We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : ORXX - Orex Gold Mines Corporation

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Ga Bard who wrote (1457)9/1/1999 11:36:00 AM
From: Tim Hall  Read Replies (1) of 2392
 
Gary,

This information is from U.S. Bureau of Mines Information Ciruclar 9143 "Bureau of Mines Cost Estimating System Handbook" These are cost models and although they are over ten years old, they are still valid for comparison.

Mining (100 ton per day, Shrinkage stoping, Adit Entry)

Production Development $7.39/ton
Mining of Ore $30.58/ton
Mine Haulage $ .65/ton
Mine Plant Operations $5.86/ton
Administration $7.44/ton
Total Operating $51.92/ton

It won't matter what milling process is used, these mining costs will be the same.

Flotation Mill (100 Tpd, 1 product)

Comminution(crushing and grinding) $6.29/ton
Flotation $4.29/ton
Solid-liquid separation $5.37/ton
General Operations $3.64/ton
Administration $2.32/ton
Total $21.91/ton

The Haber process will have all of these same costs except for flotation. Instead of placing the ore in vats where the flotation takes place, Haber will place the ore in vats where it will be leached. The Haber process will also require the extra step where the gold is recovered from solution using Merril-Crowe or carbon columns. Everything else will be the same. If we assume that the Haber Process can be accomplished for 1/2 the cost of the Flotation process, the total cost would be $19.76/ton or a cost reduction of 10% in the milling process.

If you look at the combined cost of mining and milling the total cost will be $71.68/ton, or a reduction of 3% due to the Haber process. With gold at $250 per ounce, the operation will need a grade of .29oz/ton just to break even.

Also these costs don't include allowances for reclamtion, or the costs of capital and they have not been adjusted for inflation over the past 10 plus years.

The Haber process would probably be more competative against a heap leaching operation but that is not the kind of test that is going to take place at SMM. Also the ore at SMM is completely different from the ore encountered in the big heap leaching operations.

Tim