We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Arconenergy, Inc. (Long Term Investors and Fundamentals)

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Ga Bard who wrote (16)2/8/1998 10:44:00 AM
From: Ga Bard  Read Replies (1) of 1757
 
In February of 1997 S. A. Holditch & Associates, Inc. did an evaluation of the Bob West Prospect. In the executive summary:
The three wells are Hinojosa #1, Guerra #1, and the Luera #1.
All three wells were completed in the same geologic equivalent sand, the L20, L21.
In each of these wells there are 3 to 5 additional sands with potential for gas production that has not been completed.

The following table list the primary zones and the important reservoir estimated for the Hinojosa well.

Zone .... Net Pay... Porosity...Water Sat. ...... Perm- ....... Initial
................Feet.........(%)............(%)..........Thickness ..... Permeability
....................................................................(md-ft)............(MD)

L-5 .......... 35 ...... 10.4 ........... 34 ...... ......... 2.4 ...... ...... 0.069
L-12 ...... 100 ...... 11.4 ........... 37 ...... ......... 6.9 ...... ...... 0.069
L-13 ........ 40 ........ 9.2 ........... 31 ...... ......... 2.7 ...... ...... 0.068
L-14 ........ 20 ........ 9.1 ........... 33 ...... ......... 2.7 ...... ...... 0.135
L-15 ........ 50 ........ 9.0 ........... 33 ...... ......... 3.4 ...... ...... 0.068
L-21 ........ 35 ........ 7.7 ........... 32 ...... ......... 1.1 ...... ...... 0.030

Gas production forecasts were generated assuming that the same sands observed in the Hinojosa well would be encounter in the South Bob West Prospect. Each zone should capable of draining 80 acres when propped fractured to 750 feet. The following chart summaries the results from the analysis.

Zone .... Cum. Gross... Cum Undis. Net ... Cum Undis. Revenues
...............Production.........Revenues.................. Revenues
.................(MMscf)...........($1000s).....................($1000s)

L-5 ............ 1,844 ...............2,442 ........................2,229
L-12 .......... 5,983 ...............7,995 ........................6,751
L-13 .......... 1,959 ...............2,564 ........................2,291
L-14 ............. 947 ...............1,234 ........................1,159
L-15 .......... 2,402 ...............3,153 ........................2,775
L-21 .......... 1,230 ...............1,575 ........................1,395

Totals ...... 14,365 ............ 18,963 ........... ...... .. 16,598

Note the Economic parameters assumed for the above analysis are as follows:

Gar Price - $2.00 constant; Operating Costs - $1500/month; Royality - 25%
Taxes - 7.5%; Discount Factor - 10%

The estimate for the initial zone completion cost to be Appr. $1.1M
The cost for each subsequent zones estimated $450K
Hinojosa has the appearance and indicated performance of a tight gas reservoir.
Also the cutoff valve for shaliness was 50%, water saturation was 50% and the porosity was 6%.

The following table is the results of the Promat (tm) analysis:

.................................................... Guerra #1 .....Luera #1
Permeability - thickness, md ft ........ 0.2 .............. 4.6
Permeability - md .......................... 0.005 ........... 0.035
Net Pay, ft ........................................ 37 ............... 131
Reservoir Pressure, psi .................. 11.470 ......... 10,900
Fracture Length, ft ........................... 450 ............. ------
Skin Factor ...................................... --- ............... -3.7
Drainage area, acres ......................... 77 ............... 12
OGIP, Mmscf ................................ 2,170 .......... 2,700

The reports states it is doubtful that the skin factors are accurate.

Not the report states that it is not surprising that the Luera well would have the highest permeability -thickness since this well produced over 2Bcf naturally. The Guerra well produced appr. 800 Mmscf, but hydraulically fractured. The Hinojosa well, which produced the least of the three, was not hydraulically fractured successfully.

In generating these forecasts, they assumed a 750 ft propped fracture could be created in each of the sands and the drainage area for each zone would be 80 acres.

Results from production forecasts Bob West South Prospect

Zone .... Cumulative ....... Producing ............... Minimum Flow
...............Production.............Years .................. Pressure
.................(MMscf)........... (Time) ....................(PSI)

L-5 ............ 1,847 ............... 6.7 ........................ 1750
L-12 .......... 5,985 ............. 17.2 ........................ 2050
L-13 .......... 1,985 ............... 8.7 ........................ 2050
L-14 ............. 947 ............... 4.5 ........................ 2100
L-15 .......... 2,403 ............. 10.1 ........................ 2150
L-21 .......... 1,231 ............... 7.5 ........................ 2300

If the same quality of sands are penetrated by the Bob West South Prospect, the potential production from the well could be on the order of 14 Bcf.

Hope this helps