We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Technology Stocks : Cymer (CYMI)

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Tulvio Durand who wrote (11389)12/11/1997 4:49:00 PM
From: Yakov Lurye  Read Replies (2) of 25960
 
Tulvio,

Let us asume for simplicity that steppers work non-stop and that the delay for carrying wafers between steppers is negligible. In a day stepper #1 will produce 24x80 = 1920 half-printed wafers, stepper #2 can start working after a nomimnal delay of 1/80 hour (time for stepper#1 to produce the first wafer) and will be able to finish 80 X(24-1/80) = 1919 wafers. This is very close to 80 finished wafers an hour.

Am I missing something?

Regards,

Y.