zinc  District with four drill ready targets and over  fifty zinc mineral  occurrences. The land position has excellent  exploration potential and  with systematic exploration could develop as  the world''s next major  zinc district. The common shares of the Company  are currently listed on  the TSX Venture Exchange (symbol FV) and the  Frankfurt Stock Exchange  (symbol F5V).
 
 Additional information about the Project can be found in the technical report filed on SEDAR at    www.sedar.com entitled  "Report  on the Geology, Exploration and Mineral Resources of the  Torlon Hill  ''Oxide'' Zn-Pb-Ag Project District, Huehuetenango,  Guatemala" dated  December, 2008.
 
 This news  release may contain forward looking  statements, being statements which  are not historical facts, including,  without limitation, statements  regarding potential mineralization,  exploration results, resource or  reserve estimates, anticipated  production or results, sales, revenues,  costs, "best-efforts" financings  or discussions of future plans and  objectives. There can be no  assurance that such statements will prove  accurate. Such statements are  necessarily based upon a number of  estimates and assumptions that are  subject to numerous risks and  uncertainties that could cause actual  results and future events to  differ materially from those anticipated or  projected. Important  factors that could cause actual results to differ  materially from the  Company''s expectations are in Company documents  filed from time to  time with the TSX Venture Exchange and provincial  securities  regulators, most of which are available at   www.sedar.com. The Company disclaims any intention or obligation to revise or update such statements unless required by law.
 
 
 Contact:
 Firestone Ventures Inc.
 Pamela Strand, P. Geol.
 President
 Toll Free: 1-888-221-5588
 (780) 428-3476
 info@firestoneventures.com
 www.firestoneventures.com
 |