Here is the release on the financing!ÿ
Attention Business Editors:
KASESE COBALT LOAN FINANCING SIGNED Trading Symbol: BFF TORONTO, July 18 /CNW/ - The board of Banff Resources Ltd. is pleased to advise that its 55% owned subsidiary, Kasese Cobalt Company Limited (KCCL), has signed loan finance for approximately US$66 million with five international financial institutions to fund the construction of the Kasese Cobalt Project. In addition, US$44 million in equity funding from existing and incoming shareholders of the KCCL has been organized. The debt and equity funding for the Kasese Project will be provided as set out below: The Royal Bank of Scotland have arranged a guarantee facility for the ElB loan. An additional US$1.6 million in financing is available from Standard Bank if required. The US$66 million loan finance will be available for draw down once the conditions precedent have been satisfied, which is scheduled during the third quarter of this year. Banff has already advanced to KCCL approximately US$10.6 million as debt which will be converted to equity and invested US$2.1 million as equity. Banff's remaining equity requirement in KCCL of approximately US$12 million is available from its major shareholder, LaSource SAS (LaSource), which owns a fully diluted 74% interest in the Company. Project Engineering
Bateman of South Africa has been appointed the EPCM (engineering, procurement, construction and management) contractor for the Kasese cobalt processing plant. The plant has been designed in three sections by internationally recognized leaders in their field, namely: Signet of Australia bioleaching Krebs of France solvent extraction Bateman of South Africa electrowinning
The 10.5 mega watt hydro electric power plant, which will provide electricity to the project at about US$0.02 per unit, has been designed by Marcon of South Africa, which has also been appointed EPCM contractor for the power plant. The two EPCM contractors will be on site at Kasese in August and it is anticipated that ground will be broken in September. The construction period is scheduled to be 15 months with the first saleable cobalt cathode being produced late in the fourth quarter of 1998. During the first full year of operations it is planned to produce 600 tonnes of cobalt cathode, rising to 1,000 tonnes of 99.8% high quality cobalt cathode in the second year. The plant has the production potential of 1,200 tonnes per annum. The concentrate stockpile that is situated adjacent to the process plant site contains approximately 990,000 tonnes grading 1.38% cobalt. At the projected recovery rate of above 90%, production will average 1,000 tonnes per annum of high quality cobalt for 10 years at an average cash operating cost before financing of less than US$4.00 per lb. Management believes that these costs are unlikely to escalate significantly over time as the project has its own hydro generation station.
The Cobalt Market -----------------
Demand for cobalt is increasing at a rate of about 4% or 1,000 tonnes per annum. The latest Metal Bulletin price for 99.8% cobalt was reported as US$22.00-$23.50 per lb. This has the potential to reduce when large cobalt by-product productions such as from Voisey's Bay come on stream in the early years of the next century. The political situation in the Democratic Republic of Congo (Zaire) remains uncertain and this will make it difficult to secure the capital commitments that will be required for development in this area, which historically has been a major cobalt producer. Accordingly, Banff sees a price window of opportunity of 3 to 4 years after the start of operations during which it is anticipated KCCL will be able to rapidly reduce its US$66 million debt, after which it will have an extraordinary low cost base of $4 per lb plus minimal sustaining capital.
The Project Team ----------------
The key project team leaders at KCCL are taking up residency at Kasese. They include John Aird, the Project Manager, who is a chemical engineer with 23 years experience in the Zambian copper belt including being manager of the Chambishi Division of ZCCM during construction and operation of a 2,500 tonnes per annum cobalt plant. He was also manager of the Nkana Division which had a cobalt production capacity of 6,000 tonnes per annum. Mr. Aird will be assisted by Philip Ray as Construction Manager and KCCL's interface with the EPCM contractors. Mr. Ray has over 28 years experience in the construction and contracting industry and was construction manager on the Chambishi cobalt plant. The chief metallurgist, who will be on site during the construction phase, is Pierre Ollivier. Mr. Ollivier has been with BRGM, a 40% shareholder in LaSource, for over 25 years most recently as Head of Hydrometallurgical Services. He has worked on the Kasese Project since its inception, including all the areas of process technology from laboratory and bench scale testing in France in the early 1990's, pilot plant testing in Kasese in 1994 and confirmation pilot plant testing at the Gencor laboratories in Johannesburg 1995. Mr. Ollivier has lived the metallurgy of this project since 1990.
Kilembe Mine ------------
In parallel with the successful completion of the KCCL financing Banff has continued to study the economic viability of the old Kilembe Mine and its environs. The Eastern open pit area and most of the underground mine have been extensively redrilled. While the feasibility study of reopening the mine and refurbishing the mill and concentrators is not yet finalized, it is unlikely that further work will be done by Banff to reopen the mine in the foreseeable future. This is partially because large scale additional reserves were not identified by Banff's drilling programme and those reserves that do remain are scattered and would be high cost operations. In addition, the existing mill and concentrator would have to be essentially rebuilt. While the results from work done on the old Kilembe Mine itself have been disappointing, Banff's efforts on redrilling the old Kilembe Mine tailings dam have been more than satisfactory. Auger drilling on 30 metre centres of the tailings stocked on the sides of Nyawamba River valley have established 5.158 million tonnes at 0.121% cobalt and 0.181% copper which are probably treatable. Anglo American Research Laboratories are currently carrying out metallurgical testwork on the tailings, particularly with respect to crucial recovery factors. Time Mining of South Africa have been retained to prepare a feasibility study for mining, concentrating and restockpiling the treated tailings, subject to acceptable recoveries being achieved. The resultant concentrates would be similar in grade but somewhat finer in grain size, which could be metallurgically positive, to the concentrate already stockpiled at Kasese. If recoveries are acceptable, the monitoring and concentrating of the tailings will be relatively inexpensive. The Kilembe tailing concentrates could conceivably supply the Kasese cobalt plant with approximately four years of additional feed.
Board and Management --------------------
To reflect the evolution of Banff to a development company, Banff's management team has been strengthened by the introduction of Henri Troch as President and COO. Mr. Troch, who is a metallurgist by training, has spent 19 years in Belgium, Mexico and South America with Sogem Group and Union MiniŠre and the last three years with Magotteaux in Brazil and Mexico. Mr. Troch will spend the majority of his time over the next six months in Uganda assisting with the finalisation of the Kilembe tailings feasibility, which is due to be completed by October 2, and ensuring the construction of the Kasese plant gets off to a clean start. Norman Hardie will stand down as Chairman, but will remain as a non-executive director. Gregory Martyr, who is currently a director will take over as non-executive Chairman. Charles Main remains as CFO of Banff. This has been a very challenging year for the management and shareholders of Banff, but we all can now look forward to the Company becoming a major producer of the highest quality cobalt with the first production expected from the Kasese cobalt plant in late 1998.
Banff Resources Ltd.
Per: Norman D.A. Hardie Chairman
The Vancouver Stock Exchange has not reviewed and does not accept the responsibility for the adequacy or accuracy of the content of this News Release. -30-
For further information: Gregory Martyr or Charles Main at (416) 596-1299, toll-free 1-800-756-9995, or Henri Troch in France at (33) 2-3864-3667 |