We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Strategies & Market Trends : Ride the Tiger with CD

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: Proud Deplorable1/16/2007 5:55:29 PM
  Read Replies (1) of 312917
 
Adanac 2007 Agenda
-------------

2007 Projection:

- Detailed engineering is priority. As this work moves forward the procurement of "long lead time" major pieces of plant/infrastructure is critical to maintaining the aggressive schedule to complete construction by end of 2008.

- A production decision will be made in the first quarter.

- Receipt of Mining & Environmental Permits are slated for end of first quarter

- Start of construction is expected by mid-year when winter precipitation is clear of the property.

- Major financing is expected to be structured and completed in the second quarter.

- An Impacts Benefit Agreement (IBA) for Taku River Tlingit First Nations is to be completed in the second quarter of the year.

- Approximately 1.5 kg of high grade Molybdenite concentrate product has been produced for samples to potential end users.

- This year's exploration programme will include further work to test the new zone of molybdenum mineralization discovered to the southwest in the 2006 field work.

- An independent review of the geotechnical basis for the tailings impoundment, waste dumps & site water management has been completed and finds no significant errors/flaws in the feasibility work completed.