Rio2 Provides Fenix Gold Mine Construction Update    finance.yahoo.com
    Rio2 Limited   Mon, January 13, 2025 at 4:30 AM PST 8 min read    RIOFF    -2.97% 
   Rio2 Limited  VANCOUVER,  British Columbia, Jan. 13, 2025 (GLOBE NEWSWIRE) -- Rio2 Limited  (“Rio2” or the “Company”) (TSXV: RIO; OTCQX: RIOFF; BVL: RIO), is  providing an update on construction activities at its Fenix Gold Mine  located in the Maricunga Gold Belt of the Atacama Region, in Chile.
  OVERVIEW
  Pre-construction  activities commenced at the Fenix Gold Mine in 2022 prior to the  Environmental Impact Assessment (“EIA”) for the project being rejected  by the Chilean environmental regulators. Those activities included:
 
 - ordering  and securing of long lead items for the construction of the adsorption,  desorption, and gold recovery (“ADR”) plant and associated  infrastructure
    - fabrication of ADR plant components such as tanks and ADR plant foundation footings
    - construction  of a 565-person camp and associated mess and office facilities at the  Lince infrastructure site, located 20km from the mine site
    - water loading facilities at the Nueva Atacama water treatment facilities located in Copiapo
     The project’s EIA was subsequently approved in December 2023 following a successful 18-month appeal process.
  The  Company recommenced construction activities at the Fenix Gold Mine in  October 2024 after successfully completing a debt and equity financing  for the construction of the mine announced on October 29, 2024.
  The  projected construction capex for 2025 is estimated to be USD 122 M  (excluding Chilean VAT tax which is refundable) with construction  expected to be completed in November 2025. First gold production is  currently guided for January 2026.
  PLANT SITE
  Bulk  earthworks at the plant site have been completed and concrete bases for  the footings of the processing plant have been poured. The ADR plant  will be housed within a steel framed building cladded with modular  thermo-acoustic panels.
  LEACH PAD
  Earthworks  have commenced on the leach pad stability platform, which forms the  base of the Phase 1 leach pad. The leach pad has been designed to be  built in four phases over the 17-year mine life of the 20,000 tonnes per  day operations.
  PREGNANT LEACH SOLUTION (“PLS”) POND
  Excavation  earthworks for the PLS pond have commenced adjacent to the ADR plant.  The PLS pond will be lined with a double HDPE geomembrane liner system  and have an installed capacity of 28,000 cubic metres. As determined by  water balance modelling in the 2023 Fenix Gold feasibility study, a  larger major events pond is currently planned to be built in year 6 of  the mine operation.
  PERSONNEL
  The  recruitment activities for the Fenix Gold Mine have focused on hiring  key personnel for construction activities and future mine operation  roles. Personnel numbers at the Fenix Gold Mine are increasing and,  currently, over 531 staff and contractors work on-site. At the end of Q4  2024, approximately 50% of the workforce were from the Atacama region,  and 16% of on-site personnel were women.
     SAFETY
  At the end of Q4 2024, the project achieved 161,917 person-hours worked with no lost time injuries reported.
  GRADE CONTROL DRILLING AND GEOPHYSICAL SURVEY
  In  February, the Company will commence a 12,000m grade control drilling  program focused on the first three years of production planned from the  Fenix South and Fenix North pit areas. Fenix South will be the first  area drilled during the months of February, March and April, and Fenix  North will be drilled in October and November. The Fenix South pit will  be the principal source of ore for the first year of mine production.
  From  February to March the Company will complete a survey of 25,000 meters  of CSAMT electromagnetic lines. This survey will help the geological  team identify silicified zones associated with black banded veins, which  are the main gold host at the Fenix Gold deposit. The geophysical  targets generated from this work will allow the Company to focus its  future exploration drilling campaigns with the objective to grow the  mineralized resource at Fenix Gold. Resource expansion drilling is  currently planned to occur once gold production has commenced at the  mine.
  Rio2 is also pleased to announce that  Enrique Garay has recently returned to the Company as Senior Vice  President - Geology to lead and oversee the Fenix Gold geological team  in preparation for mining toward the end of 2025 and future exploration.
