| Ivanhoe Mines Announces Restart of Underground Mining Operations on Western Side of Kakula Mine on 
 Underground water levels in Kakula Mine stabilized; dewatering to commence in Q3 2025
 
 Kamoa-Kakula revises 2025 production guidance to between 370,000 and 420,000 tonnes of copper
 
 Smelter start-up expected to commence in September 2025, with first anode anticipated in October 2025
 
 Ivanhoe Mines to host a conference call for investors before market open on June 12, 2025
 
 newsfilecorp.com
 
 June 7, 2025 June 11, 2025 4:39 PM EDT | Source:  Ivanhoe Mines Ltd.
 
 Kolwezi,  Democratic Republic of the Congo--(Newsfile Corp. - June 11, 2025) -  Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Executive Co-Chairman Robert  Friedland and President Marna Cloete announce today an update on  operational activities at the Kamoa-Kakula Copper Complex, including  preliminary geotechnical findings relating to underground seismic  activity experienced at the Kakula Mine, as first announced on  May 20, 2025.
 
 Underground  mining on the western side of the Kakula Mine has resumed in a safe and  conservative manner, with equipment and mining crews returning  underground on June 7, 2025. The short-term mine plan for the western  side of Kakula has been updated to include recommendations from the  preliminary findings.
 
 Mining activities in the eastern side of  the Kakula Mine are expected to start imminently, with activities solely  focused on developing access drives to a new mining area east of the  existing mine workings. Development to the new mining area will be  isolated from the dewatering activities on the same side of the mine.
 
 As announced on  June 2, 2025,  additional underground pumping capacity was installed at the Kakula  Mine, stabilizing underground water levels. The frequency of seismic  activity has decreased since first reported on May 18, 2025. Dewatering  the eastern side of the Kakula Mine is expected to commence in August  2025 and be complete during the fourth quarter.
 
 Recommendations  from the preliminary geotechnical findings from world-leading experts  have been included in the short-term mine plans for the Kakula Mine to  ensure a safe restart of underground operations. Concurrently, medium-  and long-term mine plans are under review by Kamoa-Kakula management,  together with technical consultants.
 
 The Phase 1 and 2  concentrators continue to operate at approximately 50% of their combined  operating capacity, processing ore from surface stockpiles. The  processing rate of the concentrators will ramp up throughout the  remainder of 2025, as mining on the western side of the Kakula Mine  increases, supplemented by feed from ore stockpiles. Mining operations  at the Kamoa underground mine, as well as ore processing at the adjacent  Phase 3 concentrator, continue to outperform.
 
 With the necessary  copper concentrate expected to be available, the on-site copper smelter  is anticipated to start up in September, with first anode expected in  October 2025.
 
 Ivanhoe Mines Executive Co-Chair, Robert Friedland commented:
 
 "We  are thankful and deeply appreciate our team's swift response to  stabilize underground water levels in the Kakula Mine and resume mining  on the western side. The team has quickly secured the critical equipment  needed to safely dewater the entirety of the mine, while preparing to  access a new high-grade mining area in the east.
 
 "While it's still  too early to outline our detailed plans for 2026 and 2027, the future  remains bright across the Kamoa-Kakula Copper Complex and adjacent  Western Forelands Exploration Project. Kamoa-Kakula is, and will  continue to be, a world-class Tier One operation, with decades ahead of  us as one of the world's leading copper producers."
 
 President & Chief Executive Officer, Marna Cloete, commented:
 
 "We  are working tirelessly to safely and systematically restore full  operations at the Kakula Mine. Safety has always been, and will always  remain, our highest priority. We want to extend our sincere thanks to  the mining crews, the engineering teams and our long-term contractors  for their extraordinary efforts in restoring pumping capacity and  restarting operations, all without any lost time injuries.
 
 "The  resilience of our team and the strength of our operations reflect the  extraordinary nature of this world-class copper district-and the future  it holds for generations to come."
 
 
  
 Figure  1. Outline of the Kakula and Kakula West orebody, overlaid with the  underground development since mining commenced in 2021. A significant  portion of the original Kakula deposit remains unmined as of May 2025.
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 Notes:  Existing underground development as at May 2025. Illustration is based  on the 2023 Kamoa-Kakula IDP showing the estimated average grade of each  vertical stack of blocks above a 2% total copper cut-off. A minimum  3-metre thickness is applied.
 
