We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Canadian Political Free-for-All

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: gg cox who wrote (19468)4/23/2019 8:48:27 PM
From: gg cox  Read Replies (1) of 37399
 
Rail Safety Advisory 617-05/19

Air brake system inspection and maintenance on grain hopper cars used in CP unit train operation

Place du Centre

4th Floor

200 Promenade du Portage

Gatineau, Quebec

K1A 1K8

11 April 2019

617-05-19

R19C0015

Ms. Brigitte Diogo (ASR)

Director General, Rail Safety

Transport Canada

14th Floor, Enterprise Building

427 Laurier Avenue

Ottawa, Ontario

K1A 0N5

RE:

Rail Safety Advisory R19C0015 05/19

Air brake system inspection and maintenance on grain hopper cars used in CP unit train operation

Dear Ms. Diogo:

On 4 February 2019, at approximately 2148 Mountain Standard Time, Canadian Pacific Railway (CP) loaded unit grain train 301-349, proceeding westward to Vancouver, British Columbia (BC), was brought to a stop at Partridge, BC (Mile 128.7) on the Laggan Subdivision, using an emergency brake application. The track grade at this location was about 2.2%. Subsequent to stopping, the crew performed the required job briefing with a supervisor and the decision was made to set retainer valves to the high-pressure position on 75% of the cars on the train (84 cars). No hand brakes were applied. After an extended period of about 2 hours 45 minutes, a relief crew arrived to replace the crew at Partridge, whose maximum hours of service had been reached. About 10 minutes later, the train began to move on its own. The relief crew had not yet recovered the air brake pressure from the emergency brake application. The crew members were in the process of securing the train to facilitate the safe release and recharge of the air brakes. The train gradually accelerated to a speed in excess of the maximum track speed, and then derailed. A total of 99 cars and 2 locomotives derailed between the Upper Spiral Tunnel and Lower Spiral Tunnel near Field, BC. The crew members on board, consisting of a locomotive engineer, a conductor and a conductor trainee, were fatally injured. At the time of the occurrence, the temperature was -28°C. (TSB Occurrence No. R19C0015)

Prior to the emergency stop, as the occurrence train began the descent on Field Hill and was proceeding through Partridge, the crew had not been able to keep the train at (or under) the maximum authorized speed of 15 mph using a progressive application of the air brakes and dynamic brakes. When the speed reached approximately 23 mph, and despite the heavy (> 20 psi) application of the air brakes in combination with full dynamic brakes, the locomotive engineer applied the air brakes in emergency, as required by CP's General Operating Instructions (GOIs), section 32.9, Uncontrolled Movements – Stop Required, which states:

Any movement descending a Heavy or Mountaingrade that attains a speed 5 MPH above permissible speed is considered an uncontrolled movement and must be stopped immediately by whatever means available, including (if necessary) using an EMERGENCY brake application.

Subsequent to the accident, the TSB conducted air brake system testing on the 13 grain hopper cars that did not derail. It was determined that:

The air brake system on these cars would not provide adequate braking effectiveness to ensure the safe operation of a loaded unit grain train in a situation where the air brakes are required to remain applied for an extended duration, such as while descending a steep grade. Annex A provides a summary of the test results, including a graph of the measured brake cylinder pressure (BCP) leakage (i.e., average BCP of the 13 cars plotted over the 3-hour test period).Relative to the expected maximum pressure during the series of service brake applications, BCP dropped to 56% in 15 minutes.Relative to the expected maximum pressure from the emergency brake application, BCP dropped to 60% at the end of the 3-hour test period.As the 13 grain hopper cars represent about 11% of the 112 cars on the occurrence train, the test results generally represent the air brake performance on train 301-349 as it operated through Partridge and at the time of the occurrence.

Other observations relating to the air brake performance of the occurrence train include:

All 13 grain hopper cars failed additional testing utilizing an automated single car test device (ASCTD). The ambient temperatures during testing ranged between -21°C and -26°C.
(Note: Association of American Railroads (AAR) Field Manual Rule 3 and AAR Manual of Standards and Recommended Practices Section E, Specification S-486 and Specification S-4027 do not require that testing be performed at the coldest ambient temperatures to which the cars may be exposed. As such, test results obtained in a repair shop environment, or in moderate outdoor temperatures, may not reveal air brake performance issues that can develop during extreme cold operating temperatures.)A properly functioning air brake system is of the utmost importance in mountain territory from a safety standpoint. For unit bulk commodity trains operating on Field Hill, CP has implemented a number of risk mitigation measures. With warmer ambient temperatures in the spring, this seasonal relief will help restore air brake efficiency. However, given the potential consequences when uncontrolled movements occur, particularly in mountain territory, Transport Canada may wish to review the efficacy of the inspection and maintenance procedures for grain hopper cars used in CP's unit grain train operations (and for other railways as applicable), and ensure that these cars can be operated safely at all times.

Yours sincerely,

Kirby Jang

Director

Investigations, Rail/Pipeline

tsb.gc.ca

So some questions from above report.

“”””The track grade at this location was about 2.2%. Subsequent to stopping, the crew performed the required job briefing with a supervisor and the decision was made to set retainer valves to the high-pressure position on 75% of the cars on the train (84 cars). No hand brakes were applied. “””

Ok, from investigation of the wreckage, Question...

How many brake retainers were applied? They are easily identifiable as about the size of a fist with pipe leading to them on each car.

“”After an extended period of about 2 hours 45 minutes, a relief crew arrived to replace the crew at Partridge, whose maximum hours of service had been reached.””

Question.

Did the original crew succeed in applying the high pressure retainers on 84 cars?

“”””About 10 minutes later, the train began to move on its own. The relief crew had not yet recovered the air brake pressure from the emergency brake application. The crew members were in the process of securing the train to facilitate the safe release and recharge of the air brakes.”””

Questions..

How were they in the process of securing the train ?

Were they tying on hand brakes? Were any hand brakes tied on,, found in the wreckage?

How is a safe release of train air brakes accomplished on a 2.2 percent grade without tying 40 or more hand brakes on and testing to see if they hold,,and possibly tying on more , to secure the train,, and then recharge the train line to maximum brake pipe pressure.

Followed by a full set brake on the whole train,,and release of 40 or more hand brakes and still a very dangerous move as the full service brake application could still not hold the train on that extreme grade... and the conductor back there releasing them.

Further Questions.

What did the train line flow indicator show cresting the hill?

Did it show excessive train line leakage? Was the train line fully charged cresting the hill?

Why has siding at Partridge been left in service after this disaster? ..here..

bst-tsb.gc.ca

It is obvious that westward full tonnage trains must not stop with emergency application of the brakes on 2.2 percent grade 13.5 miles in total as it creates more serious problems than it solves as evidenced by 2 disasters mentioned here.

Why has Transport Canada not recognized that this disaster happened because of flawed operating procedures on this extreme 2.2 percent grade and not because of lacking train brake functioning which is not provable as subsequent test on only eleven percent of rail cars involved.

Full stop and start at crest of the Hill at Steven might be a thought.

Another ,,only very experienced engineer pilots to operate this section of track.