| West Red Lake Gold Reports Third Quarter Operations Update for Madsen Mine Ramp-Up 
 ca.finance.yahoo.com
 
 West Red Lake Gold Mines Ltd.
 Tue, October 7, 2025 at 12:30 a.m. PDT 8 min read
 WRLGF
 -0.01%
 
 WRLRF
 
 
 RGLD.CN
 +20.00%
 
 
 WRLG.V
 0.00%
 
 VANCOUVER, British Columbia, Oct. 07, 2025 (GLOBE NEWSWIRE) -- West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or “WRLG” or the “Company”) (TSXV: WRLG) (OTCQB: WRLGF) is pleased to provide a third quarter (“Q3”) update on the ramp-up of the Madsen Mine located in the Red Lake Gold District of Northwestern Ontario, Canada.
 
 
 
 “Ramp  up at the Madsen mine is progressing well,” said Shane Williams,  President and CEO. “It is exciting to see tonnages rise, efficiencies  increase, and gold production grow quarter by quarter, as planned.”
 
 “It  takes a methodical approach to step a mine towards steady state  operations, ramping up daily mining while completing final  infrastructure projects and underground development needs, and at Madsen  we are now seeing the benefits of such an approach. Operational  performance at the mine in Q3 continued within the expected range.  Importantly, key parameters remained consistent, including ongoing  strong reconciliation between planned and actual gold grades in modeled  tonnes, and certain capital projects are starting to have notable  positive impacts. I am excited to see the final pieces of this operation  come into place over the fourth quarter, positioning Madsen for  commercial production in early 2026.”
 
 
 
 In  Q3 the Madsen Mine produced 35,700 tonnes of ore at an average grade of  5.4 grams per tonne gold. The mill poured 7,055 ounces of gold. Note  that mined and poured ounces do not align because of factors including  month end timings and gold in circuit. Those ounces were sold at an  average price of US$3,456 per ounce for gross proceeds of CAD$33  million.
 
 This compares to 5,260 ounces of  gold poured in Q2 for gross proceeds of CAD$24 million and 496 ounces of  gold in Q1 for gross proceeds of CAD$2.1 million. Q3 gold production  represented a 34% increase over Q2 gold production, a rate that  positions Madsen to reach targeted output levels early in 2026.
 
 Mined  ore tonnage is increasing month over month, within the variability of  mine ramp up. Increasing daily mined tonnage is the primary ramp-up  factor at Madsen, so the Company is pleased to report ore tonnage rising  consistently.
 
 
 
 
  
 figure 1    Figure 1. Ore tonnes mined at Madsen on a monthly basis from December 2024 through September 2025.
 
 Mined  waste development is also progressing as planned, as crews drive access  to new areas for drilling and mining. Importantly, as of mid-September  mined waste is now being stored largely underground.
 
 The  underground waste rock storage program is a key de-bottlenecking effort  recently in effect and is directly supporting the mine’s ability to  move ore tonnes. In the second half of September the mine moved over  1,000 tonnes of ore per day on several days, including a record day  moving 1,400 tonnes. This new ability to store all waste rock  underground, which has shifted trucking capacity away from waste haulage  to ore haulage, bodes well for production.
 
 
 In  terms of processed tonnes, variability was part of the ramp-up plan. To  test the mill’s ability to run at higher throughputs, in June and July  the mill was fed a combination of mined and stockpiled tonnes. Since the  start of August, the mill has only processed direct mined tonnes.  Madsen’s gold output is now a clear representation of what the mine is  producing as the operation progresses towards operational stability.
 
 Focus  during Q3 was on balancing the competing priorities of ramp-up projects  and regular mining operations. For instance, the need to develop a  secondary egress from a key mining complex impacted ore production in  August while work on underground power distribution impacted mining  optionality in September. The Company also managed labour force  availability impacts stemming from the June mine site incident.
 
 Reconciliation  between modeled and actual mined grades remains strong. Figure 2 below  shows a comparison of modeled versus actual longhole stope grades. Note  that sill development contributed 25 to 30% of milled tonnage over the  quarter; Figure 2 does not consider sill tonnes and grade. See Figure 3  for sill grade data.
 
 
 
  
 figure 2
 
 Figure  2: Comparison of modeled versus actual gold grade in mined longhole  stopes. Note this chart does not include sill tonnes and grade.
 
 Sill development tonnes continue to outperform on grade. In Q3, mined sill tonnes averaged 8.8 g/t gold.
 
 
 
  
 figure 3  Figure 3. Sill development gold grade and ounce production at the Madsen Mine.
 
 Equipment  availability has improved over the quarter as maintenance systems  ramped up. The maintenance team is keeping availabilities for haul  trucks, scoops, jumbo drills, and other equipment at target levels.
 
 Pathway to Commercial Production
 
 During  the quarter West Red Lake Gold defined the operational components the  Company aims to implement before declaring commercial production. With  the mine seeing good progress on staffing, the geology-engineering  workflow producing good reconciliation and grounding an achievable  detailed mine plan, the mill returning strong and consistent recoveries,  and other components from maintenance to water treatment also ramping  up as expected, focus with respect to commercial production went to  operational components, including:
 
 
 Storage of waste rock in historic underground voids. The  Madsen Mine produced approximately 2 million ounces of gold from 1936  to 1972. Many mined-out stopes were backfilled, but several large  historic stopes were left void. As West Red Lake Gold advances deeper  into the mine, such stopes are verified and measured. It was determined  that the 1136 void, which is proximal to the 1155 mining complex that is  providing 40% of mine’s produced ounces in H2 2025, is significantly  larger than expected (65,000 tonnes versus an initial expectation of  34,000 tonnes). It is also a competent void. As a result, this area is  now being utilised to store waste rock utilising a combination of  cemented rock fill (“CRF”) and dumped waste rock, at rates up to 2,000  tonnes per day.
 
 
 Since  getting this waste storage process operational in mid-September, ore  production from the mine has increased because of increased truck  availability and ventilation capacity.
 
 
 Once  these components are installed, the Company expects to start moving 350  tonnes of ore out of the mine each day through the shaft. This is  expected to provide notable benefit over trucking these tonnes in terms  of cost savings and ventilation capacity.Skipping 350 tonnes per day up the shaft.  The Madsen Shaft was developed in the 1950s; the Company rehabilitated  the square timbered shaft in H2 2024. In 2025 management decided to use  the shaft to move material. West Red Lake Gold ordered the needed hoist  components; the rope was delivered in August while the skip and scrolls  are expected in October.
 
 
 
 The  first of these requirements – underground waste storage – is now  operational. The shaft is expected to start operating in November and  the equipment should be delivered and operational at approximately the  same time.Final equipment deliveries.  The mine expects to take delivery of another 42-tonne haul truck and  two 4-yard Komatsu scoops over the next two months, which will complete  the planned fleet of mining equipment.
 
 
 These achievements will create  operational stability at the Madsen mine. The 2026 detailed mine plan is  also expected before the end of the year, which will enable confident  guidance as part of a declaration of commercial production.
 
 “The  Madsen Mine remains on track towards commercial production,” states  Williams. “We are staying focused on a methodical approach to this ramp  up because developing a strong sustainable mine gives us the potential  to create more value in Red Lake. Such potential is very apparent in our  Rowan project, which we are advancing quickly so that its anticipated  production rate of 35,000 ounces adds to our Red Lake production profile  within a few years, and we see significant additional value potential  at Madsen as we test high-grade targets in and around the deposit and  unlock the deeper opportunity of this gold system.”
 
 Additional Information on Recent Financing
 
 In  connection with the Company’s bought deal public offering previously  disclosed on September 23, 2025, the Company raised an aggregate of  C$40,651,260 and the Company paid Raymond James Ltd., as lead  underwriter, a cash commission of $2,270,469.60.
 
