We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Gold and Silver Juniors, Mid-tiers and Producers

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: roto5/23/2007 12:38:15 PM
   of 78427
 
interesting RNG info> an anonymous director (Rio Narcea) reports...

********Rio Narcea starts hot commissioning at Tasiast

2007-05-23 11:35 ET - News Release

An anonymous director reports

RIO NARCEA ANNOUNCES COMMENCEMENT OF HOT COMMISSIONING AT TASIAST

Rio Narcea Gold Mines, Ltd. has successfully completed cold commissioning and has commenced hot commissioning at its Tasiast gold project in Mauritania, West Africa. The company anticipates the first gold pour at Tasiast to take place soon after first fill of plant circuits.

Tasiast is expected to produce 50,000 ounces of gold in the second half of 2007. The deposit will be mined by simple open pit mining, with a standard gold plant flow sheet. The open pit project comprises proven and probable reserves of approximately 12.0 million tonnes at 2.70 grams per tonne (g/t) containing 1.04 million ounces of gold, calculated at a gold price of $491 per ounce. Based upon the current reserves and mine plan, annual gold production for the first eight years of mine life is estimated to average 108,000 ounces per year at a grade of 3.25 g/t and a recovery rate of 94 per cent. The mineralization is open at depth and along strike.