On August 15, 1997, the Kazakhstan State Property Department unilaterally canceled the Management Contract with Gold Pool in disregard to the terms and guarantees contained in the contract. The principle reasons stated by the government for the cancellation were arrears in payments of wages and debt, decreased production, and social tension in the mining villages. The government refused to recognize events of force-majeure and non-fulfillment of the Proprietor's contractual obligations by the State Property Department leading to the force majeure events which are described below.
Gold Pool had been operating the mines of state-owned JSC Kazakaltyn for 17 months and invested over $18 million in the process. Management of Gold Pool believes that the reason for cancellation of the contract had more to do with the government expectation that Gold Pool would continue to carry more of the responsibility for social services. Gold Pool is optimistic that a solution could be found to jointly revive this gold producing Combinat of JSC Kazakaltyn.
Contractual rights and obligations of the Managing Company
In accordance with Articles II, III and IV the Managing Company's objective was to stabilize production by restoring all producing Properties to an acceptable level of profitability; creating a favorable financial situation, and developing effective marketing contracts and a final products sales network. To do so, in accordance within Paragraph 3.2.4, the Managing Company had the right to "suspend mining, processing and other operations which are not economically viable". During the entire period of management the "Managing Company shall have an exclusive right to Purchase the State share of the Enterprise." All capital contribution into the Enterprise "shall be applied in reduction of the Purchase Price for the State Share of the Enterprise."
Investment Commitments Under the Contract
Paragraph 5.4 of the Contract stipulates that the investment for the second phase of financing (ending on August 10, 1996) is the amount of not less than US $5,000,000 and the investment for the third phase of financing (ending on April 10, 1997) is the amount of not less than US $5,000,000. Accordingly, Gold Pool was to invest not less than US $15,000,000 by April 10, 1997, being the end of the third phase of financing. However, Gold Pool has actually contributed a total amount of US $18,697,788, which is US $3,697,788 more than the total investment required by the Contract.
ASSET DESCRIPTION
Key assets include three gold mines - Aksu, Bestube, and Jolymbet, located near Stepnogorsk in the Akmola Oblast of north central Kazakhstan. The Company also had five minor gold producing properties. In addition to its mining operations, Gold Pool has license to and is exploring a large exploration license consisting of two properties covering approximately 12,500 square kilometers.
At the time of assuming management by Gold Pool, all the mines and processing plants of state-controlled JSC Kazakaltyn were shut down and the workers had not been paid for up to six months.
Due to neglect for several years before closure, the Combinat was operating in far less than optimal conditions, which resulted in a gradual deterioration of equipment.
STABILIZATION
As part of its Management Agreement, in August 1996, Gold Pool delivered a comprehensive report to the Ministry of Industry and Trade proposing a two-stage revival of the mines. Stage I would cover the first two years while Stage II would carry on for a minimum of eight additional years.
Defined costs during Stage I included U.S. $3.5 million for back wages, due diligence and engineering and an additional U.S. $7.0 million for plant refurbishment, inventory costs, social issues and back wage costs and U.S$5.0 million in general operations costs to bring the mines back to 1995 production levels. The company expected the mines to be marginally economic during Stage I with all production revenue during this stage to be returned to the enterprise.
Gold Pool's August 1996 report stated that the transition into Stage II could only be justified if both start-up and Stage I were successful. This meant that Gold Pool needed assurance that the mines could be sustained on their own generated revenues. Once this was certain, the Company intended to undertake a feasibility study and then invest U.S. $30 million for mine and plant improvements to substantially increase reserves and annual production to 250,000 ounces per year at internationally competitive costs. Throughout its involvement with the mines of Kazakaltyn, Gold Pool had to deal with a whole range of serious problems often not related to production. Power shortages was one of them. The Company could never depend on the power companies for continuous power despite the Company making advance payments for power on a regular basis. In the latter months of the contract the power price increased by 175%. Power outages continued and endangered the lives of the underground workers and caused substantial losses of production.
For entire period of its operations Gold Pool was not able to resolve the issue of back debt in excess of US $30 million accrued by JSC Kazakaltyn Combinat prior to Gold Poll's take over. Although the Management Contract clearly states that the company is not responsible for the back debt of the former operation, Gold Pool was constantly harassed by old creditors of JSC Kazakaltyn. Creditors were constantly attempting to strip the mine of its equipment and supplies.