 Underground water levels in Kakula Mine have stabilized; underground mining recommences on the western side of Kakula
 
 Although  water inflow rates into the Kakula Mine modestly increased following  the initial seismic activity, they have since stabilized at  approximately 4,000 litres per second. With existing underground pumping  infrastructure impacted by the seismic activity, a total of  approximately 4,400 litres per second of additional underground pumping  capacity was installed, stabilizing underground water levels. The new  pump stations feed into the existing central pumping infrastructure,  where the water is then pumped to surface at four locations near the  bottom of the north and south twin declines, as shown in Figure 2.
 
 With  water levels stabilized, mining in the western side of the Kakula Mine  has restarted. Mobile equipment and mining crews, which were evacuated  from the mine on May 18, 2025, are returning underground, with the first  blast having occurred on June 7, 2025. Short-term mine plans have been  updated to include the recommendations from the preliminary geotechnical  findings. Kamoa-Kakula's mining crews aim to ramp up mining from the  western side of the Kakula Mine to approximately 300,000 tonnes per  month (3.6 million tonnes per year on an annualized basis) during the  second half of 2025, subject to underground conditions.
 
 For the  remainder of 2025, Kakula's underground mining crews will focus on three  activities: ramping up mining on the western side of the Kakula Mine;  developing a new mining area on the eastern side of the Kakula Mine; and  ramping up production from the Kamoa mining area.
 
 
  
 Figure  2: Overview of Kakula Mine's existing underground infrastructure,  showing current pumping rates, future pumping capacity and depth of mine  workings.
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 The  additional mining crews deployed to the Kamoa mining area,  approximately 10 kilometres north of Kakula, will assist the existing  teams with underground development, as well as decline development from  the construction of a new box cut planned at the Kansoko Mine. The new  box cut will enable increased production from Kansoko, providing an  additional source of ore for the Phase 1 and Phase 2 concentrators.
 
 Mining  crews to focus on new mining area in eastern side of Kakula;  development to commence imminently, isolated from dewatering activities
 
 Mining  in the eastern side of the Kakula Mine will follow a new mine plan,  prioritizing development to a new mining area further east, beyond the  existing mine workings. The new mining area will be separated from the  existing mine workings by a barrier pillar. The barrier pillar is  designed to protect the new mining area from any potential spread of  geotechnical instability from the existing mining area.
 
 Mining  crews will construct two new access drives to the new mining area, which  are expected to start imminently. The new access drives will be  developed simultaneously, advancing east from existing underground  infrastructure, as shown in Figure 2. Development to the new mining area  is expected to be conducted in both ore and waste and be completed in  the second quarter of 2026. The new development drives will be isolated  from the mine workings that being dewatered and will advance  independently of dewatering activities.
 
 Following the completion  of dewatering activities on the eastern side of Kakula, a physical  geotechnical inspection of the mine's existing workings will be  conducted, concluding the full assessment by the geotechnical experts.  The results of this assessment will determine the approach and extent of  mining in this area.
 
 As shown in Figure 2, the mine workings are  at their deepest on the eastern side of the mine and therefore  underground flooding is predominantly concentrated around this area. The  Kamoa-Kakula engineering team has a two-stage plan to dewater the  entire Kakula Mine.
 
 Stage One involves the installation of  additional temporary underground pumping infrastructure to stabilize and  maintain current water levels. Stage One was completed as announced on  June 2, 2025.
 
 Stage Two  involves the installation of high-capacity, submersible pumps, and new  permanent infrastructure to fully dewater the entire Kakula Mine from  surface. Kamoa Copper has ordered five high-capacity pumps, each rated  at 650 litres per second. Additional pumps will also be ordered as part  of the long-term pumping infrastructure plan. These pumps will be  deployed in pairs down existing shaft infrastructure, accessing the  deepest sections of the Kakula Mine as shown in Figure 2. Dewatering  activities are expected to commence in August 2025. Engineering crews  will refurbish underground pumping and ventilation infrastructure, as  well as complete geotechnical assessments, as water levels subside.  Dewatering of the entire Kakula Mine is expected to be complete during  the fourth quarter.
 
