RAK - news day Rackla Metals is pleased to provide an update on drilling at Grad and other developments on property holdings in the NWT Aug 19, 2025
Vancouver, British Columbia – August 19, 2025 – Rackla Metals Inc. (TSX-V: RAK) (the “Company”) is pleased to announce that the Company continues to make good progress on its 2025 exploration program in western NWT. The drill plan has been increased by 25% to 5,000m due to encouraging observations in the drill core and surface work that has extended the mineralized zone at the BiTe showing significantly to the west and at depth.
- The drill is presently on hole G25-008, with a target depth of 500m.
| - Abundant sheeted veining has been observed in all drill holes completed to date.
- Bismuth sulphide mineralization has also been observed in all holes.
- Samples from holes G25-001 through 007 have been submitted to the lab and the Company awaits the analytical results.
- Based upon the results of the regional exploration program the Company has increased land holdings in the region.
| As of August 18th, over 3,100m have been drilled with 7 holes completed, testing an area measuring 500 x 300 x 550 m. The drill is currently on hole G25-008.
All holes drilled to date have intersected a consistent set of sheeted quartz/sulphide+tourmaline veins throughout their length. A broad zone with intense quartz and quartz-tourmaline veining and elevated bismuth content was intersected at the top of holes G25-004 and 005. This zone has been intersected in holes G25-006 and 007, 125m west of G25-004 and 005. The zone shows good continuity and appears robust with increasing strength and width as the intercepts get deeper. Hole G25-008 is targeting the same zone north of the intercept in holes G25-006 and 007.
Figure 1 – Map of the BiTe zone with the trace of drill holes G25-001 to 007 with vein density counts.
Figure 2 – Cross section through holes G25-004, G25-006, G25-007 and the bottom of hole G25-002 (section slice is 60 m wide).
Completed holes G25-001 to 007 are at the lab, with results from holes G25-001 to 003 expected within the coming week. We expect a steady flow of results following that.
Diamond drill hole collar information.
| Hole | Easting | Northing | Elevation | Dip | Azimuth | Depth (m) | | G25-001 | 517697 | 6959397 | 1805 | -50 | 88 | 208.79 | | G25-002 | 517697 | 6959397 | 1805 | -50 | 78 | 336.70 | | G25-003 | 517712 | 6959342 | 1781 | -50 | 90 | 425.20 | | G25-004 | 517637 | 6959447 | 1803 | -50 | 90 | 416.05 | | G25-005 | 517637 | 6959447 | 1803 | -50 | 60 | 431.20 | | G25-006 | 517504 | 6959464 | 1765 | -50 | 90 | 516.64 | | G25-007 | 517504 | 6959464 | 1765 | -70 | 90 | 537.97 | | G25-008 | 517504 | 6959464 | 1765 | -50 | 60 | underway |
Rackla continues working from the ridge, sampling the north, south and west face of the cliff above BiTe. Recent mapping is indicating a metal zonation with the large gossanous zone on the ridge top being arsenic-rich, and the topographically lower west and east ridges being bismuth-rich (assays pending). This zonation is believed to indicate that the ridge top has seen very little erosion, and the carapace zone is mostly intact based on the Reduced Intrusion-Related Gold System model.
Figure 3. Map of completed diamond drill holes and planned future holes as of August 18th.
Rackla is working in consultation with the Sahtu Dene and Métis communities and remains committed to maintaining the respectful, collaborative relationships we’ve built with the Sahtu. As we advance exploration at the Grad Project, we will continue working closely with local stakeholders and regulatory agencies to ensure our activities create long-term value and reflect community priorities.
|