We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Rat's Nest - Chronicles of Collapse

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Wharf Rat who wrote (5524)2/25/2007 11:10:49 AM
From: Wharf Rat  Read Replies (1) of 24232
 
Eni's Kashagan oil field hit by delays

By Carola Hoyos in London

Updated: 7:10 p.m. PT Feb 23, 2007
Development of the world's most important new oil field will be delayed by a further three years and require almost double the investment initially anticipated, Eni, the Italian oil group operating the field, said on Friday.

Kazakhstan's giant Kashagan oil field will now produce its first oil at the end of 2010 and hit peak production by 2019, according to Paolo Scaroni, chief executive of Eni, Europe's fourth largest listed international energy group.

The field, discovered in 2000, remains the largest to have been discovered in more than 30 years. It is critical for global supplies; today only three of the world's 4,000 oil fields exceed the 1.5m-barrel-a-day production Kashagan is expected to achieve by 2019.

Announcement of the delay and escalating costs comes just two days after ExxonMobil, the world's largest international energy group, scrapped its $15bn natural gas project in Qatar because of runaway expenses.

Cambridge Energy Research Associates, the consultant, estimates costs of major oil and gas projects have risen 53 per cent across the industry because of tight labour and equipment supplies in the past two years.

Kashagan will now need $19bn to develop to the initial stage of producing 300,000 barrels a day by early 2011. That is up from the original estimate of $10.3bn and the $14-15bn guidance given to investors at last year's strategy review. However, the field's peak production would be 25 per cent higher than initially thought, Mr Scaroni said.

Kashagan is Eni's flagship operation. The delay has forced the company to lower from 4 to 3 per cent its three-year production growth target, while the cost increases contributed to the 27 per cent jump in its three year capital expenditure plan to €44.6bn ($58.5bn). Partners, which include ExxonMobil and ConocoPhillips, of the US, Royal Dutch Shell and Total, of Europe, and Inpex of Japan, will also suffer.

A third of the project's extra cost has arisen from the need to move workers' quarters away from deadly hydrogen sulphide hazards. The remainder covers foreign exchange, labour and equipment cost inflation and the expansion of the project. Much of the expense will be borne by Kazakhstan, unless officials decide to rewrite the contract that allows Eni and its partners to recoup their costs.

Sanford Bernstein, the financial services group, earlier this week suggested Kashagan could become as serious a quagmire for Eni as Sakhalin II has become for Royal Dutch Shell. Shell last year lost its majority stake to Gazprom, the Russian gas monopoly, following delays and the admission that the project would cost $20bn, rather than $10bn.

Copyright The Financial Times Ltd. All rights reserved.