In the course of preparation for the heating season JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" verified and repaired more than 40% heat conductors
16.06.2004 g. g. Moscow
(translated - unedited)
In 2004 repair campaign in the thermal networks OF JOINT STOCK COMPANY "Mosenergo - Moscow Regional Administration of Power System Management" began on 11 May. At the present moment all repair work are conducted in a strict correspondence with the affirmed graphs.
The yearly plan of the preparation of capital power system for the autumn-winter season includes the required testing of thermal routes. Specifically, by this summer turning offs of hot water in capital users on 21 days are caused. This period, established by government g. Moscow, is necessary JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" for conducting the tests of the conduits of energy company. In the case of detecting the damaged sections their replacement is produced. JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" never disrupted those established it was timetable, and often concluded maintenance in advance of graph. During October according to the results of preparation for the passage of heating season the branches of energy company and entire system JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" as a whole obtains the passport of readiness for the winter.
Today energy company repaired more than 913 km of main thermal networks, which is of about 41% of the planned volumes of repair in the system JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management". 1 830 damages of pipes was revealed and removed since the beginning of the repair campaign. To complete the maintenance of networks and thermal equipment BY JOINT STOCK COMPANY "Mosenergo - Moscow Regional Administration of Power System Management" is planned at the end of August of the present year.
Within the framework of preparation for the autumn-winter load peak 2003-2004. instead of the worn net conduits it will be laid by 70 km of new pipes. Furthermore, in 2004 JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" it plans to lay 12 km of pipes in the polyurethane-foam (PPU) isolation, more reliable and have the prolonged period of operation. Thus, the total length of this type of conduit in the system JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" will increase by 16%.
According to the affirmed plan, energy company conducts the scheduled maintenance of the pumping- pumping over stations. In the second-half of August their complex tests are provided, and then start-up. Furthermore, in the third quarter of 2004 JOINT STOCK COMPANY of "Mosenergo - Moscow Regional Administration of Power System Management" will complete the building Of businovskoy pumping plant for an improvement in the quality of heat supply in the northern administrative division g. Moscow. |