We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Formerly About Advanced Micro Devices

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Paul Engel who wrote (28316)2/4/1998 11:41:00 PM
From: Yousef  Read Replies (2) of 1572159
 
Paul,

Re: "For a Fab producing 6,000 or 7,000 eight inch wafers a week ... how
many steppers would be required for the yellow room?"

A good rule of thumb for 200mm wafers is a stepper is good for about
900 outs/month (19 mask process). But remember for a .25um process, there
will be about 3 I-line steppers for each DUV tool. Thus the answer to
your question is:
6000 wfr/week needs 7 DUV tools and 21 I-Line steppers
7000 wfr/week needs 8 DUV tools and 24 I-Line steppers

Make It So,
Yousef