Robex remains on track for first gold at Kiniero in Q4 2025 
  globenewswire.com
  June 13, 2025 06:28 ET                                 | Source:                                Robex Resources Inc.
   Highlights:
      - Construction at Robex’s Kiniero Gold Project, Guinea, remains on schedule and budget with first gold pour on track for Q4 2025.
 - Project remains LTI free (lost time injury).
 - All project engineering and detail design completed.
 - Phase  1 grade control drilling of Mansounia pit continues, with 55,430m  drilled and 61,520 samples collected. Mansounia drilling to be completed  by end of June, with drilling to commence at the Sabali pit.
 - SMP (Structural, Mechanical & Piping) works commenced, with 115 tonnes erected in the milling building and pipe racks.
 - All  purchase orders for mechanical and electrical equipment, piping and  electrical materials completed and on track for delivery, including 90%  of power station materials collected and shipped.
 - Process plant concrete is approximately 95% complete and power station concrete 32% complete.
 - Structural  steel and platework fabrication at 89% and 90% complete respectively,  with 11 shipments of structural steel and four shipments of platework in  transit to Kiniero. All fabrication is to be completed ahead of  schedule.
 - Field tank structures 64% completed. CIL Tank Train A is completed with CIL Tank Train B due for completion mid-July 2025.
 - Preparation of Phase 1A of the tailings storage facility base is nearing completion, with 625,607m2 of 800,000m2 liner placed.
 - Fuel supply contract was awarded and construction of the fuel storage facility commenced.
 - Mill installation contract awarded, and the installation team is mobilising to site.
 - Contracts for mining and drill and blast to be signed this month, with mobilisation commenced. ROM pad backfilling completed.
 - Geotechnical drilling for a solar farm commenced.
      QUEBEC CITY, June  13, 2025  (GLOBE NEWSWIRE) -- West African gold producer and developer Robex Resources Inc (“Robex” or the “Company”)  (ASX: RXR | TSX-V: RBX | OTC: RSRBF | Börse Frankfurt: RB4) is pleased  to provide a June 2025 project construction update for its Kiniero Gold  Project in Guinea, West Africa. Robex is on track to deliver first gold  at Kiniero in Q4 2025.
      
  
      Figure 1: Aerial view of the Kiniero site showing process plant and infrastructure (9 June 2025)
      
  
      Figure 2: View of Milling building showing erection of steel (7 June 2025)
      
  
      Figure 3: View of CIL with main pipe rack steel erection of steel (11 June 2025)
      
  
      Figure 4: Tailings storage facility showing the extent of lining and main embankment construction (7 June 2025)
      
  
      Figure 5: View of the Milling and CIL looking west (7 June 2025)
      Robex’s Managing Director and Chief Executive Officer Matthew Wilcox said: “Kiniero  is moving closer to completion each month, and it is so pleasing to see  this progress continue in a safe and methodical manner, maintaining our  schedule to achieve first gold in Q4 2025. We’ve ordered everything we  need for the project and deliveries of materials are arriving at site on  a regular basis to ensure we continue to meet our targets. Design is  complete and many aspects of the project build are underway or nearing  completion. 
      Grade control drilling  is progressing well and will provide us with important data for mine  planning at Mansounia before we head to the Sabali pit to continue this  work. 
      Having completed our Initial  Public Offer to raise A$120 million, followed by our successful listing  on the ASX earlier this month, we are renewed in our efforts to deliver  Shareholder value through Kiniero and Nampala, and look forward to  providing further updates on Kiniero’s progress as we get closer to  pouring first gold.”
      Kiniero Construction Activities
      Construction  at Kiniero continues to track well against the schedule, with the  majority of concrete for the process plant completed. Three shipments of  structural steel arrived on site, with progressive deliveries scheduled  to arrive every two weeks. The SMP contractor has commenced structural  steel erection of the milling building and pipe racks. The milling  installation crew has commenced mobilisation to site with erection to  begin mid-June 2025. The tailings dam construction is progressing well,  with 78% of the phase 1A lining completed.
      
