We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Technology Stocks : Thermo Tech Technologies (TTRIF)

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Nicholas P. Acquaviva Jr. who wrote (1)6/27/1996 8:14:00 PM
From: Lionel Gosselin   of 6467
 
Hello Nick

Fort Devins has allocated building and site, permitting is underway
and construction will start when this is complete. The Thermo Master
plant will be the new 300 ton per day engineered design.
Management was in Edmonton today meeting with Lockerbie and Hole to
approve these improvements and determine start dates. Looks like
Richmond construction will start in July as expected. I'll keep you posted.
Brampton and Hamilton plants are operating at increased raw material
supply and are operating at profitable levels.

Thanks, Lionel