Latest Snowy 2.0 business case a surprise, but batteries might eat its lunch       David Leitch
  May 24, 2024     9        Share via Email 					 				 		
     Commentary 
    Pumped Hydro
     Snowy Hydro, just a few days after   revealing the latest problems for its luckless tunnelling machine Florence,   has published its updated (as of August 2023) business case on its   website, which claims an increase in the project’s net present value,   despite the blow out in costs.
       I am a bit out practice at  looking at Net Present Value (NPV)  calculations, so reviewing this was a  chance to get a bit of “match  practice”.
      In the brief time  available to review the numbers there is nothing  that jumps out as  being completely unreasonable. In fact, if we take  Snowy’s estimate of  annual after tax cash flows as reasonable, the  project looks  attractive. This was a surprise to me.
     Although I barely  scratch the surface on the biggest component of  value – that is simple  storage trading, which Snowy estimates is worth  $7 billion based on  earning an average trading margin of $100/MWh – my  own calculations  suggests it’s a reasonable estimate, in and of itself.
      That  is, I’d expect an asset that generates up to 2.2 GW with very  large  storage could earn $100/MWh for 4 to 6 hours per day. A battery  needs  double that margin to justify being built and historic margins  have  mostly been above $100.
      However, I also think there will be  lots and lots of competition in  the storage trading space. Still, with  margins over the past year closer  to $300/MWh than $200 there is plenty  of headroom for competition.
      What I haven’t done is look at  firming and capacity contracts, that  are the second largest source of  value, and nor have I looked at the  integration of both them to check  that for plausibility. Time for lunch.
      Overview
    Snowy 2.0 represents that for the first 15 years of operation it will   earn roughly $1.2 billion of gross margin. The trading gross margin is   the difference between the price electricity is sold for and the price   paid for it, after adjusting for the round-trip efficiency factor of say   0.75. I also use storage margin or storage reward for the same  concept.  
      The round trip efficiency has two consequences.  First it means that  to generate for 4 hours you have to pump for 5.3  hours. But when you  pump for 5.3 hours it’s likely that the average  cost per hour of pumping  will be higher than if you only pumped for 4  hours. You get less choice  in the hours to pump. 
    I have used  $12 billion for cost which is Snowy’s number. At a  minimum there is  also capitalised interest to be considered. I would  roughly estimate  $0.5 billion. 
      I am happy to exclude most of the transmission  costs. In the first  place it’s normal to do so, no matter what some  say.  Secondly I  specifically think the business case for Humelink and  VNI West is very  strong even if Malcolm Turnbull had never indulged his  nation building  urges.
      However, the component of Humelink  that is basically only used for  connecting Snowy 2.0 should be  legitimately added to project cost.  Including that and the capitalised  interest would likely get to $14  billion, even if there are no further  increases.
              Snowy 2 casual value. Source: Snowy, ITKe
       Notice  in the table below, the basically universal view of people  selling  business cases that things will get better in the far distant  future.  In this case, as the dollars are nominal, inflation is your  friend.
              Snowy 2,PV by year. Source:Snowy
       If  we assume Snowy’s estimate of its after tax cash flows are  accurate,  then once we allow for the value beyond 2050 as little as it  is, then I  estimate the project’s underlying rate of return is about 9%.
             Snowy IRR 9%?. Source:Snowy, ITKe
  The  vast majority of the value is created from the storage reward,  but  Snowy also plans to sell firming products. It is in a position to do   this, up to a point, because of the quantity of stored energy and also   its access to its own traditional generation capacity as a backup. 
       However, it cannot double-dip on the same MW for two different   revenue streams at the one time. That is, it can’t be selling the same   MW in the spot market and also firming someone else’s solar plant at the   same time.
              Snowy2 Margin by source. Source:Snowy
       Snow’s NPV is a bit easier because volume is fixed. There is no growth
    In most cases, much of the debate around the value of a business   centres on forecasting the growth rate of cash flows. However, for an   individual unit of production like a single factor, or in this case a   pumped hydro project, the volumes have a fixed limit, the only variable   to be forecast is the average price.
      In saying that, Snowy  2.0 has a huge amount of storage – 175 GWh  relative to any other long  duration storage project. The mooted Borumba  project has similar size  in power capacity but even its 48 GWh is modest  compared to Snowy 2.0.
       I am well aware that the ability of Snowy to replenish its storage   whenever it wants to is hotly contested, but I don’t propose to consider   that in this note. I have zero knowledge on that topic.
      Looking at the Storage gross margin
    Before doing some specific analysis I can take some numbers I update   every week on battery margins that assume a battery operator has perfect   foresight and can pick the highest prices to generate at and lowest   prices to pump at every day.
      The red line is a six hour  spread and the green 4 hours. Those  margins over the past year average  $297 and $356 per year. These are 3X  the numbers assumed in the Snowy  value case so very supportive.
             Storage margins. Source:NEM Review, ITK
       Equally,  a new four-hour battery at recent CSIRO Gencost, which in  this  instance I think are well in the ballpark, requires between  $200/MWh  and $300MWh to justify the initial investment. 
      In practice,  the batteries are built on the assumption that frequency  regulation  will provide some of the revenue. Like Snowy once the  battery is built,  it can undercut Snowy because Snowy’s round trip  efficiency is worse  than a battery. 
      Snowy says the design life is 150 years,  whereas a battery design  life is 20 years. Snowy’s capital cost goes up  every year, whereas for  the next decade or so battery costs will fall,  say, 6% a year.
      I have no doubt at all that when 5 GW of new  batteries under  construction are actually operating, and even assuming  that only say 75%  of that is devoted to trading, that margins will  fall from the current  levels.
             Bateries being built. Source:www.renewmap.com.au
       However, if margins fall to the $100/MWh assumed by Snowy the batteries will not recover their capital costs.
       Looking at it in a fairly casual NPV perspective, my first guess is   that if we ignore tax the numbers support Snowy’s estimate of the   storage NPV at around $7 billion. 
      To see that, I made use of  the “Gordon Growth formula.” This  approximates the NPV of an anual  cash flow as CFWACC-g where:  CF=Cash  Flow  WACC=Weighted Average Cost  of Capital  g=Growth Rate (assumed to  be inflation).
          
  The TWh a year and assumed margin were supplied in the business case document. They are almost credible.
      Finance 101 in 3 paragraphs
    TL:DR – At the risk of boring readers, a reminder that the NPV (which   my ex boss used to say stood for No Present Value) makes use of the   concept that people will pay more for $1 that they get today compared to   $1 in a year’s time and $1 received in two years’ time. 
      If  the rate of interest is 10% you would pay 1/1.1 for $1 to be  received  in one year and $1.21 for $1 to be received in two years time  and so  on. By estimating the cash inflows and outflows for each year and   choosing a discount rate one calculates the NPV.
      Many a  textbook has been written about the choice of discount rate  which, for  something involving risk uses the Weighted Average Cost of  Capital  (WACC). But the simplest and oldest version is the after tax  cost of  debt plus the cost of equity, using the proportions of each. The  cost  of equity is a long topic mainly because of the uncertainly around  the  appropriate measure of risk
      NPVs involve forecasts of future  cash flows which are highly  uncertain. The NPV is also sensitive to the  choice of discount rate and  the number of years over which the  cashflows are forecast. 
      However, for any reasonable discount  rate, cashflows more than 30  years in the future have little impact on  the NPV. Or, to put it another  way, cash flows received in the earlier  years of the project have a  much bigger impact than out year ones.
 
  
    David Leitch
  David Leitch is a regular contributor to   Renew Economy and co-host of the weekly   Energy Insiders Podcast.   He is principal at ITK, specialising in analysis of electricity, gas   and decarbonisation drawn from 33 years experience in stockbroking   research & analysis for UBS, JPMorgan and predecessor firms.
    Share on Twitter   Share on Facebook   Share on Pinterest   Share on LinkedIn   Share on Reddit 				 			
   reneweconomy.com.au
   My comments:
  Hydro still has a place but the vast amount of storage from now into the future is batteries.
  They can be put practically anywhere on the grid or behind the meter in your home or business.
  The future of large scale energy storage (electrical) has arrived.
  Cheaper today than any other storage medium.
  And that trend will only continue to get ever cheaper into the future.
  Eric   |