  
      Figure 6: Primary crusher ROM pad and chamber (7 June 2025)
      
  
      Figure 7: View of reclaim chamber (7 June 2025)
      
  
      Figure 8: Five out of eight power station generator bases have been poured (7 Jun 2025)
      
  
      Figure 9: Power station engines collected and loaded into charter vessel (7 June 2025)
      
  
      Figure 10: Power Station ancillary equipment loaded into charter vessel (7 June 2025)
      Next Steps
      - Complete final two remaining major concrete pours within the process plant by end of June 2025.
 - Complete Tailings Storage Dam phase 1A lining by end of June 2025.
 - Commence mill installation works on site.
 - Continue with erection of steelwork within the process plant.
 - Commence overland piping installation.
 - Commence grade control drilling of Sabali pit.
 - Execute contracts for mining and drill and blast on customary terms for the nature of these services.
 - Award the ore haulage contract.
 - Award the laboratory and power station operation and maintenance contracts.
 - Procure critical, operating and maintenance spares.
      Robex  remains very well positioned to advance the construction of Kiniero,  which remains on schedule to realise first gold production by Q4 2025.
      This announcement was approved by the Managing Director.
      Neither  the TSX Venture Exchange nor its Regulation Services Provider (as that  term is defined in the policies of the TSX Venture Exchange) accepts  responsibility for the adequacy or accuracy of this release.
  Robex Resources Inc.  Matthew Wilcox, Managing Director and Chief Executive Officer  Alain William, Chief Financial Officer  Email:  investor@robexgold.com   www.robexgold.com
      Investors and Media: Nathan Ryan NWR Communications +61 420 582 887  nathan.ryan@nwrcommunications.com.au
      FORWARD-LOOKING INFORMATION AND FORWARD-LOOKING STATEMENTS
      Certain  information set forth in this news release contains “forward-looking  statements” and “forward-looking information” within the meaning of  applicable securities legislation (referred to herein as  “forward-looking statements”). Forward-looking statements are included  to provide information about the Company’s management’s (“Management’s”)  current expectations and plans that allow investors and others to have a  better understanding of the Company’s business plans and financial  performance and condition.
      Statements made  in this news release that describe the Company’s or Management’s  estimates, expectations, forecasts, objectives, predictions, projections  of the future or strategies may be “forward-looking statements”, and  can be identified by the use of the conditional or forward-looking  terminology such as “aim”, “anticipate”, “assume”, “believe”, “can”,  “contemplate”, “continue”, “could”, “estimate”, “expect”, “forecast”,  “future”, “guidance”, “guide”, “indication”, “intend”, “intention”,  “likely”, “may”, “might”, “objective”, “opportunity”, “outlook”, “plan”,  “potential”, “should”, “strategy”, “target”, “will” or “would” or the  negative thereof or other variations thereon. Inherent in  forward-looking statements are risks, uncertainties and other factors  beyond the Company’s ability to predict or control.
      Specific forward-looking statements
      Forward-looking  statements and forward-looking information are made based upon certain  assumptions and other important factors that, if untrue, could cause the  actual results, performance or achievements of the Company to be  materially different from future results, performance or achievements  expressed or implied by such statements or information. There can be no  assurance that such statements or information will prove to be accurate.  Such statements and information are based on numerous assumptions,  including: the ability to execute the Company’s plans relating to the  Kiniero Gold Project as set out in the feasibility study with respect  thereto, as the same may be updated, the whole in accordance with the  revised timeline previously disclosed by the Company; the Company’s  ability to complete its planned exploration and development programs;  the absence of adverse conditions at the Kiniero Gold Project; the  absence of unforeseen operational delays; the absence of material delays  in obtaining necessary permits; the price of gold remaining at levels  that render the Kiniero Gold Project profitable; the Company’s ability  to continue raising necessary capital to finance its operations; the  ability of the Company to realize on the mineral resource and mineral  reserve estimates; assumptions regarding present and future business  strategies, local and global geopolitical and economic conditions and  the environment in which the Company operates and will operate in the  future; and the Company’s access to the facility made available under  the Sprott Facility Agreement (as detailed in the replacement prospectus  dated 6 May 2025 and lodged with ASX on 3 June 2026) (Facility Agreement).
      Risks
      Although  the Company believes the expectations expressed in such forward-looking  statements are based on reasonable assumptions, such forward-looking  statements involve known and unknown risks, uncertainties and other  factors, which may cause the Company’s actual results, performance or  achievements to differ materially from those expressed or implied by  such forward-looking statements. Factors that could cause actual results  to differ materially from those expressed or implied by such  forward-looking statements include, but are not limited to: the risk  that the Company is unable to fulfil the conditions precedent to  drawdowns under the , and is therefore not able to borrow some or all of  the principal amount otherwise available under the Facility Agreement;  the risk that the Company is unable to generate sufficient cash flow or  complete subsequent debt or equity financings to allow it to repay  amounts borrowed under the Facility Agreement; the risk that the  obligors under the Facility Agreement are unable to comply with the  financial and other covenants under the Facility Agreement, giving rise  to an event of default; geopolitical risks and security challenges  associated with its operations in West Africa, including the Company’s  inability to assert its rights and the possibility of civil unrest and  civil disobedience; fluctuations in the price of gold; uncertainties as  to the Company’s estimates of mineral reserves and mineral resources;  the speculative nature of mineral exploration and development; the  replacement of the Company’s depleted mineral reserves; the Company’s  limited number of projects; the risk that the Kiniero Gold Project will  never reach the production stage; the Company’s capital requirements and  access to funding; changes in legislation, regulations and accounting  standards to which the Company is subject, including environmental,  health and safety standards, and the impact of such legislation,  regulations and standards on the Company’s activities; equity interests  and royalty payments payable to third parties; price volatility and  availability of commodities; instability in the global financial system;  uncertainty surrounding the imposition of tariffs by one country,  including, but not limited to, the United States, on goods or services  being imported into that country from another country and the ultimate  effect of such tariffs on the Company’s supply chains; the effects of  high inflation, such as higher commodity prices; fluctuations in  currency exchange rates, particularly as between the Canadian dollar, in  which the Company presently raises its equity financings, and the US  dollar; the risk of any pending or future litigation against the  Company; limitations on transactions between the Company and its foreign  subsidiaries; volatility in the market price of the Company’s  securities; tax risks, including changes in taxation laws or assessments  on the Company; the Company obtaining and maintaining titles to  property as well as the permits and licenses required for the Company’s  ongoing operations; changes in project parameters and/or economic  assessments as plans continue to be refined; the risk that actual costs  may exceed estimated costs; geological, mining and exploration technical  problems; failure of plant, equipment or processes to operate as  anticipated; accidents, labour disputes and other risks of the mining  industry; delays in obtaining governmental approvals or financing; the  effects of public health crises on the Company’s activities; the  Company’s relations with its employees and other stakeholders, including  local governments and communities in the countries in which it  operates; the risk of any violations of applicable anticorruption laws,  export control regulations, economic sanction programs and related laws  by the Company or its agents; the risk that the Company encounters  conflicts with small-scale miners; competition with other mining  companies; the Company’s dependence on third-party contractors; the  Company’s reliance on key executives and highly skilled personnel; the  Company’s access to adequate infrastructure; the risks associated with  the Company’s potential liabilities regarding its tailings storage  facilities; supply chain disruptions; hazards and risks normally  associated with mineral exploration and gold mining development and  production operations; problems related to weather and climate; the risk  of information technology system failures and cybersecurity threats;  and the risk that the Company may not be able to insure against all the  potential risks associated with its operations.
      Although  the Company believes its expectations are based upon reasonable  assumptions and has attempted to identify important factors that could  cause actual actions, events or results to differ materially from those  described in forward-looking information, there may be other factors  that cause actions, events or results not to be as anticipated,  estimated or intended. These factors are not intended to represent a  complete and exhaustive list of the factors that could affect the  Company; however, they should be considered carefully. There can be no  assurance that forward-looking information will prove to be accurate, as  actual results and future events could differ materially from those  anticipated in such information.
      See also  the “Risk Factors” section of the Company’s Annual Information Form,  available under the Company’s profile on SEDAR+ at  www.sedarplus.ca  or on the Company’s website at www.robexgold.com, for additional  information on risk factors that could cause results to differ  materially from forward-looking statements. All forward-looking  statements contained in this news release are expressly qualified by  this cautionary statement.
      Additional Updates
      All  of the forward-looking statements contained in this news release are  given as of the date hereof and are based upon the opinions and  estimates of Management and information available to Management as at  the date hereof.
      The Company disclaims any  intention or obligation to update forward-looking information if  circumstances or Management’s estimates, assumptions or opinions should  change, except as required by applicable law. If the Company does update  one or more forward-looking statements, no inference should be drawn  that it will make additional updates with respect to those or other  forward-looking statements. The reader is cautioned not to place undue  reliance on forward-looking information.
      Figures accompanying this announcement are available at: globenewswire.com |