  MINE EXPANSION STUDY & ASSOCIATED EIA
  A  preliminary internal study completed by the Rio2 technical team has  indicated that the Fenix Gold Mine has the potential to be expanded from  its first phase 20,000 tonnes per day ore mining rate to around 80,000  tonnes per day. Increasing the ore mining rate to this level could see  gold production rise from an initial rate of approximately 100,000 oz  per annum to a target range of 250,000 – 300,000 oz per annum. To  quantify and justify this potential expansion, the Company has initiated  a mine expansion study with a target completion date by the end of  2025. Long-term water options will be assessed for the study and the  most optimal water strategy will be selected and form a base case for  project economics. To put this potential expansion case on a fast track  to a construction decision, Rio2 has recently initiated baseline studies  for an EIA study on the project, which is anticipated to be ready for  review by the environmental regulators in the Atacama Region by Q4 2026.  As most of the required infrastructure for the expanded project (apart  from water which is expected to be provided by a third-party provider)  is within the existing footprint of the currently approved EIA, the  Company expects the EIA process to advance relatively smoothly. Updates  will be provided as the expansion study and EIA progress.
  Andrew  Cox, President & CEO, commented, “Site activities at the Fenix Gold  Mine continue advancing to plan. We are delighted with the team we are  putting together and the milestones achieved so far. We look forward to  continued success as we prepare the mine for first gold production in  January 2026.”
  Photos of the construction activities can be found at (https://www.globenewswire.com/Tracker?data=aa5pAMUCuL4GrTDpLXYOJs4hHzd5aU9A5Y_RjQC8fLONGqL70sf3_o4rFNypJjCkqJyAdIe6E-csHwMwtgIFx_HpvBbNbwmSNf3zEhPpbJm6iVrQ1enGYNPjqXP-XzF4). To view a 3D VRIFY version of Rio2’s corporate presentation please click the following link:  https://vrify.com/decks/17439 or visit the Company’s website at  www.rio2.com
  STOCK OPTION GRANT
  The  board of directors of the Company has approved the grant of an  aggregate of 6,310,000 incentive stock options (the “Options”), pursuant  to the Company’s Stock Option Plan, to a total of 72 directors,  officers and employees of the Company, its Peruvian subsidiary, Rio2  S.A.C., and its Chilean subsidiaries, Fenix Gold Limitada and Lince S.A.  The Options are exercisable at a price of $0.70 per share (based on a  10% premium over the closing price of C$0.63 on January 10, 2025) and  will expire five years from the grant date. The Options represent the  Company’s annual grant of long-term incentives consistent with the  Company’s regular yearly compensation.
  FENIX GOLD PROJECT
  The  Fenix Gold Project is one of the largest undeveloped gold oxide, heap  leach projects in the Americas, hosting a Measured and Indicated mineral  resource (as such term is defined in National Instrument 43-101  -Standards of Disclosure for Mineral Projects, “NI 43-101”) of 4.8  million ounces of gold which the Company believes will make a positive  contribution to the Atacama Region and Chile. The Project is an example  of modern gold mining where a full complement of technical,  environmental, and social considerations has been consulted and designed  from the outset. The Project represents a significant investment in the  gold mining business in Chile by a junior mining company of  approximately US$235M of initial and sustaining capital, generating  employment for at least 1,200 people during the construction phase and  550 people during the 17-year operations phase. The mine being  contemplated will be a run-of-mine heap leach operation; no crushing or  tailings storage facilities are required, thereby minimizing the overall  impact and footprint of the Project.
  The  scientific and technical content of this news release has been  reviewed, approved and verified ?by Enrique Garay, MSc P.Geo/FAIG who is  a QP under NI 43-101. For additional information regarding the Project,  including key parameters, assumptions ?and risks associated with its  development, see the independent technical report entitled ??“NI 43-101  Technical Report on the Feasibility Study for the Fenix Gold Project”  (the “Feasibility Study”) pursuant to National Instrument 43-101  Standards of Disclosure for Mineral Projects (“NI 43-101”). The  Feasibility Study is dated October 16, 2023, with an effective date of  October 16, 2023, a copy of which document is available under ?Rio2’s  SEDAR+ profile at ? www.sedarplus.ca.
