DATE:     February 13, 2001
  FOR IMMEDIATE RELEASE:
  Calgary, Alberta -- Centurion Energy International Inc. (TSE: CUX) has released an update of activities on its El Manzala Concession which  covers 420,000 acres in Egypt. Centurion has 100% working interest in this concession and at the present time is concentrating on two core areas,  El Wastani and Abu Monkar. 
  Centurion's plans for Egypt in 2001/2002 focus on tying in gas from the  El Wastani field and undertaking exploration and development drilling to  prove up additional reserves in both of the El Wastani and Abu Monkar areas. 
  Production from the El Wastani field is expected to commence by  mid-year, with initial production from two wells estimated to be approximately 12 mmcf/d of gas and 300 bopd of condensate. Success on any additional  well in the Abu Monkar area when added to the Abu Monkar #1 reserves would  enhance the economics of constructing a pipeline to tie into the national gas  grid. Centurion expects that first gas from the Abu Monkar area will be  on-stream by mid 2002.
  April Construction Start for El Wastani Pipeline
  The tie-in of the El Wastani field is progressing and the project  remains on schedule to tie-in production by mid year. 
  Approvals for the El Wastani Field Plan of Development (POD) and the  Gas Sales Agreement were received in November 2000, allowing the gas  project to move into the construction phase. Line pipe has been purchased for the pipeline and gathering system to tie-in gas from the El Wastani field  to a nearby gas processing facility. Pipeline survey and soil investigation  work is underway and construction of the pipeline is expected to begin in  April.
  Aggressive Drilling Program Planned for 2001/2002
  The drilling program is an aggressive plan which is scheduled to be completed by mid 2002.
  A drilling rig has been contracted to carry out further development and exploration drilling in the El Manzala Concession. The rig, expected to  be available to Centurion in April, has been contracted for three firm  wells with the option to drill four additional wells. 
  The first well will be drilled in the El Wastani area.  East El Wastani  is scheduled to spud in April.  An option well to the south of the East El Wastani field is planned later in the year pending success at East El Wastani.  A second option well, El Wastani #3, is scheduled to spud in  the fourth quarter following a seismic acquisition program which is  currently underway.  
  The second well, Gelgel #1, will be drilled in the southern part of the  El Manzala concession and is scheduled to spud in July.  Gelgel #1 is 20 kilometres to the northwest of the discovery well, Abu Monkar #1. The  third well, Abu Fasada, will spud following completion of drilling Gelgel #1.   Two option wells could be drilled in the Abu Monkar area pending drilling results from Gelgel. Success on any one well when added to the Abu  Monkar #1 reserves would enhance the economics to construct a pipeline to tie  into the national gas grid.  
  Projects in the El Manzala concession, which have progressed  significantly since Centurion became operator, are key to Centurion's strategy to  balance its gas to oil production mix.
  - 30 -
  Certain statements in this press release constitute forward looking statements.  The information in this press release is based on  Centurion Energy's current information, expectations and assumptions, and is  subject to a number of uncertainties and risks that could cause the actual  results to differ materially from those anticipated.  Such risks include, among others, the risk that production flow rate could be materially less  then the flow rate tested and the uncertainty as to the timing of the  commencement of production and continuing production levels.
  For More Information: Said S. Arrata, President and CEO,  or       Barry W. Swan, Senior Vice President, Finance and CFO Tel:  (403) 263-6002 / Fax: (403) 263-5998 E-mail: info@centurionenergy.com Web:  centurionenergy.com |