Baley gold project feasibility study completed Armada Gold Corp AAU Shares issued 79,252,868 Oct 28 close $0.50 Wed 29 Oct 97 News Release Mr Derek Fisher reports A newly-completed independent feasibility study has concluded that the first phase of the Taseevskoe portion of Armada's Baley gold project in southeastern Russia is capable of producing an average of 220,000 ounces of gold a year for an initial period of 10 years. Kvaerner Metals Davy of Toronto, which conducted the feasibility study, estimates that the cash operating cost will average US$166 an ounce. Kvaerner found that the project is technically and economically feasible to develop. A particularly favourable aspect of the project is that higher-grade ore is to be produced in the first two years of operation. Production in the first year is estimated to be 267,000 ounces and in the second 324,000 ounces. The operating cost would be US$140 an ounce in the first year and US$120 an ounce in the second year. The company confident that it has identified a viable, economically sound project with a rate of return that will support financing for the development. Discussions have commenced with various institutions that have shown interest in providing equity and debt financing for the project, and the company has retained Levesque Beaubien Geoffrion to advise it on maximizing shareholder value. Armada Gold, through its Russian-subsidiary, Balgold Limited, has an 85% interest in the Baley gold project in the Chita region of Siberia. Kvaerner based its study on an open-pit mine with a stripping ratio of 7.2 to 1, with the ore to feed a processing plant rated at 1.75 million tonnes of ore per year. The first 10 years of mining will provide ore to the plant at an average grade of 4.5 grams of gold a tonne. The mine plan will result in an additional 10.7 million tonnes of low-grade ore being stockpiled in the first 10 years, which will be available for subsequent processing. Armada Gold believes that the pit shell also may capture additional ore, as it is likely that a portion of the inferred resource will report as ore during mining. The Kvaerner study did not attempt to take this into account. Armada Gold is also investigating the possibility of augmenting the Taseevskoe mill feed with higher-grade ore from the satellite ore bodies at Baley that are held by Balgold. Kvaerner's work has demonstrated that processing of the Taseevskoe ore will result in 87% gold recovery using conventional gold processing technology of crushing, grinding and making a concentrate by flotation. The concentrate will be pressure-oxidized and the gold in the oxidized concentrate and in the flotation tailings recovered in a carbon-in-leach circuit. The Kvaerner study includes a detailed plan for development of the project which estimates that the first gold can be poured within 28 months of the decision to proceed. The key parameters of the first phase development of Armada Gold's Baley gold project are:
Mineable Reserves (.88 g/t cut-off)
Proven 9,200,000 t at 5.21 g/t Au
Probable 19,000,000 t at 2.26 g/t Au
Stripping ratio 7.2:1
Plant throughput 1,750,000 t per year
Plant cut-off grade 2.0 g/t
Gold recovery 87%
Average annual gold production 220,000 ounces
Mine life 10 years
Low-grade stockpile (at end of 10 years) 10.7 million t at 1.14 g/t
Preliminary Economic Indicators (Pre-Tax)
Cash operating cost per tonne US$20.94
Cash operating cost per ounce US$166
Total cost per ounce US$243.00
Capital cost - mill US$122.4 million
Mining fleet US$34.1 million
Pre-strip US$12.5 million
Net present value
Dis- US$350 US$375 counted oz oz rate
(over 10 yr mine life) 0% 220.1 275.1 5% 117.2 156.1 10% 55.1 83.6 Payback period 4.2 yr 2.9 yr
IRR (after tax leveraged US$375) 24.0%
Armada has concluded a tax protocol with the Chita region administration and is currently finalizing appropriate contracts with Russian banks and authorities to enable its gold production to be marketed in Russia and abroad. Armada also has a 49% interest in the Erdmin joint venture in Mongolia, which is producing at the rate of 11 tonnes of copper cathode a day from a demonstration plant and is studying the feasibility of an expansion to 60 tonnes a day. (c) Copyright 1997 Canjex Publishing Ltd. canada-stockwatch.com |