Gold theft and physical violence was an ever increasing concern to Gold Pool. With the exception of the assistance of a small, private security force retained by Gold Pool, there was very little else Gold Pool could do to safeguard produced metals and protect the safety and security of employees of the mines. The Ministry of Industry and Trade was informed of this concern of Gold Pool by a letter of October 28, 1996 but no assistance was offered.
MINE OPERATIONS
For the first few months after undertaking the Management Contract Gold Pool was required to defer the start of operations until a satisfactory repair was completed. On of the immediate Gold Pool's big concerns was the payroll confusion at JSC Kazakaltyn. By December of 1996, only 7 months from signing the contract, Gold Pool had succeeded in restarting the mines and exceeded former annual production levels for the past 10 years. The production was attaining the rate of 150,000 ounces (4.8 mt) per year at costs less than $300 per ounce before the Balkhash smelter closed only a month after.
Because of the long established production process at the mines, an outside smelter was required for intermediate and final processing and refining. In September 1996 Contract No. 614AO/96 was signed with JSC Balkhashmys smelter to process 5,000 tons of concentrates per month on a tolling basis for one year. In the event of failure of the Combinat, the contract required sufficient notice and return of the concentrates and gold products. Concentrates were continuously shipped to the smelter from October 1996 to January 1997. Because of the 60-day processing period the first out turn was due in January 1997.
In January 1997, Gold Pool was notified by Balkhash smelter that it had to drastically cut its capacity of processing Gold Pool concentrate. A few weeks later the smelter stopped production completely and was declared bankrupt by the government. Disregarding numerous demands by Gold Pool, the smelter refused to return 256 kilograms of processed gold worth US$3.0 million and/or the concentrates shipped from the mines, as required by the contract. Instead, the smelter redirected 63 kg of gold in the electrolytic sludge belonging to Gold Pool and valued at US$700,000 to Leninigorsk Combinat. These above funds were vital for the payment of mine wages and suppliers. The closure of the Balkhash smelter and the long delay in receiving funds from gold sales factored into the decision of Gold Pool to immediately suspend operations at the Aksu and Jolymbet mines and place them on care and maintenance status, as permitted in article 3.2.4 of the Management Contract. The Ministry of Industry and Trade was informed of this decision in writing on January 19 and again on February 5, 1997. The workers were neither fired nor laid off but were placed on administrative leave. This enabled Gold Pool to pay all the miners a monthly allowance until the mines are restarted along with paying maintenance costs pending receipts for gold production at Balkhash and commissioning of a new process facility on site to replace the smelter.
Production at Bestube mine was maintained until June 1997. The flotation concentrate was stockpiled for later treatment. This production however was not sufficient to carry the Bestube mine costs and the cost of flotation product inventory. The mine continued production at a rate of 500 metric tons per day. Between 30 to 70 kg of gravitation gold was produced per month. After several months of negotiations with Samsung and their subsidiary Zhezkazgantsvetmet Combinat and with personal involvement of Mr. D.T. Duisenov - then Deputy Prime Minister of Kazakhstan , on June 16, 1997, Gold Pool finally succeeded to sign a new gold concentrate sales contract with Samsung for a one year period. Gold Pool had almost 4,000 tons of gold concentrates accumulated over a six month period at the mines in need of processing. The terms of the contract were far less favorable for Gold Pool than those of the former smelting contract with JSC Balkhashmys. However, on July 4, 1997, the contract was unilaterally cancelled by Samsung for ostensibly economic reasons.
Starting from June 1997, the mines were hit by a severe power outage. The local power provider Akmola Tselinenergo company formally informed Gold Pool that power would be kept on the emergency level only for up to two months. Faced with the inability to process the concentrates, the discontinuation of power supply, and the lack of production revenues, Gold Pool had no economic alternatives but to suspend operations at the Bestube mine.
For the period from April 10, 1996 to August 15, 1997, the volume of gross production comprised the sum of almost US$7.5 million. A total of 656.40 kg of gold was produced, including 444 kg in concentrates and 212.4 kg in gravity gold (sponge). Up to 3,000 employees were on the payroll at the mines, and a number of independent mining, maintenance, supply, and other service companies were engaged on contracts. In October 1996 a "Gold Tail" joint venture agreement was signed for this purpose between Gold Pool and Globa Kazakhstan. A recent study determined that heap-leaching the tailings (ore concentrate stockpiled at the mine sites after higher grade concentrates are extracted) could contribute an additional 1.5 metric tons of gold at low production costs.
