We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Non-Tech : Alternative energy

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: Eric10/9/2017 7:56:08 PM
   of 16955
 
Renewable energy

Mega-battery plant to come online in Sheffield

Facility run by E.ON, to be followed by many more, will help UK grid cope with fast-growing amount of renewable energy


The storage facility in Blackburn Meadows, Sheffield, with a combined heat and power plant in the background. Photograph: E.ON

Adam Vaughan

@adamvaughan_uk

Monday 9 October 2017 18.54 BST First published on Monday 9 October 2017 12.12 BST

Britain’s switch to greener energy will take another significant step forward this week with the opening of an industrial-scale battery site in Sheffield.

E.ON said the facility, which is next to an existing power plant and has the equivalent capacity of half a million phone batteries, marked a milestone in its efforts to develop storage for electricity from windfarms, nuclear reactors and gas power stations.

The plant, housed in four shipping containers, is the type of project hailed by the business secretary, Greg Clark, as crucial to transforming the UK’s energy system and making it greener.

At 10MW, the Blackburn Meadows battery is one of the biggest in Britain so far, but will soon be eclipsed by much larger plants.

Centrica, the parent company of British Gas, is building a 49MW facility on the site of a former power station in Barrow-in-Furness, Cumbria, while EDF Energy is working on one of the same size at its West Burton gas power station in Nottinghamshire.

David Topping, the director of business, heat and power solutions at E.ON, said: “This is a milestone for E.ON in the new energy world and an important recognition of the enormous potential for battery solutions in the UK.”

The utility-scale batteries are being built in response to a request from National Grid, the owner of Britain’s power transmission network, for contracts to help it keep electricity supply and demand in balance, which is posing an increasing challenge for the grid as more intermittent wind and solar comes online.

Balancing supply and demand is essential for keeping the frequency of electricity constant at 50Hz across the UK. The ability of batteries to respond to demand in less than a second makes them ideal for the task, with earlier sources of backup power much slower at just under 10 seconds.

E.ON has secured £3.89m of the £65.9m of contracts awarded for the service, though National Grid estimates the batteries will save it £200m over four years.

Leon Walker, the commercial development manager at National Grid, said: “Using battery storage is a significant development for managing the national grid. It’s an ultra-fast way of keeping electricity supply and demand balanced.”

The new generation of batteries will also earn their owners money by helping with the government subsidy scheme for providing backup power during winter, known as the capacity market. The storage plants will also be able to take power off the system when supply is unexpectedly high, such as on a particularly windy or sunny day.