We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Technology Stocks : Semi-Equips - Buy when BLOOD is running in the streets!
LRCX 139.60-6.2%3:59 PM EST

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Ross who wrote (8834)10/20/2000 9:11:38 AM
From: Ian@SI  Read Replies (3) of 10921
 
1. Many chipmakers have their customers "on allocation" for several of their chip products.

2. It takes 6-9 months to get all the new equipment ordered up to speed in a production environment.

3. There's a 3-5 month lead time for front end equipment; longer for leading edge lithography whereas test equipment is sold on a turns basis.

4. As the cycle heats up, more wafers are pushed out with existing spare capacity. This causes a spurt in the test equipment required. Once existing capacity is consumed, there's a 2-3 quarter pause while new capacity is brought on stream before the next spurt in test equipment orders. Longer delay is required with greenfield fabs.

I don't see any evidence that demand in the back end is falling off because of reduced chip demand. Rather, there's a bottleneck in front end processing giving the backend guys a bit of a respite prior to the next wave of orders as new capacity comes onstream.

IMO,
Ian.