GOCERNENMENT RELATIONS
After the Balkhash crisis the company was missing up to US$3 million of production capital from the gold held up at the smelter. In order to resolve the issue, Gold Pool representatives had numerous meetings with high ranking government officials, among them Mr. H.A. Ospanov - former Minister of Industry and Trade, Mr. U.Y. Shukeev - Minister of Economy, Mr. A.S. Yesimov - First Deputy Prime Minister, Mr. D.T. Duisenov - Deputy Prime Minister. Gold Pool also held negotiations with Executives of Samsung, new managers of the Balkhash smelter. Only in June 1997 could the company return less than half of its missing gold (107 kg less smelting and refining charges). The gold up to the value of US $1,500,000 has still not been returned.
The illegal action by one of the biggest Kazakstani producer and the inability of the government of Kazakhstan to completely resolve the situation dissuaded investors of Gold Pool and Kazakstan Goldfields Corporation, on whose support the company, like all Western companies operating in Kazakhstan, heavily depend.
In order ensure investors' financial commitment to the project and secure funds for production needs and for the construction of the CIP plant, in April 1997 Gold Pool submitted a formal application for privatization with the Department of Industry and Trade of the Ministry of Economy of the Republic of Kazakhstan, the department that had been responsible for supervising the execution of the Management Contract. The Management Contract provides the Managing Company with an option to purchase the State shares at any time. In the letter dated May 4, 1997, # 01-556 (signed by Mr. Ospanov H. A.), the Department of Industry and Trade concluded that, based on the balance sheets, Gold Pool had fulfilled its obligations under the Contract.
The letter was forwarded to the Department of Management of State Property and Assets for final approval. Instead of an anticipated privatization decree, on May 19, 1997, the State Property Committee issued a letter signed by Mr. S.S. Kalmurzayev, stating its intention to unilaterally terminate the contract.
No well founded reasons of the violation of the Contract were given. A response was sent from Gold Pool on June 4, 1997, which reiterated the terms of the Management Contract and rejected allegations of non-fulfilment of its terms.
The Managing Company received an acknowledgement of their right to exercise the privatization option from Mr. Kalmurzaev of the Department on June 6, 1997, Letter # 40-1/1940. Since that time, a number of excuses for not permitting the privatization of the Enterprise were put forward by the Department. Pursuant to Article 12.3 of the Contract, the Department is not entitled to terminate the Contract after it has received notice that the Managing Company wishes to purchase the State shares of the Enterprise.
The Department, acting through Mr. Kalmurzaev, did not provide the Managing Company with a proper notification listing contractual defects and requesting correction of those defects. The Department also did not fulfil its obligation not to hinder the performance by the Managing Company of its rights, when it did not take into account the force majeure events. The Department only noted the figures on decrease of the volumes of production without taking into account the reasons.
Several letters (April 21 and May 19, 1997) were also forwarder to Mr. S.M. Yesimov - First Deputy Prime Minister and Executive Director of the State Committee for Investments.
The Committee acknowledge Gold Pool's complaint, but did not express any particular interest about the issue and did not provide any assistance whatsoever in resolving the dispute. Gold Pool's legal counsellors, Macleod Dixon, contacted the Department of State Property on Gold Pool's behalf in writing on July 30, 1997, outlining Gold Pool's disagreement with the position of the government and offering a possible resolution of this crisis situation. Nevertheless, On August 15, 1997, Department of Management of State Property issued Decree No. 257 unilaterally cancelling the Management Contract with Gold Pool in violation of the terms of the Contract and disregarding demands and explanations of Gold Pool. On September 1, 1997, Gold Pool registered a formal Demand letter with the Ministry of Finance and the Department of State Property of Kazakhstan stating its strong disagreement with the government actions and proposing to settle the issue before arbitration procedures are initiated. Macleod Dixon legal firm was engaged to represent Gold Pool in a possible litigation.
Gold Pool is currently awaiting a response from the government of Kazakhstan. |