We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Santa Catalina Mining SLM.V

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Greywolf who wrote (28)6/14/2001 6:35:35 PM
From: Greywolf   of 30
 
Completion Program - Sneddon,

June 14, 2001 (SLM - CDNX) ... Santa Catalina Mining Corp. (the "Company")
is pleased to announce that the completion program will be commencing
shortly on the Sneddon deep gas well in northern Alberta. The well is
currently cased and awaiting a service rig to begin completion on several
gas zones. The planned program will begin by perforating the main
Kiskatinaw sand which tested gas on an abbreviated Drill Stem Test. The
completion program is designed to determine maximum flow rates and
reserves on this zone.

After the main sand is completed, work will move uphole to
complete 2 additional sands (an upper Kiskatinaw sand for additional
production, and the Bluesky for evaluation). It is anticipated that
production can be brought onstream within 60 days of successful testing.
Due to wellbore and regulation limitations, only 2 sands can be produced
concurrently from any one well. Additional drilling locations are summer
accessible and will be picked immediately following the completion program.