We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Pacific Rim Mining V.PFG

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: skynight who wrote (13043)4/28/2000 8:19:00 AM
From: Quickdraw  Read Replies (1) of 14627
 
Refresh of where we are and a rough estimate of what will be happening over the next few months:

First week of May: Road construction to the Luicho property is completed. Construction of access roads/ drill pad sites begins. This is expected to take 4-6 weeks to complete. Drilling will begin after 4 weeks as drill pad construction continues.

May 2-5, 2000: PFG participates at the Fourth International Gold Symposium in Lima Per£. Technical Conference. ekeko1.rcp.net.pe Tom Shrake, Dave Ernst and Peter Dilles will do a 20-30 minute presentation (geological map of the Luicho property will be part of their discussion).

May (more than likely included with the mid-May release): Financing announced

Mid-May: News release regarding construction of drill pads, further surface sampling results and notification of date drilling is scheduled to commence.

End of May: (1-1.5 hour) information sessions provided to investors over a 3-4 day period in Vcr, Cgy and Tor. I will try to get definitive dates.

May 31/June 1: PFG invited to attend NY conference. iiconf.com

First week of June: Drilling begins at Luicho with one RC drill, 2nd drill arrives 10-14 days later and begins drilling (minimum 35-40 300m holes) (minimum 12,000 meters). First results are expected approximately 4 weeks after drilling commences.

June:Analyst tour(s) of the Luicho property begin as drilling takes place.

early July: First drill results and column leach test results are released. Diamond drill arrives to continue drilling.