 
  
 Looking  south: The two existing shaft locations where the "Stage Two"  dewatering surface pumping infrastructure will be installed to dewater  the eastern side of the Kakula Mine. Water will be discharged into  existing surface water channels (right of picture).
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 
  
 Looking  north with the Phase 1 and 2 concentrators in the background: One of  the two shaft locations shown in the foreground that will be used for  the "Stage Two" dewatering of the deepest area of the Kakula Mine.
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 
  
 A  high-capacity submersible pump, similar to those being procured by  Kamoa Copper for dewatering the Kakula Mine, prior to being lowered down  a shaft at the Luansha Copper Mine, Zambia in September 2024. Photo  source: CNMC (China Nonferrous Metal Mining Group Co., Ltd).
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 Preliminary geotechnical findings on the cause of recent seismic activity
 
 Two  prominent, independent geotechnical engineering organizations, Beck  Engineering of New South Wales, Australia (Beck Engineering) and Open  House Management Solutions of Potchefstroom, South Africa (Open House),  were engaged and mobilized to Kamoa-Kakula shortly after seismic  activity was first detected on May 18, 2025. Both consulting engineering  firms have been working diligently with Kamoa-Kakula's engineering  team, with support from Ivanhoe Mines.
 
 Preliminary findings  indicate that the seismic activity originated in an area within the  eastern side of the Kakula Mine with a mature percentage of extraction.  Current thinking postulates that blocks of ore, earmarked for secondary  extraction, started to yield in a cascading fashion, which resulted in  stress redistribution onto regional pillars. As a consequence, the  regional pillars became over-stressed and started to yield. The  backfill, placed in mined-out stopes, was not capable of preventing the  stress redistribution onto regional support pillars, but may have been a  mitigant. The possibility that adverse regional geological features may  have exacerbated the yielding of regional pillars cannot be excluded at  this time. Pillars are sections of untouched ore or rock left in place  to support the roof of the mine, while stopes are mined-out areas.  Backfill is the process whereby mined-out stopes are filled with a  mixture of concentrator tailings and cement, which cures to achieve a  targeted strength.
 
 The geotechnical assessment has not yet been  finalized as it relies on physical access to the eastern section of the  Kakula Mine once dewatering is completed.
 
 The preliminary findings  recommend modifying the short-term mine plans to increase pillar widths  for additional structural support. The findings also advise changes to  the mining sequence to improve stress distribution and overall  stability. Furthermore, enhanced geotechnical monitoring will be  installed throughout the mine.
 
 Kamoa-Kakula's management,  together with Beck Engineering, Open House and other technical  consultants, are evaluating any changes to the short-, medium- and  long-term mine plans in light of these preliminary geotechnical  findings.
 
 Work on an updated life-of-mine integrated development  plan, which was underway before the seismic activity occurred, has been  paused until Ivanhoe Mines' engineering team and its panel of technical  experts have reviewed and agreed on any updated assumptions. Ivanhoe  Mines will provide a timing update on the delivery of an updated IDP  once work recommences.
 
 
  
 Members of Kamoa-Kakula's mining crew, (L-R) Kalume Malidja, Mining Foreman and Morné Du Plooy, Mining Superintendent
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 Phase  1 and 2 concentrators operating at reduced capacity and set to ramp up  as mining restarts on western side of the Kakula Mine; Phase 3  concentrator continues to outperform
 
 Crews recommenced mining  on the western side of Kakula on June 7, 2025. Mining from this section  will commence safely and conservatively, with planned ramp-up to an  annualized mining rate of 3.6 million tonnes during the third quarter.  This rate is sufficient for the Phase 1 and 2 concentrators to operate  at a throughput of more than 80% of their combined design capacity of  9.2 million tonnes per annum, supplemented by ore from surface  stockpiles and ore trucked from the Kamoa mines. Run-of-mine grade from  the western side of Kakula, including development, is expected to range  between 3.0% and 4.0% copper for the remainder of the year.
 
 The  Phase 1 and 2 concentrators continue to operate at approximately 50% of  their combined capacity, processing ore from surface stockpiles since  underground operations ceased on May 18, 2025.
 
 The Phase 3  concentrator, located adjacent to the Kamoa mines area as shown in  Figure 3, has continued to outperform operationally since the start of  the year. The concentrator is operating at an average annualized milling  rate of approximately 6.5 million tonnes per annum, which is 30% higher  than the concentrator's design capacity of 5 million tonnes per annum.  Year-to-date, ore processed by the Phase 3 concentrator has an average  feed grade of 2.84% copper. Mining from the Kamoa and Kansoko mines,  have ramped up over the past 2 months to a combined rate of over 6.8  million tonnes per annum on an annualized basis.
 
 Short-term mine  plans for the Kamoa and Kansoko mines have findings been updated to  include the recommendations from the preliminary geotechnical  assessment. Longer-term mine plans will be also be reviewed alongside  Kakula.
 
 
  
 Figure 3. Overview of the Kamoa-Kakula Copper Complex
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 Revised 2025 production guidance
 
 Kamoa-Kakula's  updated 2025 production guidance is based on several assumptions and  estimates as of June 10, 2025. The guidance provided involves estimates  of known and unknown risks, uncertainties, and other factors that may  cause the actual results to differ materially.
 
 The revised 2025  production guidance takes into account the probable effect of recent  seismic activity and associated interruptions in mining operations at  the Kakula Mine. Although mining in the western side of the Kakula Mine  has restarted risk factors remain, including; it is too early to  accurately predict potential disruption caused by further unexpected  seismic activity, the integrity of underground infrastructure, the  ability to ramp up underground operations, the ability to complete  dewatering activities and the time required to access the new mining  areas. The updated 2025 production guidance is based on an assessment of  these factors that management believes are reasonable at this time,  given all available information. A waterfall diagram shown in Figure 4  details a breakdown of the revised production guidance.
 
 
 | Revised 2025 Production Guidance |  | Kamoa-Kakula | 370,000 - 420,000 | Contained copper in concentrate (tonnes) | 
 
 All  figures are on a 100%-project basis and metal reported in concentrate  is before refining losses or payability deductions associated with  smelter terms.
 
 
  
 Figure  4. Waterfall breakdown of original to revised 2025 production guidance,  approximated by category ('000's tonnes of copper) with percentage  change shown in boxes
 
 To view an enhanced version of this graphic, please visit:
 images.newsfilecorp.com
 
 The  2026 target of approximately 600,000 tonnes of copper production is  withdrawn pending further review. Ivanhoe Mines will provide a timely  update on the 2026 target production rate when more information becomes  available.
 
 Ivanhoe Mines will provide updated 2025 C1 cash cost  (C1) per pound of payable copper in the second quarter of 2025 financial  results.
 
 On-site direct-to-blister smelter to start up in third quarter
 
 Kamoa-Kakula's  senior management has confirmed that the start-up of the on-site  direct-to-blister copper smelter will commence in early September 2025,  with first anode expected in October. The smelter can operate at a  minimum operating capacity of 50%, or approximately 250,000 tonnes of  copper on an annualized basis.
 
 As at May 31, 2025, unsold  concentrate stockpiles consisted of 33,000 tonnes of copper. In  preparation for the first feed of concentrate, approximately four to six  weeks after start-up commences, it is expected that total unsold  concentrate stockpiles will be approximately 35,000 tonnes of copper in  concentrate.
 
 In addition, Kamoa-Kakula's senior management  anticipates the commissioning of the 178-megawatt Turbine #5 at the Inga  II hydroelectric dam in October 2025, further boosting domestically  generated hydroelectricity supplied to the Kamoa-Kakula Copper Complex.
 
 Ivanhoe Mines to host a conference call for investors on June 12, 2025
 
 The  company will hold an investor conference call to discuss the  operational update at Kamoa-Kakula before the market opens on June 12,  2025, at 8:00 a.m. Eastern time / 5:00 a.m. Pacific time. The conference  call will conclude with a question-and-answer (Q&A) session. Media  are invited to attend on a listen-only basis.
 
 To view the webcast, use the link: api.newsfilecorp.com
 
 Audience Phone Number:
 (+1) 647 951 0841 (Toll, for international callers)
 (+1) 888 985 7261 (Toll-Free North America)
 
 An  audio webcast recording of the conference call, together with  supporting presentation slides, will be available on Ivanhoe Mines'  website at  www.ivanhoemines.com.
 
