We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Pastimes : The Engine Room

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Copperfield who started this subject10/9/2001 6:25:23 PM
From: Copperfield   of 23
 
Second-Phase Power Project at Qingshan Starts Trial Operation
Xinhua News Agency ( October 09, 2001 )

HANGZHOU, Oct 9, 2001 (Xinhua via COMTEX) -- The second-phase project of Qinshan Nuclear Power Plant in Haiyan County, east China's Zhejiang Province, was completed and put into trial operation Tuesday.

The trial operation of China's first self-designed and constructed nuclear power plant is a milestone in the development of the country's nuclear power technology, experts said.

The total investment of the second-phase project amounts to 14.8 billion yuan (1.79 billion US dollars). It will send 8 billion kwh of power a year to the east China power grid since June, 2002.

Zhang Yuliang, a nuclear power expert, said that measures had been taken to prevent nuclear leakage in the second-phase Qinshan power plant.

The first-phase project of Qinshan nuclear power plant started operation in 1991.

Copyright 2001 XINHUA NEWS AGENCY