Nevsun Resources adds Snowden report to Tabakoto study Nevsun Resources Ltd NSU Shares issued 27,257,209 Sep 5 close $1.50 Thu 5 Sept 2002 News Release Mr. Don Halliday reports TABAKOTO PROJECT MINING REVIEWS Nevsun Resources has completion geological and mining reviews conducted by Snowden Mining Industry Consultants of Australia (Snowden) for inclusion in the Tabakoto project final feasibility study. The full study is scheduled to be completed by MDM (Metallurgical Design and Management) of South Africa during September, 2002. The final determination of the preproduction capital cost of the process plant and associated infrastructure for Tabakoto will conclude the feasibility study. Highlights Cumulative cash flow potential of $58-million (U.S.) ($325 (U.S.) gold) from five-year to seven-year open-pit mining operations. Estimated capital cost of $25-million (U.S.) for a 650,000-tonne-per-year operation. Projected annual production of 105,400 ounces gold. Underground mining extensions add $30-million (U.S.) cash flow potential. Development drilling at Segala to provide opportunity for second mining operation. Exploration drilling to commence in October on many targets within the Tabakoto and Segala mining licences. Open-pit operations, five to seven years Initial pit -- five years The optimum projected annual production rate for the Tabakoto project is 650,000 tonnes per year at an average grade of 5.45 grams per tonne gold from an initial open-pit operation with a five-year mine life producing a total of 526,800 ounces (an average of 105,400 ounces per year). The metallurgical recovery applied for the open-pit operation is 94 per cent. This may be followed by a transition to a longer-life sustainable underground operation. The underground mine startup may be delayed should additional surface resources be delineated on the property. The cash cost of production outlined in the Snowden Tabakoto mining review is $187 (U.S.) per ounce for the surface operation, and the indicative preproduction capital cost for the surface mine (including process plant, infrastructure and prestrip mining) is $25-million (U.S.). The capital cost will be finalized when the final process capital is confirmed by MDM later in September, 2002. The cumulative cash flow for the initial five-year-life open-pit mine life is $37-million (U.S.) at $325 (U.S.) per ounce. The initial open pit has been designed as a three-phase operation over five years. The first phase is concluded during the first year of production and takes the pit to a depth of 60 metres. A cutback and deepening of the pit takes production through to the third year at a new pit depth of 140 metres. A second cutback takes the pit to its ultimate depth of 205 metres between years three and five. These three stages of open-pit development have been designed to ensure steady overall mining rates throughout the life of the surface mine to maximize the efficiency of a contract mining fleet. In-pit inferred -- additional four months An additional 220,000 tonnes of inferred resource grading 8.56 grams per tonne gold has been identified within the open-pit profile outlined in the Snowden study. This material will be mined, according to the study, within the waste envelope and only needs to cover processing costs to match against potential revenue. When mined as part of the base case mine development plan, this material has a computed additional cash flow potential of $13-million (U.S.). Potential extension to the pit -- additional 18 months Extensions to the open pit (immediately adjacent to the open pit and along the northern strike) of 978,000 tonnes at 4.2 grams per tonne gold of measured, indicated and inferred material have also been identified (including 73,000 tonnes at 8.48 grams per tonne gold of inferred resource). This is considered to require minimal drilling to raise the level of confidence for it to be included in the mining program as a reserve. The area will be infill drilled in October, 2002. It provides an opportunity for a further increase in cash flow of $8-million (U.S.) in net benefit to the Tabakoto mine. Inclusive of the extensions to the initial open pit, cumulative cash flow would total $58-million (U.S.). Transition to underground operation -- additional six years Snowden has evaluated the potential for future underground operations at Tabakoto to a prefeasibility study level. The underground mining prefeasibility recognizes the opportunity for sustained mining to a depth of 600 metres (the current limit of drill intersections into the Tabakoto deposit) at a mining rate of 6,000 to 8,000 tonnes per vertical metre, provided continued drilling below the pit profile is conducted to enhance current drill intersect density. It is anticipated that such drilling will be conducted during the open-pit mine life and will continue from underground as the underground infrastructure is developed. It is estimated that the underground infrastructure will be developed over a 12-to-18-month period during the last two years of open-pit mine production. The initial capital cost for developing the underground mine is estimated at $7-million (U.S.). A six-year production operation at 6,000 tonnes per vertical metre could provide 330,000 tonnes per year of mill feed at an average grade of 7.5 grams per tonne gold (metallurgical recovery 96 per cent) to a depth of 600 metres producing approximately 75,000 ounces per year. This could provide a cumulative cash flow for the underground production of approximately $30-million (U.S.) at a gold price of $325 (U.S.) per ounce. The structures containing the Tabakoto resources are known to continue to at least 900 metres (the sensitivity limit of the geophysical interpretation). Cumulative cash flows The following table provides the range of possible cumulative cash flows from each stage of future development of the Tabakoto mine. It is presented at a range of gold prices from $300 (U.S.) to $350 (U.S.).