 Disclosure of Technical Information
 
 Disclosures  of a scientific or technical nature in this news release, other than  the preliminary geotechnical findings and the technical information in  Figure 1, have been reviewed and approved by Steve Amos, who is  considered, by virtue of his education, experience, and professional  association, a Qualified Person under the terms of NI 43-101. Mr. Amos  is not considered independent under NI 43-101 as he is Ivanhoe Mines'  Executive Vice President, Projects. Mr. Amos has verified the technical  data disclosed in this news release.
 
 Disclosures of a scientific  or technical nature regarding the preliminary geotechnical findings in  this news release have been reviewed and approved by Koos Bosman, who is  considered, by virtue of his education, experience, and professional  association, a Qualified Person under the terms of NI 43-101. Mr. Bosman  is considered independent of the company for purposes of NI 43-101 as  he is Managing Director of Open House. Mr.  Bosman has verified the  technical data regarding the preliminary geotechnical findings disclosed  in this news release.
 
 Disclosures of a scientific or technical  nature in Figure 1 of this news release have been reviewed and approved  by Joshua Chitambala, who is considered, by virtue of his education,  experience, and professional association, a Qualified Person under the  terms of NI 43-101. Mr. Chitambala is not considered independent under  NI 43-101 as he is the Resource Manager for Ivanhoe Mines. Mr.  Chitambala has verified the other technical data regarding the surface  stockpiles disclosed in this news release.
 
 About Ivanhoe Mines
 
 Ivanhoe  Mines is a Canadian mining company focused on advancing its three  principal projects in Southern Africa; the expansion of the Kamoa-Kakula  Copper Complex in the DRC, the ramp-up of the ultra-high-grade Kipushi  zinc-copper-germanium-silver mine, also in the DRC; and the phased  development of the tier-one Platreef  platinum-palladium-nickel-rhodium-gold-copper Mine in South Africa.
 
 Ivanhoe  Mines is exploring for copper in its highly prospective, 54-100% owned  exploration licences in the Western Forelands, covering an area over six  times larger than the adjacent Kamoa-Kakula Copper Complex, including  the high-grade discoveries in the Makoko District. Ivanhoe is also  exploring for new sedimentary copper discoveries in new horizons  including Angola, Kazakhstan, and Zambia.
 
 Follow Robert Friedland ( @robert_ivanhoe) and Ivanhoe Mines ( @IvanhoeMines_) on X.
 
 Information contact
 
 Investors
 Vancouver: Matthew Keevil +1.604.558.1034
 London: Tommy Horton +44 7866 913 207
 
 Media
 Tanya Todd +1.604.331.9834
 
 Forward-Looking Statements
 
 Certain  statements in this news release constitute "forward-looking statements"  or "forward-looking information" within the meaning of applicable  securities laws. Such statements and information involve known and  unknown risks, uncertainties, and other factors that may cause the  actual results, performance, or achievements of the company, its  projects, or industry results to be materially different from any future  results, performance, or achievements expressed or implied by such  forward-looking statements or information. Such statements can be  identified using words such as "may", "would", "could", "will",  "intend", "expect", "believe", "plan", "anticipate", "estimate",  "scheduled", "forecast", "predict" and other similar terminology, or  state that certain actions, events, or results "may", "could", "would",  "might" or "will" be taken, occur or be achieved. These statements  reflect the company's current expectations regarding future events,  performance, and results and speak only as of the date of this news  release.
 