  ABOUT RIO2 LIMITED 
  Rio2  is a mining company with a focus on development and mining operations  with a team that ?has proven technical skills as well as successful  capital markets track record. Rio2 is focused on ?taking its Fenix Gold  Project in Chile to production in the shortest possible timeframe based  on a ?staged development strategy. Rio2 and its wholly owned subsidiary,  Fenix Gold Limitada, are ?companies with the highest environmental  standards and responsibility with the firm conviction ?that it is  possible to develop mining projects that respect the three pillars  (Social, Environment, ?Economics) of responsible development. As related  companies, we reaffirm our commitment to ?apply environmental standards  beyond those that are mandated by regulators, seeking to ?protect and  preserve the environment of the territories that we operate in.?
  Forward-Looking Statements
  This  news release contains forward-looking statements and forward-looking  information (collectively ???“forward-looking information”) within the  meaning of applicable securities laws relating to Rio2’s ?development of  the Fenix Gold Project and other aspects of Rio2’s future ?operations  and plans. In addition, without limiting the generality of the  foregoing, this news release ?contains forward-?looking information  pertaining to the following: the development of a mine at the Project  and related construction activities; the expected capital required for  such mine; the expected timing of the first pour of gold; estimated  indicated and measured gold resources; expected mine life; development  and operating plans and expenditures; certain anticipated economic  benefits of a mine at the Project to the local region; the potential to  expand production from the first stage mining rate and associated gold  production along with the timing for the completion of related studies  and approvals; and other matters ancillary or incidental to the  foregoing. 
  All  statements included herein, other than statements of historical fact,  may be forward-looking information and such information involves various  risks and uncertainties. Forward-looking information is often, but not  always, identified by the use of words such as “seek”, “anticipate”,  “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”,  “predict”, “potential”, “targeting”, “intend”, “could”, “might”,  “should”, “believe” and similar expressions. The forward-looking  information is based on certain key expectations and assumptions made by  Rio2’s management, including but not limited to: expectations  concerning prevailing commodity prices, exchange rates, interest rates,  applicable royalty rates and tax laws; capital efficiencies; legislative  and regulatory environment of Chile; future mining and production rates  and estimates of capital and operating costs; expectations regarding  the availability of debt financing; estimates of reserves and resources;  anticipated timing and results of capital expenditures; the sufficiency  of capital expenditures in carrying out planned activities; results of  operations; performance; the anticipated timing and results of expansion  studies and related approvals; the availability and cost of financing,  labor and services; and Rio2’s ability to access capital on satisfactory  terms. 
  Rio2  believes the expectations reflected in these forward-looking statements  are reasonable, but no assurance can be given that these expectations  will prove to be correct and such forward-looking statements in this  news release should not be unduly relied upon. A description of  assumptions used to develop such forward-looking information and a  description of risk factors that may cause actual results to differ  materially from forward-looking information can be found in Rio2's  disclosure documents on the SEDAR+ website at www.sedarplus.ca.  These risks and uncertainties include, but are not limited to: risks  and uncertainties relating to the completion of debt and equity  financing for the construction phase of the mine, market conditions and  management’s ability to anticipate and manage the factors and risks  referred to herein.
  Forward-looking  statements included in this news release are made as of the date of this  news release and such information should not be relied upon as  representing its views as of any date subsequent to the date of this  news release. Rio2 has attempted to identify important factors that  could cause actual results, performance or achievements to vary from  those current expectations or estimates expressed or implied by the  forward-looking information. However, there may be other factors that  cause results, performance or achievements not to be as expected or  estimated and that could cause actual results, performance or  achievements to differ materially from current expectations. Rio2  disclaims any intention or obligation to update or revise any  forward-looking statements, whether as a result of new information,  future events or otherwise, except as expressly required by applicable  securities legislation. 
  To learn more about Rio2 Limited, please visit: www.rio2.com or Rio2's SEDAR+ profile at  www.sedarplus.ca.
  ON BEHALF OF THE BOARD OF RIO2 LIMITED
  Alex Black Executive Chairman  Email:  alex.black@rio2.com Tel: +51 99279 4655
  Kathryn Johnson  Executive Vice President, CFO & Corporate Secretary  Email:  kathryn.johnson@rio2.com Tel: +1 604 762 4720
  Neither  TSX Venture Exchange nor its Regulation Services Provider (as that term  is defined in the policies of the TSX Venture Exchange) accepts the  responsibility for the adequacy or accuracy of this release. |