We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : International Precious Metals (IPMCF)

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Gerald Walls who wrote (2253)2/12/1997 4:50:00 PM
From: ges turner   of 35569
 
From the 2/4/97 news release:

"The tests will be performed independently utilizing a $3 million bulk test pilot plant. The facility was specifically designed for the processing of ores under highly controlled conditions, providing for the fine-tuning and optimization of the recovery process.

IPM and the research facility expect the current round of pilot scale testing to be completed around mid-February. Behre Dolbear & Co., Inc., IPM's mining engineering consultants, in the normal course of their responsibilities, has been instructed to secure a suite of new BRX bulk samples for delivery to the pilot plant facility during the week of February 17th. Bulk sample process procedures for precious metals recovery will then recommence with Behre Dolbear monitoring."

Interpretation:
2/4 thru 2/14 get the $3M plant ready
2/17 thru 2/21 BD deliver bulk samples to plant
2/24 recommence recovery procedures on bulk samples - BD monitoring

It seems as though we have now been given a target date for the final activity of "mid-March".