SI
SI
discoversearch

We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Caussa Capital (formerly Antares) T.CAU

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: leebo who wrote (2642)2/16/1998 9:43:00 AM
From: Brian Warner  Read Replies (1) of 4718
 
theglobeandmail.com

Royal Oak faces possible delay in mine startup

Applies to divert water from B.C. lake

Monday, February 16, 1998
By Allan Robinson
Mining Reporter

Royal Oak Mines Inc. is facing a possible delay in the proposed April startup of its $427-million
Kemess gold and copper mine in north-central British Columbia because of a shortage of water.

In mid-December Royal Oak applied to the B.C. Ministry of Environment, Lands and Parks for
approval to drain two million cubic metres of water from Duncan Lake during February and
March, but approval has not yet been granted.

The water project would require construction of a 3.7-kilometre access corridor for a pipeline and
electric power supply system to allow water pumping.

"It's only a precautionary measure we are taking," Graham Eacott, a spokesman for Royal Oak,
said yesterday. "At this stage it's possible that we won't need the project."

Mr. Eacott said Royal Oak's preliminary figures suggest the pipeline would cost $750,000 and it
would mean a possible delay in the startup of Kemess of only two weeks. He added that Royal
Oak, which is based in Kirkland, Wash., is waiting for the construction permit and expects to
make a final assessment on the water diversion project within two weeks.

In the application for the permit, Larry Connell, the manager of environmental services for the
Kemess project, said the company's consultants estimate that -- based on average levels of
precipitation -- the amount of water required by the mill will exceed the amount of water projected
to accumulate in the mine's tailings pond by 3.6 million cubic metres. That estimate covers water
needs from April, 1998 to March, 1999.

"Realistically, precipitation runoff would not be available to make up this shortfall until mid-May
and June of 1998," Royal Oak told the government. That would necessitate a delay in the startup
of the mine, planned for "on or before April 1," and is not a preferred option, Royal Oak said.

"I can't comment on that [report]," Mr. Eacott said when asked about Royal Oak's filing to the
government.

Royal Oak estimates that the drainage project could reduce the water level of Duncan Lake by at
most 0.8 metres, and would have no effect on fisheries and wildlife.

Environment ministry officials, however, say the scheme potentially could affect another lake and
stream system into which the water would be diverted for use by Royal Oak.

The ministry has completed a technical review and recently passed on the proposal for review by
the Tsay Keh Dene Band, which has retained consultants to study the impact of the proposed lake
drainage on their environment, Peter Freeman, the lawyer for the band, said.

Last June, Royal Oak obtained an injunction permitting the company to remove a roadblock set up
by the band to stop haulage to the mine construction site. The Indian community lives on the
western shore of Lake Williston, about 350 kilometres north of Prince George.

Royal Oak's original plan had assumed that enough natural water runoff would have been collected
in the tailings pond to allow the mine to start up in April, said ministry official Egon Weger.

Royal Oak attributed the water shortage to delays in completing the construction of its dam for the
tailings pond in the fall of 1996 because of a change in location and design.

In its application to the government, filed on Dec. 17, Royal Oak said it intended to start
constructing the pipeline in late December, and begin pumping on Feb. 1.

The water would be siphoned from Duncan Lake to Kemess Lake and then to the company's
tailings pond. Mr. Eacott said the water drained from Duncan would be replenished by the spring
runoff.

The amount of water being drained from Duncan Lake exceeds the total volume of water in
Kemess Lake.

Royal Oak said in its filing that it needs the additional water before it can begin milling operations in
April, in order to "sustain milling operations through to the spring freshet [a rush of spring water
caused by melted snow] in June of 1999."

Royal Oak's consultants, Knight Piesold, said in December that based on its studies, and using
"optimistic projections," the amount of water now available at Kemess mine is about three million
cubic metres less than the amount needed to sustain operations for the first full year.
Report TOU ViolationShare This Post
 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext