Merit Mining Corp. Receives Positive Preliminary Economic Assessment on Its Gold-Copper Greenwood Gold Project
VANCOUVER, April 9 /CNW/ - Merit Mining Corp. (TSX-V: MEM) is pleased to report that a Preliminary Economic Assessment ("PEA") has been completed on the Company's gold-copper Greenwood Gold Project, co-authored by P & E Mining Consultants Inc. ("P&E") of Brampton, Ontario, Roxburgh & Associates Ltd. ("R&A") of Bolton, Ontario, Paul S. Cowley, VP Exploration & Director of the Company, and Merit Consultants International Inc. of Vancouver. The report will be filed on Sedar (www.sedar.com) and the Company's website (www.meritminingcorp.com).
The PEA is based on an initial four year mining plan with production at the rate of 200 tonnes per day for the first twelve months of operation and, following permitting, expansion of production to 400 tonnes per day in the second year.
Project Cash Flow
On pre-production capital expenditures totalling C$13.0 million, assuming 82% equity financing and 18% debt financing through the lease purchase of underground and surface equipment and plant assets, the project has a payback period of 1.3 years. Based on 12-month trailing average metal prices for gold and copper as of November 30, 2006 ($US 595 per ounce gold price and $US 2.98 per pound copper price), the project generates a net pre-tax cash flow of C$29.6 million. This results in a pre-tax IRR of 66 percent and a pre-tax NPV of C$20.6 million at a discount rate of 10%. Smelting, refining and royalty costs are C$21.80 per tonne and site operating costs are C$115.30 per tonne, for total cash operating costs of C$134.60 per tonne. Site operating costs are US$266 per gold equivalent ounce and total cash operating costs are US$311 per gold equivalent ounce. The study has an accuracy of minus 15% plus 30% with respect to estimates of mining, milling, tailings management and associated costs.
Resources The potentially mineable resource was estimated based on P&E's updated September 2006 resource estimates for the Lexington-Grenoble and Golden Crown deposits (NR 06-15). Each stoping area was individually designed using an economic block model of the in-situ mineral resource combined with the mining, geological, and ground support constraint criteria. The objective of this methodology is to maximize the operating cash flow ("OPCF") contribution from each stope. OPCF is defined as net smelter return ("NSR") minus site operating costs ("OPEX"). Each stope included all blocks above a C$10/tonne contribution margin. Low or zero value blocks that must be mined are included as dilution. The NSR calculation was derived from metal prices of US$ 494/oz for Au and US $2.04/lb for Cu, a C$/US$ exchange rate of $0.842; 95% Cu recovery to concentrate; 45% Au recovery to doré, 45% Au recovery to Cu concentrate; concentration ratio 30:1; Cu Smelter Payable of 93.5%; Au Smelter Payable of 95.5%; Au doré payable of 99%; Cu refining charge of US$0.15/lb; Au refining charge of US$5.50/oz; concentrate shipping and smelter charges of US $215/tonne; Mining Cost of $65.00 per tonne mined; Process Cost of $29.00 per tonne processed; and General & Administration Cost of $7.50 per tonne processed. The Greenwood Gold Project has a measured and indicated potentially mineable portion of the resource of 352,000 tonnes, in addition to which there are 86,000 tonnes in the inferred classification as tabled below.
<< Au Cu Tonnes (g/t) (%) ------------------------------------------------------------------------- Lexington-Grenoble Mineable Portion of Resource by Classification ------------------------------------------------------------------------- Measured 4,000 13.18 1.92 ------------------------------------------------------------------------- Indicated 234,000 10.49 1.46 ------------------------------------------------------------------------- Measured & Indicated 239,000 10.54 1.47 -------------------------------------------------------------------------
------------------------------------------------------------------------- Inferred 74,000 4.25 0.66 -------------------------------------------------------------------------
------------------------------------------------------------------------- Golden Crown Mineable Portion of Resource by Classification ------------------------------------------------------------------------- Measured 0 0.00 0.00 ------------------------------------------------------------------------- Indicated 113,000 9.58 0.44 ------------------------------------------------------------------------- Measured & Indicated 113,000 9.58 0.44 -------------------------------------------------------------------------
------------------------------------------------------------------------- Inferred 11,000 4.45 0.27 -------------------------------------------------------------------------
------------------------------------------------------------------------- Greenwood Gold Project Total Mineable Portion of Resource by Classification - Lexington-Grenoble and Golden Crown Mines ------------------------------------------------------------------------- Measured 4,000 13.18 1.92 ------------------------------------------------------------------------- Indicated 347,000 10.19 1.13 ------------------------------------------------------------------------- Measured & Indicated 352,000 10.23 1.14 -------------------------------------------------------------------------
------------------------------------------------------------------------- Inferred 86,000 4.28 0.60 -------------------------------------------------------------------------
(1) Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. (2) The quantity and grade of reported inferred resources in this estimation are conceptual in nature. (3) The reader is cautioned that the preliminary assessment is preliminary in nature, that it includes inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary assessment will be realized. >>
The mineral resources in this news release were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council December 11, 2005.
Mining and Processing Mining methods are primarily conventional underground narrow vein jack leg and slash open stoping and jumbo mining methods in the larger initial high grade stopes at the Lexington-Grenoble mine and narrow vein shrinkage stoping at the Golden Crown mine. A central process plant and tailings facility will be constructed 1.5 kilometres from the Golden Crown mine and 9.5 kilometres from the Lexington-Grenoble mine. The process flowsheet uses conventional crushing, grinding, gravity and flotation to produce both doré and a gold-rich copper concentrate.
Conceptual Mineralization
Merit Mining has identified and modeled contiguous conceptual mineralized targets adjacent to the Lexington Grenoble and Golden Crown Mines. The models have been volumetrically quantified, applied nearest neighbour grades and subsequently volumetrically reduced according to reasonable estimates of risk which finally resulted in a conceptual tonnage figure with grade. This scenario could potentially add 220,000 to 270,000 tonnes grading 8.0 to 9.0 grams Au per tonne and 1.0 to 1.2 percent copper.
Mine life could be extended to six or more years if resources are added from exploration success on the conceptualized targets at the Lexington-Grenoble and Golden Crown mines and the Company's nearby Lone Star deposit.
The reader is cautioned that the consideration or use of mineral potential derived from conceptual mineralized targets, as outlined above, is hypothetical in nature and involves the quantification of mineralization that is as yet unrealized and estimates of such mineralization should not be relied upon. There can be no assurance that any of the mineral potential, in whole or in part, will ever become economically viable. This mineral potential will require further evaluation that the Company's management and consultants intend to carry out in due course.
The PEA includes a C$2.2 million exploration program at the Lexington-Grenoble Mine and Golden Crown Mine to prove up this conceptual mineralization. This exploration, planned over a two year period, is initially from surface and subsequently extended underground from the existing ramp from which access will be gained to the adjacent indicated and inferred resource blocks.
Conclusions and Recommendations P&E and R&A consider that the Greenwood Gold Project operating plan, based on the Lexington-Grenoble and Golden Crown mine potentially recovered resources, has a high probability of economic viability. The project can be quickly brought into production in eight to ten months from project release. The project is highly sensitive to metal prices and moderately sensitive to changes in operating and capital costs. P&E and R&A have made several recommendations in the PEA. The Company should finance and develop the Greenwood Gold Project according to the mine production plan and schedule in the PEA. Exploration programs should focus on expanding the highest potential resources at the Lexington-Grenoble mine and Lone Star deposit. An NI 43-101 compliant resource estimate should be completed on the Lone Star deposit and a mine development, permitting and operating plan should be initiated. The Company is pleased with the report and intends to carry out the recommendations. The Company has recently announced a financing arrangement with Wega Mining ASA, whereby Wega has agreed to make an investment of up to C$21 million in Merit. This major investment will enable the Company to develop the Greenwood Gold Project to production. Mr. Eugene Puritch, P.Eng, of P&E Mining Consultants Inc., Mr. James Roxburgh, P.Eng., of Roxburgh and Associates Ltd, and Mr. Jay Collins, P.Eng. of Merit Consultants International Inc. are independent "Qualified Persons" responsible for the PEA. Mr. Paul Cowley, P.Geo., VP Exploration and a director of the Company, who also co-authored the PEA, is a non-independent Qualified Person. Messrs. Puritch, Roxburgh, Collins, and Cowley have read and approved the contents of this news release.
Merit Mining Corp. Signed "Fred Sveinson" Fred Sveinson, President & CEO
The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
The statements made in this News Release may contain certain forward-looking statements. Actual events or results may differ from the Company's expectations. Certain risk factors may also affect the actual results achieved by the Company.
For further information: Fred Sveinson at (604) 694-2344; For Investor Relations Information contact: MarketSmart Communications, (604) 261-4466 or 1-877-261-4466
cnw.ca |