We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : KERM'S KORNER

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Arnie who wrote (9136)2/19/1998 3:08:00 PM
From: Herb Duncan   of 15196
 
FIELD ACTIVITIES / Colt Energy Inc. and Ultra Petroleum Corp.
Drilling Update

AND COLT ENERGY INC.

ASE SYMBOL: COE

FEBRUARY 19, 1998



MONTREAL, QUEBEC--Colt Energy Inc. is pleased to provide an update
of the drilling and completion activity in the Green River Basin,
Sublette County, Wyoming.

Completion work has commenced on the North Lizardhead 11-B well
with completion of the special seismic program. A service rig is
currently on site. The lower sections in the well should be
perforated this week. Hydraulic fracturing will be coordinated
with completion of the Western Gas Resources ("WGR") a pipeline to
the Lizardhead area. Construction of the WGR pipeline has
commenced with completion scheduled for month end.

Ultra has obtained the drilling permit and completed lease
construction on the Horse Creek 14-33 well, the earning well on
the Antelope ranch prospect. Drilling has been delayed by the
federal regulatory authority because of the unusually mild winter
weather, which results in access road problems. The well is not
expected to commence drilling until May, 1998.