We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Strategies & Market Trends : Dino's Bar & Grill

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Goose94 who wrote (12396)7/9/2015 9:31:36 AM
From: Goose94Read Replies (1) of 203382
 
Mountain Province Diamonds (MPV-T) July 7, '15 is pleased to announce that development of the Gahcho Kué diamond mine is progressing according to plan and budget with the overall project approximately 62 percent complete at the end of May, 2015. Key areas of focus are continued dewatering to expose the kimberlites, the placement of concrete foundations and the erection of steel superstructures of the major facilities. A key milestone is to ensure that the process plant building is enclosed by October 2015.

Patrick Evans, Mountain Province President and CEO, commented: "We're on track for first production in H2 2016 and are currently making arrangements to be in a position to receive and sell our 49 percent share of diamond production. These arrangements are expected to be in place by the end of 2015."

There are currently approximately 500 employees and contractors on site at Gahcho Kué and this number is expected to peak at approximately 650 during the third quarter of 2015. During production there will be approximately 400 employees at Gahcho Kué. The project Operator, De Beers Canada, maintains a strong focus on a robust safety record with fifteen consecutive months without a lost-time injury.

Mountain Province Diamonds is a 49% participant with De Beers Canada in the Gahcho Kué diamond mine located in Canada's Northwest Territories. Gahcho Kué is the world's largest and richest new diamond mine.

The Gahcho Kué Project consists of a cluster of four diamondiferous kimberlites, three of which have a probable mineral reserve of 35.4 million tonnes grading 1.57 carats per tonne for total diamond content of 55.5 million carats.

A 2014 NI 43-101 feasibility study report filed by Mountain Province (available on SEDAR) indicates that the Gahcho Kué project has an IRR of 32.6%.

The Gahcho Kué diamond mine is expected to produce an average of 4.5 million carats a year over a 12 year mine life.

Qualified Person

This news release has been prepared under the supervision of Carl G. Verley, P.Geo., who serves as the qualified person under National Instrument 43-101.

Mountain Province Diamonds Inc.,
Patrick Evans, President and CEO,
161 Bay Street, Suite 2315,
Toronto, ON
M5J 2S1,
Phone: +1-416-361-3562,
E-mail: info@mountainprovince.com
http://www.mountainprovince.com
Report TOU ViolationShare This Post
 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext