| West Red Lake Gold Reflects on Madsen Mine Achievements To Date 
 finance.yahoo.com
 
 West Red Lake Gold Mines Ltd.
 Wed, April 9, 2025 at 12:13 AM PDT 11 min read
 
 WLGMF
 
 WRLGF
 +4.34%
 
 West Red Lake Gold Mines Ltd.   VANCOUVER,  British Columbia, April 09, 2025 (GLOBE NEWSWIRE) -- With the Madsen  Mine in Ontario, Canada, on track to start operating in a few months, West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or the “Company”) (TSXV: WRLG) (OTCQB: WRLGF) looks back at 22 months of achievements that have brought the project to this point.
 
 “As  we process our bulk sample - producing gold and further reinforcing  that our systematic approach will successfully deliver Madsen as a new,  high-grade gold mine in Canada - it is time to reflect on how West Red  Lake has delivered on its goals,” said Shane Williams, President and  CEO. “We bought a complicated asset, assessed needs, and got to work. We  stated specific goals and we have delivered on those goals. Our plan  has always been to restart Madsen as a sustainable mine and, with  anticipated production just months away, we are on track to deliver this  project from purchase to production in only two years.”
 
 
 
 West  Red Lake Gold completed the purchase of the Madsen Mine in June 2023.  By October 2023 the Company published its first set of plans to advance  Madsen and the nearby Rowan project. In June 2024 the Company added  detail to those plans through a list of projects designed to advance  Madsen to production in 2025.
 
 Below are listed the stated operational goals and the accomplishments on each to date.
 
 Goal Stated October 2023, Restated June 2024: Complete 39,000 metres (“m”) of underground drilling by the end of 2024.
 
 Accomplishment: From October 2023 through Q1 2025, the Company has completed 88,191 metres of drilling from underground at Madsen.  Approximately 90% of those metres have been definition drilling, which  references drilling into known resources to tighten drill hole spacing  and upgrade confidence ahead of stope engineering. Not only does the  tight-spaced drilling increase confidence in the resource but it also  allows the team to effectively define very high-grade zones of gold  mineralization that may not be fully represented in the life-of-mine  resource model. A perfect example of this would be the 114.26 grams per  tonne (“g/t”) gold (“Au”) over 10.6m recently announced from South  Austin (see press release dated  February 26, 2025).  This high-grade panel between 8 Level and 10 Level (400m and 500m  vertical depth) has seen very little historic development and is a  near-term focus for additional drilling.
 
 
 
 Approximately  10% of the metres were focused on resource expansion targets, often  with good success. Most of the expansion metres were drilled in late  2023 and early 2024 targeting North Austin. Initial results were quite  favorable including 27.15 g/t Au over 10.28m and 22.31 g/t Au over 8.5m  (see press release dated  November 21, 2023). Additional drilling at North Austin is planned for 2025 to continue extending this zone down plunge.
 
 
 Goal Stated October 2023: Complete 3,200 metres of underground development at Madsen in 2024.
 
 Accomplishment: West Red Lake completed 3,065 metres of underground development at Madsen in 2024.  To date in 2025 the Company has completed another 1,178 metres. These  metres are in addition to the development of the Connection Drift.
 
 Goal Stated June 2024: Complete a Pre Feasibility Study  (“PFS”) for the restart of the Madsen Mine. Results were originally  planned for release in November 2024; this timeline was slightly  extended to allow for further mine design optimization.
 
 Accomplishment: the results of the PFS were published on January 7th.  The PFS validated the rationale to restart the Madsen Mine by  generating strong economic results, including almost $70 million in  average annual free cash flow over 6 full production years.
 
 West  Red Lake has since described the PFS as the ‘base case’ for the Madsen  Mine’s restart. That statement stems from the conservative nature of the  PFS, in particular that Reserves were determined at a gold price of  US$1,680 per oz. If all other modifying factors stay equal, a higher  gold price would result in a larger Reserve and more favourable mine  economics.
 
 Goal Stated June 2024, Refined September 2024: Initiate a test mining program to assess longhole stope and cut-and-fill mining methods on the range of underground mining scenarios at Madsen, as an essential step in derisking the return to mining.
 
 Accomplishment: Six months of test  mining successfully produced the bulk sample. The test mining program  has also provided indispensable knowledge of how to mine safely and  effectively at Madsen, which in-house mining crews will now take with them into operations.
 
 In  addition, the test mining program proved the mineability of ore  directly adjacent to historic stopes. Lack of demonstrated mineability  meant that ore adjacent to old stopes was at risk of being unsafe or  dilutive to mine. Test mining, in places, blasted directly up against  old stopes; the test was successful in that the stopes remained  competent and the legacy backfill remained in place, which meant the  area was safe to mine and the blasted mineralization was not diluted.
 
 
 
  
 figure 1
 Figure 1: Ore from Stope 3 of the bulk sample stockpiled on surface.
 
 Goal Stated June 2024, Refined September 2024: Use  a test mining program to generate a bulk sample to enable a  reconciliation test between expected and actual tonnes and grade for  planned stopes.
 
