Off Grid/Energy Access    New York Utilities Learned a Lot From Superstorm Sandy. Will That Help Them in Puerto Rico?    “We are well prepared and uniquely qualified to help them restore power.”
    Emma Foehringer Merchant  
  December 08, 2017        
  Con Edison utility workers helped New York survive Superstorm Sandy. Now they're at work in Puerto Rico 
   Photo Credit: Mark Dye, Con Edison
    After   Superstorm Sandy rattled New York, its storm surge   washing over electrical equipment   and darkening a large chunk of Manhattan, Johnny Price lived at the  Con  Edison control center where he worked for nearly a week. 
    “I just kind of stayed on a cot downstairs for the first six days,”   Price said, then an operator responsible for Westchester County and   Staten Island. “The emergency phone didn’t stop ringing for a   day-and-a-half, which was pretty wild. Tensions were high, my brain felt   like mush after a 14-hour shift. We did about 14 or so shifts in a   row.”
   At the same time, it was exhilarating for Price. Con Ed,  which services  New York City and Westchester, got things up and running  “incredibly  quickly,” he said.  
   With the initial response  behind them, Con Ed and other Northeastern  utilities mapped out a  years-long storm hardening plan that continues  today.
   That  focus on resilience -- as well as the timing of Hurricane Maria so   close to Sandy’s five-year anniversary -- led to comparisons between New   York and Puerto Rico. 
   New York. Gov. Andrew Cuomo has   visited the island   three times and continues to consult closely on restoration efforts. A   mutual aid agreement sent hundreds of workers from the state to assist   in restoration. And New York utilities felt their engineers were   equipped to help get the island's grid back up and running, namely   because of their experience with Sandy.    “We are well prepared  and uniquely qualified to help them restore  power,” said Gil Quiniones,  CEO at the New York Power Authority (NYPA).  “This is what we do every  year -- there’s always a storm.” 
  But Puerto Rico’s uniquely  devastated grid, topography, and  infrastructure have all presented New  York crews with new challenges.  Even after weathering a storm like  Sandy, the situation in Puerto Rico  is anything but simple for utility  crews.
   In Old San
   Juan Crews from New York landed  in Puerto Rico to assist engineers from  PREPA, the island's utility,  almost immediately after Hurricane Maria  passed. Under a mutual aid  agreement, there are now over 450 New York  utility workers there, most  working in Old San Juan.
   While Price and Quiniones both said  their experiences with Sandy prepped  them for work in Puerto Rico, Con  Ed’s Puerto Rico incident manager,  Orville Cocking, said working in  Puerto Rico has been “humbling.” 
     Orville Cocking, Con Ed's Puerto Rico incident manager, is responsible for many of the New York crews deployed to the island.
   Some of the work in Puerto Rico is comparable to restoration post-Sandy.
  “The  work is pretty similar: Get poles back in the ground, bury them  deep  so they’re more resistant to storms, and put the wire back on the   poles, put the transformers back on the poles,” said Price. “Once you   get authorization -- pick up customers.”
   There are major differences, however.
    The overhead, radial distribution system looked familiar to New York   crews, as did the equipment and the voltage. But the installation of   Puerto Rico’s energy infrastructure is entirely unique from New York’s   system.
   In Old San Juan, for instance, the archeological  significance of the  colonial-era district means poles can’t be dug into  the ground. Instead,  they’re placed high up on rooftops, which in some  cases had been made  unstable by the storm. 
   “We would never  see anything like that in New York,” said Quiniones.  There, poles are  buried or embedded in the pavement of streets and  sidewalks. 
    Instead of using bucket or line trucks to work from the street, which   are at times too narrow for trucks, Price and Cocking described working   within individual buildings using ladders or contracted crane operators   to reach poles. That involved anchoring damaged buildings and  employing  tour guides as translators between crews and the crane  operators. 
   New York crews also had difficulty navigating  streets filled with  concrete detritus from downed structures. Parts of  Puerto Rico have  concrete power poles, whereas New York uses wood.  (Maria was so strong  it brought concrete poles down.) New York crews  weren't able to lift the  heavy poles, so workers had to rely on cranes  in those instances, too. 
  “Each job took a lot of thought and effort,” said Price. 
   Brain Dump
   Despite the unique challenges, the New York contingent said many post-Sandy practices are applicable in Puerto Rico. 
    Price said he was very impressed with PREPA’s engineers, but did notice   differences in procedures. When he first arrived, he was greeted with a   185-page book of PREPA’s standards. After Price had some more help  with  translating, he discovered that Con Ed’s standards were stricter.  When  practical, line workers have been repairing the grid to Con Ed’s   standards, said Price and Cocking.
   The two utilities also  differed in their monitoring of poles. According  to Price and Cocking,  PREPA didn’t have a numbering system to help track  which poles were  being worked on. That made it difficult for the many  different mutual  aid and local crews working to coordinate, so Con Ed  shared its mapping  and tracking system.
   “One thing we noticed earlier on is they  were a little looser with us in  terms of communication and log out, tag  out,” said Price, referring to a  pole-logging system. “We ran our own  little control center down there  to keep the process as tight as  possible.”
     Johnny Price, a Con Ed section manager of the Staten Island overhead, worked in Puerto Rico for 20 days in November.
   Price stressed the importance of taking breaks -- a difficult task when the situation on the island is so dire.
    “You have to pace yourself, you need to make people go to sleep so they   can be useful the next day,” he said. “You might be helping, but  you're  also a danger in your 19th or 20th hour of work.”
   That mentality will only become more important. 
    "The PREPA engineers and lineman have been working pretty much for 80   days straight to try to get the power back," he added. "They’ve got a   lot of work ahead of them, too.”
   A Long Haul
    According to Quiniones, New York will continue to play a key role in the   rebuild process. He said Gov. Cuomo’s team and NYPA are helping to   flesh out the $94 billion plan for federal relief that Puerto Rican Gov.   Ricardo Rosselló submitted in mid-November. 
  “We all need to take a long view,” said Quiniones. “The goal is to figure out how they can build back better.”
    To that end, NYPA and PREPA have formed a working group that includes   Con Ed, Long Island Power Authority, Southern California Edison (because   of its work on distribution automation and use of renewables and   distributed energy resources, according to Quiniones), the Electric   Power Research Institute, Smart Electric Power Alliance, the Department   of Energy, and national laboratories Brookhaven, Pacific Northwest, and   the National Renewable Energy Laboratory.  
   Even with that  deep lineup of energy innovators, the path will be long.  Quiniones  noted that Long Island Power Authority and Con Ed are still  modernizing  and hardening the grid five years after Sandy.
   Quiniones  rattled off a list of "basic hardening" measures, such as  relocating  and elevating substations, installing flood walls,  putting some  circuits underground, bundling conductors, and  standardizing voltage at  13 kV. He said the island will ultimately have  to decentralize its  grid.
   “This is going to be a long haul,” said Quiniones. “It’s probably going to take a decade.”
   greentechmedia.com |