SI
SI
discoversearch

We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Gabriel resources GBU

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: TheBusDriver who wrote (32)2/21/2002 5:07:27 PM
From: I_C_Deadpeople  Read Replies (1) of 41
 
Gabriel recalculates Rosia Montana economics

Gabriel Resources Ltd (2) GBU
Shares issued 81,510,954 Feb 21 close $3.40
Thu 21 Feb 2002 News Release
Mr. Clifford Davis reports
GABRIEL RESOURCES LTD. - BASIC ENGINEERING PHASE OF DEVELOPME ...
Gabriel Resources has provided the following update on its activities.
Optimum plant capacity
Following receipt of two definitive feasibility studies in 2001 on
Gabriel's 80-per-cent-owned Rosia Montana project in Romania, Gabriel began
the process of determining an appropriate plant capacity upon which to base
the basic engineering phase of development.
SNC Lavalin Engineers & Constructors Inc. (SLE&C) was engaged to determine
an optimal plant capacity and concluded that a nominal plant throughput of
13 million tonnes per year was a suitable rate, based upon proven equipment
sizing. Gabriel's subsequent financial analysis indicated that such a plant
capacity provided an appropriate blend of strong project economics and
capital cost parameters. SLE&C has now been engaged to undertake and
complete the basic engineering phase of development by the end of the third
quarter of 2002.
Updated financial analysis
Gabriel has updated its financial analysis of the Rosia Montana project to
reflect a 13-mtpa plant throughput. This analysis suggests that the
economics of the 13-mtpa scenario closely approximate those of the 20-mtpa
case, which formed the basis of the initial definitive feasibility study on
Rosia Montana, while requiring substantially less total initial capital.
A summary of the updated project economics, on a 100-per-cent project basis
and assuming owner mining, is as follows:


Plant throughput 13 Mtpa

Reserves 10.4 Moz gold
52.0 Moz silver

Mine life 16.2 years

Average annual
gold production(1) 504,000 oz

Initial capital
cost (millions) US$253

Working capital
(millions) US$5.3

Sustaining capital
(millions)(1) US$126

Cash operating
costs (1)(2) US$107

Total cash costs(1)(2) US$113

Total production costs(1)(2) US$157

Gold price

US$275 US$300
Internal rate
of return(3) 29.4% 33.8%

Net present
value (millions)
(0% discount)(3) US$911 US$1,102

Net present
value (millions)
(5% discount)(3) US$489 US$604

Net present
value (millions)
(10% discount)(3) US$266 US$341

Payback period
(years) 2.8 2.5

1. Over the life of the mine
2. Per ounce gold net of silver credits
3. 100-per-cent equity basis
Appointment of project manager
Gabriel has appointed Jim Tapp as its project manager responsible for
supervising the development of the Rosia Montana project. Mr. Tapp is a
mechanical engineer with more than 20 years of experience in the
development of international projects.
Project development timetable
Gabriel anticipates that basic engineering will be completed by the end of
the third quarter of 2002, thereby allowing the tender and awarding of an
EPC or EPCM contract to be completed during the first quarter of 2003.
Commencement of construction is currently targeted to begin during the
second quarter of 2003.
WARNING: The company relies upon litigation protection for
"forward-looking" statements.
(c) Copyright 2002 Canjex Publishing Ltd. stockwatch.com
Report TOU ViolationShare This Post
 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext