We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Strategies & Market Trends : YellowLegalPad

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: John McCarthy who wrote (530)10/22/2007 1:57:18 PM
From: dara  Read Replies (1) of 1182
 
I ran across this article today. I don't know anything about PTQ but thought you might be interested.

Petaquilla to ramp up Au output by Mar - Panama

Published: Friday, October 19, 2007 16:20 (GMT -0400)

Vancouverite Petaquilla Minerals (TSX: PTQ) is aiming to reach an "efficient rate" of gold output at its Molejón project in Panama in March 2008, senior corporate development VP Gianni Kovacevic told BNamericas.

bnamericas.com

The first gold pour is expected to occur by January after Petaquilla completes construction of Molejón's plant. The idea is to ramp up to full production by roughly March, he said.

The company is aiming to produce 120,000oz/y of gold at a processing rate of 2,200t/d at Molejón.

Petaquilla also updated Molejón's resource to include 2.76Mt grading 0.35g/t gold or 30,886oz contained in measured resources, 5.21Mt grading 0.34g/t gold or 58,611oz contained in the indicated category and 4.83Mt of 0.34g/t gold or 53,079oz contained in inferred resources.

All the resources were calculated using a 0.3g/t gold cutoff, although the project will also be able to process lower-grade ore, Kovacevic said.

By Pablo Gaete
Business News Americas