INCREMENTAL CASH FLOW (UNDISCOUNTED NET PRESENT VALUE) (in millions of U.S. dollars except gold price)
Gold price (per ounce) $300 $325 $350
Five-year-life open pit 24 37 49
In pit inferred 12 13 14
Pit extension 6 8 11
Underground 18 30 40 ---- ---- ---- Total 60 88 114
Internal rates of return The incremental impact on the internal rate of return (per cent IRR) for the open pit expanding from the base case, adding in the in pit inferred and then adding in the pit extension, is presented below. The subsequent impact from the underground project as a project extension to the surface mine is also presented.
INTERNAL RATE OF RETURN
Gold price (U.S. dollars per ounce) $300 $325 $350
Five-year-life open pit 19% 29% 38%
Add in pit inferred 24 33 44
Add pit extension 25 35 43
Add underground 30 39 47
The underground aspect of the project could provide an extension to the Tabakoto mine life of up to six years, continuing to use the installed metallurgical processing capacity of the base case open-pit operation. The internal rate of return of the underground operation as a future stand-alone investment using the infrastructure already paid for by the initial surface operations is 98 per cent at a gold price of $325 (U.S.) per ounce -- initial preproduction underground capital of approximately $7-million (U.S.) with a potential annual net cash flow of approximately $6-million (U.S.) for six years of underground operation. Mine financing The company intends to seek debt financing for the Tabakoto project during 2002 in order to be able to commence mine construction early in 2003 for eventual production from Tabakoto early in 2004. The company has an existing banking advisory relationship with Barclays Capital and a financing relationship with ABSA Bank of South Africa. The initial sourcing of capital for the Tabakoto mine will be focused on the open-pit opportunity to the ultimate pit depth of 205 metres. The economic crossover from surface to underground mining will be continuously assessed throughout the period of open-pit mining. The eventual development of the underground operations is expected to be financed from the internal cash flow of the surface mining project. Exploration potential Nevsun's adjoining 23-square-kilometre Segala concession will be a focus for infill drilling to more fully define the known resource for a future Segala feasibility study. Additional ounces defined in a new Segala feasibility study may provide the basis for a second mining operation or may be used as future mill feed to further extend the life or increase the capacity of the Tabakoto mining operation. In addition, there are several new targets to be drilled on the Segala property along the northern extension of the Tabakoto deposit. Running concurrent with the Segala program, exploration drilling will be conducted on several targets within the Tabakoto mining licence which now covers 60 square kilometres in the Kenieba district of western Mali. Some of these targets are the direct extensions of the Tabakoto deposit. This includes the recently acquired Fougala, Koutila and Dioulafoundou gold properties. A diamond and reverse circulation drilling program worth $2.5-million (U.S.) is planned to commence in October, 2002, on the Segala and Tabakoto mining licence areas. John Clarke, Nevsun's president and chief executive officer, states: "The company is extremely pleased to have brought the Tabakoto project to the feasibility stage and it is now better positioned than at any time in its corporate history to develop one of Africa's exciting new mining camps. With the Tabakoto project, the Segala deposit and the exploration potential of its combined 83-square-kilometre landholding, Nevsun is poised to become a significant regional producer and explorer." (c) Copyright 2002 Canjex Publishing Ltd. stockwatch.com |