SI
SI
discoversearch

We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Electron Energy Storage

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: Eric8/24/2025 8:33:00 AM
   of 962
 
Markets

Argentina’s oversubscribed BESS tender draws record-low bids

The Argentine Energy Secretariat has received significantly more bids than expected for its public call to install large-scale battery energy storage systems (BESS) in the Buenos Aires metropolitan area (AMBA). Although the tender aimed for 500MW, the AlmaGBA procurement drew proposals totaling 1,347MW on the back of highly competitive pricing and strong industry interest.



By
Luis Ini

Aug 22, 2025


Image: Gobierno de la Ciudad Autónoma de Buenos Aires


The Argentine Energy Secretariat has received bids for its open national and international call to install large-scale battery storage systems (BESS) in the Buenos Aires Metropolitan Area (AMBA). Although the target was 500MW, the tender attracted 27 proposals from 15 companies, totaling 1,347MW – far exceeding expectations.

Competition proved intense. Argentina’s wholesale electricity market administrator CAMMESA’s specifications had set a reference price of $15,000/MW/month, but most bids came in well below that level. The government had established an award threshold at 94% of the reference price – around $14,100/MW/month – but exceptionally competitive bids led to an expansion of the award capacity

Of the 27 proposals, seven were selected, mainly companies with a strong market presence:
  • Central Puerto emerged as the standout: it offered 150MW at $10,161/MW/month—nearly 40% below the reference price. Another 55MW project through its subsidiary, Central Costanera, was awarded at $11,147/MW/month.
  • MSU Green Energy was awarded 150MW at $11,290/MW/month
  • Southern Wind secured contracts at $11,461/MW/month
  • Genneia and Coral Energía (part of the Corven Group) also won bids.
Other companies that had offered significant volumes, such as Sullair Argentina (144 MW), were not selected.

Awarded prices ranged from $10,161 to $12,400/MW/month, with a weighted average of $11,336/MW/month.

The Edenor concession area will host 440?MW, while Edesur will receive 77?MW.

This AlmaGBA tender signifies a transformation in Argentina’s Wholesale Electricity Market (MEM). For the first time, contracts are being signed directly between generators and distributors, with CAMMESA serving as guarantor—not as offtaker.

The procurement seeks to strengthen critical AMBA nodes, improve network reliability, and encourage private sector restructuring.

Next steps The official schedule states that:
  • August 29: Projects will be formally awarded.
  • September 5: Contracts will be signed.
  • January 1, 2027: The awarded projects must begin operating.
  • December 31, 2028: Final commissioning deadline
Each contract will be valid for 15 years from the date it enters into commercial operation.

From pv magazine LatAm

ess-news.com

Report TOU ViolationShare This Post
 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext