We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Formerly About Advanced Micro Devices

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Mani1 who wrote (78083)11/1/1999 2:21:00 PM
From: Yousef  Read Replies (1) of 1576593
 
Mani,

Re: "As they stop wafers starts at 8", they start the upgrade as the
wafers go through the system. So after the wafers clear the litho, they
start replacing the steppers."

This removal, install, and qualification going from 8" to 12" would
take at least 6 - 9 months. Do you really want the Fab "idle"
for that amount of time ?? Mani, please stick to other "non-technical"
areas in which you are qualified ... like "harassing" people. <ggg>

Make It So,
Yousef