We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Impeach George W. Bush

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: jttmab4/14/2006 8:43:54 AM
  Read Replies (1) of 93284
 
* Intentional Overcharging: Halliburton repeatedly overcharged the taxpayer, apparently intentionally. In one case, “[c]ost estimates had hidden rate factors to increase cost of project without informing the Government.” In another instance, Halliburton “tried to inflate cost estimate by $26M.” In a third example, Halliburton claimed costs for laying concrete pads and footings that the Iraqi Oil Ministry had “already put in place.”

* Exorbitant Costs: Halliburton was “accruing exorbitant indirect costs at a rapid rate.” Government officials concluded that Halliburton’s “lack of cost containment and funds management is the single biggest detriment to this program.” They found a “lack of cost control … in Houston, Kuwait, and Iraq.” In a partial review of the RIO 2 contract, DCAA auditors challenged $45 million in costs as unreasonable or unsupported.

* Inadequate Cost Reporting: Halliburton “universally failed to provide adequate cost information,” had “profound systemic problems,” provided “substandard” cost reports that did “not meet minimum standards,” and submitted reports that had been “vetted of any information that would allow tracking of details.” Halliburton produced “unacceptable unchecked cost reports.”

* Schedule Delays: Halliburton’s work under RIO 2 was continually plagued by delays. Halliburton had a “50% late completion” rate for RIO 2 projects. Evaluations noted “untimely work” and “schedule slippage.”

* Refusal to Cooperate: Evaluations described Halliburton as “obstructive” with oversight officials. Despite the billions in taxpayer funds Halliburton has been paid, the company’s “leadership demonstrated minimal cooperative attitude resolving problems.”

Extracted from: Halliburton's Performance Under the Restore Iraqi Oil 2 Contract
democrats.reform.house.gov