SouthernEra's loss drops to $700,000 in Q3 SouthernEra Resources Ltd SUF Shares issued 51,828,400 Nov 28 close $6.19 Fri 29 Nov 2002 News Release Mr. Patrick Evans reports SOUTHERNERA RELEASES THIRD QUARTER RESULTS SouthernEra Resources has provided the following highlights from the third quarter of 2002: SouthernEra joint venture awarded new platinum properties in South Africa, 7.8 million ounces of platinum group minerals (PGM) added to resource base; trading in the company's common shares commences on London Stock Exchange's AIM; drill program defines 1.44-million-ounce mineral resource at Millennium platinum; Camafuca diamond operating joint venture agreement signed; Yamba Lake diamond project yields encouraging diamond results; SouthernEra underwrites Messina Ltd. rights offer; Messina phase 2 feasibility study completed by SRK, upgrading mineral resource to 6.3 million ounces; SouthernEra added to S&P/TSX Composite Index; and Messina platinum commissions phase 1 (Voorspoed) main shaft and concentrator plant. Subsequent to Sept. 30, 2002: additional drilling at Yamba Lake completed; shaft deepening capital costs reduced by 50 per cent following optimization study at Messina; phase 1 mine; Messina rights offer concluded; and company reports progress at Millennium platinum second phase drilling program. Operations update The company's 70.91-per-cent subsidiary (70.42 per cent at Sept. 30, 2002) Messina Ltd. and its wholly owned subsidiary Messina Platinum Mines Ltd., continued to make good progress in developing the phase 1 mine. Equipping of the main shaft to 430 metres was concluded, while development and production at the 150- and 200-metre levels continued through the secondary shaft. Following the recently announced optimization study, the conventional shaft sinking will conclude at the end of November. Development of a decline ramp system below the 350-metre operating level has commenced following completion midyear of the design for the implementation of the mechanized long hole stoping method at the phase 1 mine. By leading with the ramp development to 730 metres, it is possible to raise bore and slipe the phase 1 shaft system. As planned, the phase 1 main shaft was commissioned on Aug. 19 and the construction of the main 90,000-tonne-per-month concentrator plant was commissioned on Sept. 12. The focus of activity has now shifted to development on the 275-, 350- and 400-metre levels to support the buildup of production to 80,000 tonnes per month during the third quarter of 2003 and 120,000 tonnes per month during the second quarter of 2004. At the company's 50-per-cent-owned Klipspringer diamond mine, sinking of the decline was completed during the quarter. Fissure development and mining is now the focus of activity. In the current quarter, tonnage throughput was 61,900 tonnes. Average grade in the quarter was 40 carats per hundred tonnes, yielding 24,900 carats. The company incurred a net loss for the three months to Sept. 30 of $700,000 (one cent per share) on revenue of $900,000, compared with a loss of $800,000 (two cents per share) on revenue of $700,000 in the third quarter of 2001. Cash flow used in operations for the quarter was $3-million (six cents per share), compared with a source of $1.6-million (two cents per share) in the third quarter of 2001. For the nine months ended Sept. 30, the net loss was $4.3-million (nine cents per share) versus $3.8-million (12 cents per share) for the comparable period in 2001. Cash used in operations totalled $4.1-million (eight cents per share) compared with $800,000 (three cents per share) for the nine months in 2001. SouthernEra joint venture awarded new platinum properties in South Africa: 7.8 million ounces of PGM added to resource base The award of three new platinum properties (the Dwaalkop properties) to SouthernEra and its 50-per-cent joint venture partner, Mvelaphanda Resources, increased the PGM resource base at the Greater Messina to approximately 25 million ounces. The newly acquired properties contain both the UG2 and Merensky reefs and are located between phase 1 (Voorspoed) and phase 2 (Doornvlei) projects currently being developed by Messina Ltd., SouthernEra's 70.42-per-cent subsidiary (following the conclusion of the Messina rights issue, see news in Stockwatch on Nov. 11, 2002, this interest increased to 70.91 per cent). Trading in the company's common shares commences on the London Stock Exchange's AIM Trading in the company's common shares on the London Stock Exchange's AIM commenced on Aug. 13, 2002. In support of its application to AIM the company published an AIM admission document pursuant to the AIM rules of the London Stock Exchange. The document includes an independent competent person's report. 1.44-million-ounce mineral resource at Millennium platinum The initial drilling program at the company's Millennium project in Mpumalanga, South Africa, successfully intersected the UG2 reef and defined an inferred resource of 10.03 million tonnes, grading 4.46 grams per tonne (g/t) (5PGE + Au), containing 1.44 million ounces of precious metals. The mineral resource defined is restricted to portions 10 and 11 of the farm Blaauwbank 168 JS only, less than 20 per cent of the prospected area to be drilled. Camafuca operating joint venture approved The council of ministers of Angola approved the operating agreement for project Camafuca and authorized the formation of the operating company, Sociedade Mineira do Camafuca Lda (SMC). Following the incorporation of the operating company and the issuance of the necessary mining licences, it is anticipated that production at Camafuca could commence during 2003. Yamba Lake diamond project results SouthernEra's first drill hole into the Sue kimberlite pipe on the company's 60-per-cent controlled Yamba Lake project in the Northwest Territories of Canada intersected 172 metres of kimberlite yielding a sample of 226.7 kilograms. The sample returned 77 microdiamonds (using a 0.106-millimetre mesh bottom screen) plus 18 macrodiamonds having one dimension greater than or equal to 0.50 millimetre. Subsequent to the quarter a further three holes tested the Sue kimberlite pipe. The three additional drill holes; Y02-09, Y02-10 and Y02-11 yielded sample sizes of 190.95, 147.9 and 151.33 kilograms and returned five, four and six macrodiamonds respectively, having one dimension greater than or equal to 0.50 millimetre (see news in Stockwatch on Oct. 29, 2002). SouthernEra underwrites Messina Ltd. rights offer The Messina Ltd. rights offering consisted of 20 rights for every 100 shares currently in issue. Each right enabled the purchase of one common share of Messina at a price of 60 rands. A total of 2,592,979 rights were issued to the shareholders of record of the 12,964,895 Messina shares issued and outstanding for total proceeds of 155.6 million rands. The rights offer was concluded subsequent to the quarter and the company's ownership in Messina increased to 70.91 per cent. Messina phase 2 feasibility study completed by SRK The company announced the completion of the bankable feasibility study for its Messina phase 2 project on the Doornvlei property by SRK Consulting. The property is 100 per cent owned by Messina, which in turn is 70.91 per cent owned by SouthernEra Resources Ltd. (70.42 per cent at Sept. 30, 2002). An indicated mineral resource of 6.3 million ounces, grading 5.08 grams per tonne (5PGE + Au) has been defined at Doornvlei. The expected operating mine life is 23 years with full production of 120,000 tonnes per month with an annual average production rate of approximately 173,000 ounces of 5PGE + Au. SouthernEra added to S&P/TSX Composite Index SouthernEra's admission followed the quarterly S&P/TSX Composite Index review and the subsequent announcement on Sept. 17 by Standard and Poor's. The index changes outlined in the announcement occurred after the close of trading on the Toronto Stock Exchange on Sept. 20, 2002. Messina platinum commissions phase 1 (Voorspoed) main shaft and 90,000 tonnes per minute concentrator plant Following cold commissioning, the 90,000-tonne-per-month main concentrator plant was handed over for hot commissioning on Sept. 12, nine days ahead of schedule and approximately 12 per cent under budget. Final commissioning occurred on Sept. 19, 2002. |