 Accomplishment: A bulk sample program of 6 stopes totalling at least 15,000 tonnes is almost complete.  The sixth stope is currently being mined. Three of the six stopes have  been processed through the Madsen mill. Independent experts have  observed the entire project and will confirm the validity of the  results, which will compare the tonnes and grade expected in each stope  (based on the Company’s detailed internal mine plan) with the tonnes and  grade actually mined. The Company expects to release these results by  May.
 
 Goal Stated October 2023, Refined June 2024: Complete a 1,200-metre haulage way connecting the East and West Portals of the Madsen Mine by March 31st, 2025.
 
 Accomplishment: The 1,448-metre Connection Drift was completed on March 28th.  This underground highway, as Vice President Technical Services Maurice  Mostert describes it, is an essential part of the Company’s plan to move  material efficiently at the Madsen Mine. It was the largest of the  capital projects planned in support of restarting the Madsen Mine and it  was completed on time.
 
 
 
  
 figure 2
 Figure 2: The face of the last blast for the Connection Drift.
 
 
 
  
 figure 3
 Figure 3:  The Connection Drift with blasting complete. The muck from the last  blast is still on the floor and the meshing and bolting from the west  advance is visible from the east side.
 
 Goal Stated June 2024: Complete a 4-metre tailings dam lift to ensure adequate capacity to support tailings management.
 
 Accomplishment: A 4-metre tailings dam lift was completed on October 8th. This major earthworks project was completed on schedule and under budget.
 
 Goal Stated June 2024: Procure and install a camp to house 100 workers at the Madsen site.
 
 Accomplishment: A 114-person camp opened for operation at the Madsen Mine on March 18th, with junior suites, a cafeteria, a gym, and full staffing.
 
 Goal Stated June 2024: Install a permanent primary crusher.
 
 Accomplishment: A permanent primary crusher is operating at the Madsen Mine.  A Terex brand crusher with a nominal capacity of 145 tons per hour –  well in excess of Madsen current needs – was delivered to the mine site  on November 5th, 2024. It was commissioned and operational within two weeks.
 
 Goal Stated June 2024: Procure, install, and staff a mine dry sufficient to support miners of a full-operations Madsen mine team to transition in and out of shifts.
 
 Accomplishment: The constructed mine dry received its occupancy permit on April 3rd, 2025, and is now welcoming workers.
 
 
 
  
 figure 4
 Figure 4: The main room of the men’s dry prior to occupancy.
 
 Goal Stated June 2024: Continue dewatering the mine.
 
 Accomplishment: Dewatering has almost reached level 17, an achievement of 70 vertical metres since dewatering started in the fall of 2023.  The 17 Level of the Madsen Mine has not been dry since 1972. Dewatering  to this level and beyond will enable the Company to develop level  access to large promising areas of the resource in preparation for  definition drilling and mining and to explore deeper areas of the mine  where we have evidence of both grade and tonnage extension.
 
 Goal Stated June 2024: Install two evaporator fans with the ability to manage 2,000 cubic metres of water daily, to increase overall water management capacity at the mine site.
 
 Accomplishment: Two evaporator fans were installed and commissioned in the summer of 2024.
 
 
 
  
 figure 5
 Figure 5: Two evaporator fans operating over the polishing pond at the Madsen Mine
 
 Goal Stated October 2023: Publish updated Mineral Resource Estimate for Rowan by Q4 2023.
 
 Accomplishment: An updated MRE for Rowan was published in March 2024.  The Company is now completing an internal scoping study to evaluate the  potential for a direct shipping ore (“DSO”) scenario at Rowan.
 
 Goal Stated October 2023: Restart the Madsen Mine in 2025.
 
 Accomplishment:  With the mill running smoothly, definition drilling and mine  engineering having outlined over 15 months of mine-ready tonnes, the  Connection Drift complete, mining crews operating effectively,  development crews creating access to all needed mining areas, staffing  up to needed levels, maintenance working well, and stockpiles underway, the Madsen Mine is on track to start operating by H2 2025.
 
 Additional Accomplishments
 
 West  Red Lake has purchased and commissioned 19 major pieces of underground  equipment for mine operations, at a cost of $5.7 million. The rolling  stock on site is now sufficient for startup.
 
 The  Company implemented a new Enterprise Resource Planning (“ERP”) system  across the business. An ERP system is the backbone of expenditure  decisions and tracking within a complex operation like a mine and such a  system reaches into every key facet of the mine: maintenance  scheduling, supply procurement, personnel planning, capital project  management, and more. An ERP system fit to the task is essential for  smooth mine operations, which is why the Company dedicated significant  time and effort to testing, implementing, and training personnel on a  robust new system.
 
 There are now over 200  employees at the Madsen Mine. Establishing a workforce of this scale  spanning all roles with suitable aptitudes is a challenge. West Red Lake  is glad to have been able to work through this challenge over the last  18 months of active mine site operations, as with that time the Company  feels confident it has built a competent team to deliver operationally  at Madsen.
 
 West  Red Lake has dedicated significant effort to developing robust safety  systems and a strong safety culture at Madsen. Through 2024 the mine had  a Total Reportable Incident Frequency of 1.0, versus an Ontario mining  average of 4.53. The Company is committed to maintaining strong safety  practices every day at Madsen.
 
 “Restarting the  Madsen mine as a sustainable, efficient operation required a multitude  of projects,” said Mr. Williams. “I am proud to say that we delivered  every named project on or close to schedule, while also completing a  host of other requirements from staffing the mine to securing funding.  Collectively, these efforts have Madsen on track to start operating in  H2 2025, which is on the schedule we stated since the start.”
 
 QUALIFIED PERSON
 
 The  technical information presented in this news release has been reviewed  and approved by Maurice Mostert, P.Eng., Vice President of Technical  Services for West Red Lake Gold and the Qualified Person for technical  services at the West Red Lake Project, as defined by National Instrument  43-101 Standards of Disclosure for Mineral Projects.
 
 ABOUT WEST RED LAKE GOLD MINES
 
 West  Red Lake Gold Mines Ltd. is a mineral exploration company that is  publicly traded and focused on advancing and developing its flagship  Madsen Gold Mine and the associated 47 km2 highly prospective  land package in the Red Lake district of Ontario. The highly productive  Red Lake Gold District of Northwest Ontario, Canada has yielded over 30  million ounces of gold from high-grade zones and hosts some of the  world’s richest gold deposits. WRLG also holds the wholly owned Rowan  Property in Red Lake, with an expansive property position covering 31 km2 including three past producing gold mines – Rowan, Mount Jamie, and Red Summit.
 
 
 
  
 Madsen and Rowan Projects Location Map  ON BEHALF OF WEST RED LAKE GOLD MINES LTD.
 “Shane Williams”
 Shane Williams
 President & Chief Executive Officer
 
 FOR FURTHER INFORMATION, PLEASE CONTACT:
 Gwen Preston
 Vice President Communications
 Tel: (604) 609-6132
 Email:  investors@wrlgold.com or visit the Company’s website at globenewswire.com
 
 Neither  the TSX Venture Exchange nor its Regulation Services Provider (as that  term is defined in the policies of the TSX Venture Exchange) accepts  responsibility for the adequacy or accuracy of this release.
 
 CAUTIONARY STATEMENT AND FORWARD-LOOKING INFORMATION
 
 Certain  statements contained in this news release may constitute  “forward-looking information” within the meaning of applicable  securities laws. Forward-looking information generally can be identified  by words such as “anticipate”, “expect”, “estimate”, “forecast”,  “planned”, and similar expressions suggesting future outcomes or events.  Forward-looking information is based on current expectations of  management; however, it is subject to known and unknown risks,  uncertainties and other factors that may cause actual results to differ  materially from the forward-looking information in this news release and  include without limitation, statements relating to the plans  and timing for the potential production of mining operations at the  Madsen Mine, the potential (including the amount of tonnes of material  from the bulk sample program) of the Madsen Mine; the benefits of test  mining; any untapped growth potential in the Madsen deposit or Rowan  deposit; and the Company’s future objectives and plans. Readers are  cautioned not to place undue reliance on forward-looking information.
 
 Forward-looking  information involve numerous risks and uncertainties and actual results  might differ materially from results suggested in any forward-looking  information. These risks and uncertainties include, among other things,  market volatility; the state of the financial markets for the Company’s  securities; fluctuations in commodity prices; timing and results of the  cleanup and recovery at the Madsen Mine; and changes in the Company’s  business plans. Forward-looking information is based on a number of key  expectations and assumptions, including without limitation, that the  Company will continue with its stated business objectives and its  ability to raise additional capital to proceed. Although management of  the Company has attempted to identify important factors that could cause  actual results to differ materially from those contained in  forward-looking information, there may be other factors that cause  results not to be as anticipated, estimated or intended. There can be no  assurance that such forward-looking information will prove to be  accurate, as actual results and future events could differ materially  from those anticipated in such forward-looking information. Accordingly,  readers should not place undue reliance on forward-looking information.  Readers are cautioned that reliance on such information may not be  appropriate for other purposes. Additional information about risks and  uncertainties is contained in the Company’s management’s discussion and  analysis for the year ended November 30, 2023, and the Company’s annual  information form for the year ended November 30, 2023, copies of which  are available on SEDAR+ at www.sedarplus.ca.
 
 The  forward-looking information contained herein is expressly qualified in  its entirety by this cautionary statement. Forward-looking information  reflects management’s current beliefs and is based on information  currently available to the Company. The forward-looking information is  made as of the date of this news release and the Company assumes no  obligation to update or revise such information to reflect new events or  circumstances, except as may be required by applicable law.
 
 For  more information on the Company, investors should review the Company’s  continuous disclosure filings that are available on SEDAR+ at  www.sedarplus.ca.
 
 Photos accompanying this announcement are available at:
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 |