We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Formerly About Advanced Micro Devices

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Yougang Xiao who wrote (82610)12/10/1999 1:37:00 PM
From: Shane Geary  Read Replies (4) of 1571928
 
Some Info on DRESDEN Capacity.

I was talking to someone who has spent some time in Fab 30 and got the lowdown on AMD's capacity.

It appears that they currently have 6 steppers installed.

They aim to double this over the next 6 months.

Steppers usually are the bottleneck tools in a well designed fab since lithography contributes 30% to the total equipment cost, but this may not be the case in a fab undergoing expansion. But let's assume they are.

Say these steppers have a throughput of 80 wafers per hour.

At an Overall Equipment Efficiency of 40%, this gives us 32 wafers per hour.

Thus we have

32 wfrs x 6 steppers x 168 hrs = 32k alignments per week

With a 26 mask process (anyone got firmer data?) this gives a total wafer output of 1230 wafers per week.

Many of these will be engineering runs of course, but that is indicative of the overall capacity.

(Note that I don't know if all the steppers are qualified at this stage).

Regards,

Shane

PS Also, a couple of months ago I got word that AMD did have a copper contamination 'event', but got no sense of the magnitude.