We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Canadian Diamond Play Cafi

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Natedog who wrote (9501)4/19/2015 7:28:00 PM
From: Natedog  Read Replies (1) of 16206
 
MTX

Permit to Take Water 3481-9F6LJQ was issued March 27, 2015 for the initial filling of the Fine Tailings Settling Pond for the temporary bulk sample plant at the U2 project site. This permit will expire on March 27, 2020.

Source Name: Fine Tailing Settling Pond
Source Type: Pond - Dugout
Purpose: Industrial
Maximum rate per minute (Litres): 694 (estimated seepage)
Maximum number of hours of taking a day: 24
Maximum volume per day (Litres): 1,000,000 (estimated seepage)
Maximum number of days taking in a year: 30
Earliest calendar date of taking (mm/dd): 01/01
Latest calendar date of taking (mm/dd):12/31