Drilling is not enough for veining. So we had to trench, trenches 12-15 feet wide, 15-20 feet deep , some as long as 100 feet and spaced every 50m to get an idea of how to quantify the structures. Drilling was a waste of money as it turns out. If you have a vein on surface and you angle drill an intersect it at 40m, thats not enough, you have to prove its a vein with depth. So trenching, lots of it.
What we will put out in next 2 months is a 43-101/PEA/PFS/BFS combined.
Costing for trucks, plant, equipment, Income from Marble, aggregate, graphite. Building repair costs, tailings pond refurbishment to 2015 standards etc CAPEX for entire project, which I am estimating at $15million total. 43-101 I am saying rolling resource of 15,000 tons concentrate and silently hope for 20K
West side..... 560,000 tons of concentrate. and I am sticking with those numbers.
IT ALL TAKES TIME....1.5-2 months to go. |