We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Gasification Technologies

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Dennis Roth who wrote (1043)8/30/2008 5:59:49 AM
From: Dennis Roth   of 1740
 
RWE Plans Large-Scale Lignite-Fired IGCT Power Plant in Huerth
redorbit.com
Posted on: Friday, 29 August 2008, 12:01 CDT

RWE has announced plans to build a large-scale power plant with integrated gasification combined-cycle and CO2 capture, transportation and storage technology. The new power plant, which will be fueled by local lignite resources, will be constructed on the Goldenbergwerk site in Huerth near Cologne, Germany.

RWE has said that around E2 billion will be required for this integrated gasification combined-cycle turbine (IGCT) plant with its 450MW capacity, pipeline and storage facility. RWE has already committed E1 billion for this purpose.

RWE Dea plans to investigate suitable CO2 storage locations in Schleswig-Holstein. In order to transfer the CO2 from the power plant site in the Rhineland mining district to these storage locations in the north of Germany, RWE Dea plans to build a climate protection pipeline.

Juergen Grossmann, CEO of RWE, said: "We will do everything in our power to ensure this innovative project is now swiftly expedited. With our expertise in clean power technologies, we want to show the energy to lead in this field."