 The  technical information presented in this news release has been reviewed  and approved by Will Robinson, P.Geo., Vice President of Exploration for  West Red Lake Gold and the Qualified Person for exploration at the West  Red Lake Project, and by Hayley Halsall-Whitney, P.Eng., Vice President  of Operations for West Red Lake Gold and the Qualified Person for  technical services at the West Red Lake Project, as defined by National  Instrument 43-101 - Standards of Disclosure for Mineral Projects.
 
 ABOUT WEST RED LAKE GOLD MINES
 
 West  Red Lake Gold Mines Ltd. is a gold mining company that is publicly  traded and focused on its flagship high-grade Madsen Gold Mine and the  associated 47 km2 highly prospective land package in the Red  Lake district of Ontario. The highly productive Red Lake Gold District  of Northwest Ontario, Canada has yielded over 30 million ounces of gold  from high-grade zones and hosts some of the world's richest gold  deposits. WRLG also owns the Rowan Property in Red Lake, which hosts a  small, high-grade deposit that West Red Lake Gold is looking to advance  towards production.
 
 
 
  
 figure 4  ON BEHALF OF WEST RED LAKE GOLD MINES LTD.
 
 “Shane Williams”
 
 Shane Williams
 
 President & Chief Executive Officer
 
 FOR FURTHER INFORMATION, PLEASE CONTACT:
 
 Gwen Preston
 
 Vice President Communications
 
 Tel: (604) 609-6132
 
 Email:  investors@wrlgold.com or visit the Company’s website at globenewswire.com
 
 Neither  the TSX Venture Exchange nor its Regulation Services Provider (as that  term is defined in the policies of the TSX Venture Exchange) accepts  responsibility for the adequacy or accuracy of this release.
 
 CAUTIONARY STATEMENT AND FORWARD-LOOKING INFORMATION
 
 Certain  statements contained in this news release may constitute  “forward-looking information” within the meaning of applicable  securities laws. Forward-looking information generally can be identified  by words such as “anticipate”, “expect”, “estimate”, “forecast”,  “planned”, and similar expressions suggesting future outcomes or events.  Forward-looking information is based on current expectations of  management; however, it is subject to known and unknown risks,  uncertainties and other factors that may cause actual results to differ  materially from the forward-looking information in this news release.
 
 Forward-looking  information involves numerous risks and uncertainties and actual  results might differ materially from results suggested in any  forward-looking information. These risks and uncertainties include,  among other things, market volatility; the state of the financial  markets for the Company’s securities; fluctuations in commodity prices;  and changes in the Company’s business plans. Forward-looking information  is based on a number of key expectations and assumptions, including  without limitation, that the Company will continue with its stated  business objectives and its ability to raise additional capital to  proceed. Although management of the Company has attempted to identify  important factors that could cause actual results to differ materially  from those contained in forward-looking information, there may be other  factors that cause results not to be as anticipated, estimated or  intended. There can be no assurance that such forward-looking  information will prove to be accurate, as actual results and future  events could differ materially from those anticipated in such  forward-looking information. Accordingly, readers should not place undue  reliance on forward-looking information. Readers are cautioned that  reliance on such information may not be appropriate for other purposes.  Additional information about risks and uncertainties is contained in the  Company’s management’s discussion and analysis for the year ended  December 31, 2024, and the Company’s annual information form for the  year ended December 31, 2024, copies of which are available on SEDAR+ at  www.sedarplus.ca.
 
 The  forward-looking information contained herein is expressly qualified in  its entirety by this cautionary statement. Forward-looking information  reflects management’s current beliefs and is based on information  currently available to the Company. The forward-looking information is  made as of the date of this news release and the Company assumes no  obligation to update or revise such information to reflect new events or  circumstances, except as may be required by applicable law.
 
 For  more information on the Company, investors should review the Company’s  continuous disclosure filings that are available on SEDAR+ at  www.sedarplus.ca.
 
 Photos accompanying this announcement are available at
 
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 
 globenewswire.com
 
 
 
 |