| entamin plc:        Q1 Preliminary Production Results 
 PERTH, AUSTRALIA--(Marketwired        - Apr 9, 2014) - Centamin plc ("Centamin" or "the Company") (LSE: CEY)        (TSX: CEE)
 
 Centamin is pleased to announce preliminary production        results from its Sukari Gold Mine ("Sukari") in Egypt for the quarter        ended 31 March 2014. Total gold production for the quarter was 74,241        ounces, a 14% decrease on the corresponding quarter in 2013 and 19%        lower than Q4 2013. Although gold production was affected by a temporary        reduction in the underground average grade, the first quarter        demonstrated record levels of material movement from the underground        mine and process plant throughput and all areas of the operation have        provided a solid foundation for the year ahead. Production guidance for        2014 remains unchanged at 420,000 ounces gold.
 
 Open pit total        material movement continued well from the previous quarter with a small        increase of 1% to 9,749kt. A decrease in open pit ore production of 26%        on Q4 2013 to 2,325kt reflected a focus on waste stripping activities in        line with the mine plan. The run of mine ore stockpile balance decreased        by 216kt to 1,540kt at the end of the period.
 
 Record quarterly        throughput at the process plant was 1,486kt, a 6% increase on the prior        year period and a 6% increase on Q4 2013, exceeding the nameplate        annualised rate of 5 million tonnes for the fifth successive quarter        with continued high levels of productivity and availability. The Stage 4        commissioning process will progressively lift overall plant throughput        and hence gold production levels through the remainder of the year.
 
 The        primary challenge faced during the quarter was from poor mining fleet        availability within the high grade stoping areas of the underground        mine. Whilst the operation delivered a record 206kt of ore, up 18% on Q4        2013, this limited ability to remotely mine the high-grade stopes        reduced the average mined grade to below planned levels and thus        restricted the contribution to overall production. These problems with        equipment availability were rectified late in the quarter.
 
 Q1        2014 (estimate) Q4 2013 Q1 2013 ----------------------------------------        ------------------ ------- ------- Total Material Movement - Open Pit        (kt) 9,749 9,642 10,550 ----------------------------------------        ------------------ ------- ------- Open Pit Ore Production (kt) 2,325        3,161 2,133 ---------------------------------------- ------------------        ------- ------- Underground Ore Production (kt) 206 174 119        ---------------------------------------- ------------------ -------        ------- Process Plant Throughput (kt) 1,486 1,400 1,402        ---------------------------------------- ------------------ -------        ------- Process Plant Productivity (tph) 745 698 689        ---------------------------------------- ------------------ -------        ------- Gold Produced (oz) 74,241 91,546 87,016        ---------------------------------------- ------------------ -------        -------
 
 Josef El-Raghy, Chairman of Centamin, commented:
 
 "Consistently        high levels of productivity have again been achieved with the process        plant at Sukari, with minimal impact from the Stage 4 commissioning        activities. Although underground performance has impacted Q1 we are        pleased to confirm commissioning of Stage 4 is proceeding as planned,        with Sukari achieving a major milestone towards the end of Q1 as first        ore was fed through the new circuit. We expect plant throughput, and        hence quarterly production rates, to increase through the rest of the        year as commissioning continues. Our forecast 2014 production and the        continued ramp up towards Sukari's long-term target of 450,000-500,000        ounces per annum remain on track."
 
 For more information        please contact:
 
 Centamin plc
 
 Josef El-Raghy, Chairman
 
 Andy        Davidson, Head of Business Development and Investor Relations
 
 (andy.davidson@centamin.je)
 
 +44        (0) 1534 828708
 
 Buchanan
 
 Bobby Morse
 
 Gordon Poole
 
 Gabriella        Clinkard
 
 |