We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : CFGL-Canfibre Group

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: DCBEN who wrote (578)12/17/2001 7:14:22 PM
From: Abuckatatime  Read Replies (2) of 612
 
Maybe I should occasionally visit the company's website. A year-end update from management would be most welcome.

October 26th 2001

Lackawanna Mill reaches 75% of designed capacity levels.

The CanFibre mill in Lackawanna reached and sustained production volumes and quality at the
designed capacity desired for this facility. Reaching this level of production was very satisfying for the
CanFibre mill management team. With the untimely bankruptcy of the projects engineer and general
contractor, Stone and Webster, the CanFibre staff supervised the completion of construction and
installation of the equipment. The project was completed on time and on budget and was followed by a
normal ramp-up. The first starter board was produced in the first quarter followed by production of
AllGreen Premium grade in the third quarter and certification of a fire rated grade at the start of the fourth
quarter.

The plant will now focus on expanding the product line into more value added MDF products including
MR, Lite board and other Fire Rated Products.

canfibre.com