 Such statements include, without limitation: (i)  statements that development from existing underground infrastructure  toward a new mining area in the eastern side of the Kakula is expected  to commence imminently, and that this development will be isolated from  the dewatering activities; (ii) statements that dewatering of the  eastern side of the Kakula Mine is expected to commence by the end of  August 2025 and be complete during the fourth quarter; (iii) statements  that the processing rate of the concentrators will ramp up throughout  the remainder of 2025, as mining on the western side of the Kakula Mine  increases, supplemented by feed from ore stockpiles; (iv) statements  that, with necessary copper concentrate expected to be available, the  on-site copper smelter is expected to start up in the third quarter,  with first anode expected in October; (v) statements that Kamoa-Kakula's  mining crews aim to ramp up mining from the western side of the Kakula  Mine to approximately 300,000 tonnes per month (3.6 million tonnes per  year on an annualized basis) during the second half of 2025, subject to  underground conditions; (vi) statements that for the remainder of 2025,  Kakula's underground mining crews will focus on the following three  activities: ramping up mining on the western side of the Kakula Mine,  developing a new mining area on the eastern side of the Kakula Mine and  ramping up production from the Kamoa mining area; (vii) statements that  the new box cut at Kansoko will enable increased production from  Kansoko, providing an additional source of ore for the Phase 1 and Phase  2 concentrators; (viii) statements that development of a new mining  area on eastern side of the Kakula Mine will commence imminently; (ix)  statements that development of the new mining area is expected to be  conducted in a mix of ore and waste and be completed in the second  quarter of 2026; (x) statements that following the completion of  dewatering activities on the eastern side of Kakula, a physical  geotechnical inspection of the mine's existing workings will be  conducted, concluding the full assessment by the geotechnical experts;  (xi) statements regarding additional pumps being ordered as part of the  long-term pumping infrastructure plan and such pumps being deployed in  pairs; (xii) statements that delivery, installation, and commissioning  of the surface dewatering infrastructure is expected by mid-September;  (xiii) statements regarding the impact of the preliminary assessment on  the mine plan at Kakula, Kamoa and Kansoko; (xiii) production guidance  for Kamoa Kakula for 2025; (xiv) statements that ore from the western  side of Kakula is expected to deliver a head grade ranging between 3.0%  and 4.0% copper; (xv) statements that the smelter's minimum operating  capacity is 50%, or approximately 250,000 tonnes of copper on an  annualized basis; (xvi) statements that Kamoa-Kakula's senior management  anticipates the commissioning of the 178-megawatt Turbine #5 at the  Inga II hydroelectric dam in September, further boosting domestically  generated hydroelectricity to the Kamoa-Kakula Copper Complex; and (xv)  statements regarding the locations where the "Stage Two" dewatering  surface pumping infrastructure will be installed to dewater the eastern  side of the Kakula Mine and that water will be discharged into existing  surface water channels.
 
 Forward-looking statements and information  involve significant risks and uncertainties, should not be read as  guarantees of future performance or results, and will not necessarily be  accurate indicators of whether such results will be achieved. Many  factors could cause actual results to differ materially from the results  discussed in the forward-looking statements or information, including,  but not limited to: (i) uncertainty around the rate of water ingress  into underground workings; (ii) the ability, and speed with which,  additional equipment can be secured; (iii) the continuation of seismic  activity; (iv) the state of underground infrastructure; (v) uncertainty  around when future underground access can be secured; (vi) the fact that  future mine stability cannot be guaranteed; (vii)  the fact that future  mining methods, may differ the impact on Kakula operations; and (viii)  the ultimate conclusion of the assessment of the cause of the seismic  activity at Kakula and the impact of same on the mining plan at the  Kamoa Kakula Copper Complex. Additional factors also include those  discussed above and under the "Risk Factors" section in the company's  MD&A for the three months ended March 31, 2025, and its current  annual information form, and elsewhere in this news release, as well as  unexpected changes in laws, rules or regulations, or their enforcement  by applicable authorities; changes in the rate of water ingress into  underground workings; the continuation of seismic activity; the state of  underground infrastructure; delays in securing underground access;  changes to the mining methods required in the future; the failure of  parties to contracts with the company to perform as agreed; social or  labour unrest; changes in commodity prices; and the failure of  exploration programs or studies to deliver anticipated results or  results that would justify and support continued exploration, studies,  development or operations.
 
 Although the forward-looking statements  contained in this news release are based upon what management of the  company believes are reasonable assumptions, the company cannot assure  investors that actual results will be consistent with these  forward-looking statements. These forward-looking statements are made as  of the date of this news release and are expressly qualified in their  entirety by this cautionary statement. Subject to applicable securities  laws, the company does not assume any obligation to update or revise the  forward-looking statements contained herein to reflect events or  circumstances occurring after the date of this news release.
 
 The  company's actual results could differ materially from those anticipated  in these forward-looking statements as a result of the factors outlined  in the "Risk Factors" section in the company's MD&A for the three  months ended March 31, 2025, and its current annual information form.
 
 
  SOURCE:  Ivanhoe Mines Ltd. |